A New Tradition in EVM Analysis!
Presentation Outline
In the 1900s.....
-
Refresher on
Earned Value Concepts
How earned value management is different
from cost reports and schedule updates.
Planned
Value
Performance
Measurement
Baseline (PMB)
Time
(C) 2009 Management Technologies
Planned
Value
Earned
Value
Time
Value
($ or hours)
Planned
Value
Actual
Costs
Earned
Value
Time
10
11
Analyzing Variances
From the Plan
Now
Value
($ or hours)
Schedule
Variance
Planned
Value
Time
Actual
Costs
Cost
Variance
Earned
Value
12
CPI =
EV
WORK _ DONE
1000 hrs
=
=
= 0.66
AC COST _ OF _ WORK _ DONE 1500 hrs
(C) 2009 Management Technologies
13
SPI $ =
EV
WORK _ DONE
1200 hrs
=
=
= 1 .2
PV WORK _ PLANNED 1000 hrs
(C) 2009 Management Technologies
14
15
16
Project schedule
improvement or
false indications
due to SPI?
1.1
SPI$ 1.0
3 months
TIME
SPI$
.9
.8
Original
Project
Finish
Actual
Project
Finish
17
Simple extrapolation
Final cost = cost of work done + (work left/past
performance)
Assumes future performance is same as past
(generally true)
EAC (CPI) = AC+(BAC-EV)/CPI = BAC/CPI
EAC (CPI, SPI) = AC+(BAC-EV)/(CPI*SPI)
19
Budget
or
When work
was to be
done (PV)!
staff hours
Work done
(EV)
6 months
Time
10 months
Actual Time (AT) i.e., NOW
Earned Schedule (ES) i.e.,
How much have you accomplished and
when were supposed to?
20
21
EXAMPLES:
6
(C) 2009 Management Technologies
10
22
Budget
Spent
Cost
Variance
(CV)
BAC
Planned work
(PV)
Funds spent
(AC)
Schedule
Variance (SV$)
Work done
(EV)
Work
Done
Planned Duration (PD)
Actual Time (AT)
Earned Schedule (ES)
(C) 2009 Management Technologies
Schedule
Variance (SVt)
Planned
Completion
Date
23
EAC =
BAC
CPI
SV$ = EV PV
New
SPI t =
ED =
ES
AT
PD
SPI t
CV = EV AC
24
Comprehensive Example
Putting all the pieces together.
25
Comprehensive Example
Planned
Budget
(BAC)
Budget
Spent
Cost
Variance
(CV)
12 BAC
Planned work
(PV)
7 PV
Funds spent
(AC)
5 AC
4 EV
Work done
(EV)
Work
Done
6 ES
10 AT
18 PD
Schedule
Variance (SVt)
26
Comparing EV and
ES Schedule Analysis
Traditional
New
EV $4
SPI $ =
=
= 0.57
PV $7
ES
6months
SPI t =
=
= 0.6
AT 10months
SV$ = EV PV = $4 $7 = $3
ED =
PD 18months
=
= 30months
SPI t
0.6
27
1/31/06 2/28/06 3/31/06 4/30/06 5/31/06 6/30/06 7/31/06 8/31/06 9/30/06 10/31/06
PV - CUMULATIVE (BCWS)
1800
3500
5000
6100
8400
10300
12500
12900
14200
16800
EV - CUMULATIVE (BCWP)
680
1900
4340
5600
6700
9100
11230
12450
12650
12750
AC - CUMULATIVE (ACWP)
500
1800
4400
5725
7025
9025
12525
14025
15025
16025
8/19/06
1/13/06
11
30
73
103
125
159
191
208
221
228
28
56
87
117
148
178
209
240
270
301
351
332
289
259
237
203
171
154
141
134
TIME REMAINING
334
306
275
245
214
184
153
122
92
61
-17
-26
-14
-14
-23
-19
-18
-32
-49
-73
SPI(t)
0.37
0.52
0.84
0.88
0.84
0.89
0.91
0.86
0.81
0.75
28
29
Research Results
Does Earned Schedule analysis really work?
30
Empirical Evidence
(Henderson)
Findings derived from a small set of real life project
Commercial IT Infrastructure Expansion Project Phase 1
data
Earned Schedule, Independent Estimate At Completion (time) - IEAC(t)
as at Project Completion: Week Starting 15th July xx
Planned Schedule
IEAC(t) PD/SPI(t)
40
35
30
Duration (Weeks)
25
20
15
10
5
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Henderson, K., 2003, Earned schedule: a breakthrough extension to earned value theory? A retrospective
analysis of real project data, The Measurable News, Summer 2003, 21, 13-17
31
Academic Research
(Vanhoucke)
32
Research Process
33
34
Vanhoucke M., Vandevoorde St., A Simulation and Evaluation of Earned Value Metrics to Forecast
the Project Duration, Ghent University, Working Paper 2005/312, June 2005
35
36
USAF
Lockheed Martin
Belgium
Management Technologies (education, processes, tools)
(C) 2009 Management Technologies
37
USAF Planning
38
Previously
- EVM was great at cost management
- EVM was ok at schedule management, sometimes
Now
- EVM can address both cost and schedule well
- EVM can estimate
Cost at completion
Completion date!
- SPIt can record project outcome in lessons learned
39
Credit to Discoverers,
Advocates, & Researchers
- Henderson Kym, Earned Schedule: A Breakthrough Extension
to Earned Value Theory? A Retrospective Analysis of Real
Project Data,The Measurable News, Summer 2003
- Robert Handshuh, New Concept in Earned Value - Earned
Schedule, PMI Southeast Regional Conference USA, June
2005
- Walt Lipke & Kym Henderson, Earned Schedule Status
Update and Early Adaptor Applications Feedback, 17th IPMC
November 2005
- Vandevoorde St., Vanhoucke M., A Comparison of different
project duration forecasting methods using earned value
metrics, Ghent University, working paper 2005/312, June 2005
Published in International Journal of Project Management
(C) 2009 Management Technologies
40
Conclusions
So What?
41
42
43
44
Seminal Documents
45
Other References
46
One-Stop Shopping
www.earnedschedule.com
www.mgmt-technologies.com
The Earned Value Management Maturity Model,
published by Management Concepts, Vienna VA
47
In Closing