Professional Documents
Culture Documents
Associates v. Gammino, Inc., 1st Cir. (1993)
Associates v. Gammino, Inc., 1st Cir. (1993)
BOUDIN,
Circuit
Judge.
This action
arises
out
of
______________
efforts
Plaza
of
to develop
a shopping
complex
real
estate
developer
known as
Bald Hill
Anthony DelVicario,
who
was
("Commercial").
Tilcon
Gammino, Inc.
do
certain
construction
project, primarily
with
Tilcon's
work in
connection
grading.
approached
with
the
DelVicario,
Lechmere,
Inc.
that operates a
chain
project
the real
was
to be located, and
the
property
Commercial
needed
for
the development.
responsible
construction
for
of
the
the
store would be
built.
the
site-clearing
work
underlying
and
the
In consideration,
Lechmere
"footprint"
to
its store
and
estate on which
would
the
entire
Lechmere's
Lechmere agreed to
general contractor
-2-
for the
site-clearing
-2-
work.
dated February
of
the work
estimated total
be performed
by
Tilcon and
supervisor
of
the
project
and
contained
Tilcon started
DelVicario was
directed
the pad
could open
completed by
that September in
March 15,
Tilcon's
Lechmere
1985, so
an
had
its store
holiday shopping
season.
insisted
Tilcon's
staff to
work
overtime
and
necessitating
extra
site that
contained in the
went
beyond the
description
of the
job
to
Tilcon's compensation.
Tilcon
claimed that
it was
entitled
to
additional
compensation for
performed at DelVicario's
it believed
price"
mechanic's
been paid
bills
by
it
a "guaranteed maximum
in full--and
submitted
"extras"
Commercial disagreed--
and had
final three
direction.
the
refused to
Tilcon.
Tilcon
pay the
filed
-3-3-
to the
Rhode Island
statute, Commercial
posted a
$1.2 million bond to release the lien, and the action proceed
in rem against the bond.1
__ ___
Following
a seven-day
found in favor of
found
that
contained
found
Tilcon
in the
Tilcon.
was
bench trial
In
the superior
court
court
not bound
original February
by
the
estimated price
8 contract.
The court
basis for
was entitled to
numerous
Finally,
the court
compensation on a
"extras" performed
"cost-
at the
site,
proceeding only
period prior
"lien period").
for
to notice
work performed
of the lien
within the
(the so-called
was
____________________
1The mechanic's lien statute provides that respondents
can secure the release of a lien by depositing with the
registry of the court "cash equal to the total amount of the
accounts and demands of all persons claiming liens" or a
surety bond in that amount in lieu of cash. R.I. Gen. Laws
34-28-17. In this case, Commercial deposited a $1.2 million
bond with the registry and, apparently without any objection
from Tilcon as to the amount, the lien was discharged.
-4-4-
period,
but held
amounts in
that
its judgment.
it had
The
no
power to
court left it
include
these
to Tilcon
to
The
Rhode
Island
court
entered
judgment
against
which represented
compensation due
Tilcon for work at the Bald Hill site during the 120-day lien
period.
Tilcon,
million,
the
release the
judgment
however, was
amount of
able
the bond
to collect
that
decision was
Tilcon's
Supreme Court.
had been
$1.2
posted to
recovery.
affirmed in
only
The
all respects
superior
by the
court's
Rhode Island
own
removed
diversity
Island
arising out
the
of
action
this separate
Superior Court
of the
to
Bald
federal
citizenship.
It
action against
seeking damages
Hill project.
district
also
proceeding,
court
filed a
of
Tilcon
based
on
counterclaim
not
recoverable
in
the
lien
action--the
deficiency
-5-5-
summary judgment
on
its counterclaim
in this
action.
as
DelVicario bound
a matter
of
Commercial to
that
Lechmere
that
a series
Tilcon was
under those
fact
owed
of oral
contracts with
specific amounts
contracts.
Lechmere
Tilcon, and
for work
and
performed
Commercial and
matter
superior
of law
for the
court's judgment
$129,207 discrepancy
and
the $1.2
between the
million bond,2
as
by the Rhode
court
that
established that
work
performed
concluded
the
Rhode
that
the
findings but
to its judgment.
Island
and Lechmere
decision
Thus, the
conclusively
lien period.
Rhode Island
But
the district
decision
did
not
deficiency, nor
____________________
2Tilcon claims that it is entitled to recover in this
case the entire $1,329,207 amount of the Rhode Island
judgment. But it is undisputed that Tilcon recovered $1.2
million by executing on the bond, and Tilcon does not explain
why it is entitled to more than the $129,207 discrepancy for
the lien period.
-6-6-
did
it
establish Tilcon's
entitlement to
claims of
the
to
the lien
period.
stipulations.
court
Pursuant
instructed
Tilcon's
now
limited
The dispute
to its
was further
certain
$129,207 for
and
by Tilcon prior
prior ruling,
that
having been
to Commercial's
the jury
entitlement to
proceeded to trial.
case was
Lechmere's liability, if
The case
compensation for
narrowed by
the district
facts, primarily,
work done
during the
be reconsidered.
The court
therefore precluded
deficiency would
be imposed upon
whichever of
the
defendants was
held
liable at
trial for
the pre-lien
work.
At
trial, Tilcon
that Commercial
and
introduced
Lechmere
were
evidence seeking
liable
for
law
for Lechmere
leaving only
the court's
to all
Tilcon against
The jury
At the close
a matter of
of Tilcon's
this opinion.
additional
granted judgment as
with respect
to show
claims,
discussed later in
favor of
-7-7-
added
to this
amount
the $129,207
deficiency between
the
made a
parties, and
in favor
of Tilcon
Tilcon now
appeals.
It argues
Island
as well as against
partnership
is a
defunct
in this appeal;
or insolvent
explain
why it is important
against
Lechmere.
estoppel made
also
from Commercial.
if the limited
might
obtain a judgment
argues
that
collateral
Commercial
entity, that
to Tilcon to
Tilcon
Lechmere and
$600,000 in work
Commercial.
for some
that it
aside,
judgment for
by considering
the collateral
estoppel issue
Commercial.
"Federal courts
are bound by
Cir. 1986);
-8-8-
state law on
Carillo v. Brown,
________________
see also 28
___ ____
U.S.C.
1738;
Cir. 1984).
Rhode Island
effect
that the
Rhode Island
the same
preclusive
courts themselves
would give
that decision.
In
order for
the
doctrine of
collateral estoppel
apply under
satisfied:
there must be
proceeding must
merits;
and the
sought must
party against
be the same as
Like
decided."
whom collateral
estoppel is
the party in
A.2d 120,
122
the
the identity-of-
crucial one in
own:
third, the
sought to
decided in the
have been
Id. at 123.
__
In addition,
prevailing
latitude
judgment on
litigated; and
final
or in privity with
prior proceeding;
in a
requirements must be
an identity of
have resulted
to
Rhode Island
approach,
in
applying
"allow
the
courts, consistent
themselves
rule [of
good
collateral
with the
deal
of
estoppel],
Hill v.
_______
Bain,
____
15
R.I.
Commissioner,
____________
75,
23 A.
880 F.2d
44
260,
(1885);
see
___
264 (10th
also Klein v.
____ _________
Cir. 1989)
("Trial
-9-9-
courts
are granted
broad discretion
collateral estoppel.").
We
in
below, as
the district
court
in the
application of
was sitting
in
this
Superior
agent
Court's finding
of Lechmere
contracts
in the
court stated
payment
authority
to Tilcon,
for
and
such bound
Lechmere to
is
behalf
in making
within the
of
as an
the oral
based on
was "acting
on
was acting
Tilcon's argument
that DelVicario,
court
that DelVicario
and as
with Tilcon.
single paragraph
the
in which
assurances of
scope of
Commercial
[his]
and
modifications.
We agree with
the district
court that
the
Tilcon was
not one that "must necessarily have been decided" in the lien
proceeding, and
therefore
is
not
entitled
to
preclusive
context that
an issue was
not only
See
___
actually
Restatement
to the judgment").
collateral
although it
issue,
may
be
the
subject
of
-10-10-
finding, is
and the
___
litigate
Wright,
parties
may well
have
only limited
incentive
to
See
___
oral or
written contract
landowner.
1(a) (emphasis
added).3
superior court
suit (or
34-28-
liability of
that
Tilcon's
Lechmere's request.
work
on
the
A "request,"
property
in the
was
of course, is
and the
done
a far
at
cry
____________________
3Deleting
irrelevant
language,
the
mechanic's lien statute provides as follows:
Rhode
Island
from
contract.
existence
and
To
terms
be
of
sure,
the
findings
contract
regarding
governing
the
Tilcon's
the
amount of
contract.
185
the
lien is
dependent
upon the
underlying
A. 136
Commercial
(1936).
alone,
irrelevant.
But
whether
or Commercial
that contract
and Lechmere
was
with
jointly, was
not rest
If a factual issue
prior proceeding
and were
decision,
preclusion might
hindsight
it
could be
determination is
single
focus of
the court's
appropriate even
the
not inherently
issue was,
After
"if an inquiry
if in
in some
all, a
untrustworthy just
principle that
the
to the outcome.
the
well be
shown that
parsing of
different,
matters had
preclusion
supra,
_____
is
denied."
517 (1925)).
The Rhode Island
was an
agent of
Lechmere only at
that DelVicario
one point in
its 28-page
We
do not think it is at
all clear
superior
court
meant
to
determine
that
DelVicario
was
Tilcon.5
We
"finding" was
need
clarity in
of three
for a
considerations:
finding of
the supposed
such an
the
lack of
agency, the
any
lack of
earlier, explicit
____________________
5The later sentence relied upon by Tilcon occurs in the
context of a discussion rejecting Commercial's claim that
"extras"
authorized by DelVicario did not enlarge the
liability of Commercial under the written contract; and it is
__________
at least possible that the court meant no more than that
DelVicario spoke for Commercial and that Lechmere, having
contracted
with
Commercial,
was stuck
with
limited
responsibility for DelVicario's extras that flows from the
mechanic's lien statute.
-13-13-
Tilcon also
findings as
owed Tilcon
Bald
Hill
to the amount
site
prior to
the
start
the lien
at the
period.
Although
it declined
no power under
the mechanics lien statute to award compensation for the prelien work.
Accordingly,
their
to rescue
these findings by
arguing that
has promised
that
can
mechanic's lien
be
to do a
collected
statute is
job for
for
extent that a
a fixed
that
limited to the
job
Lechmere
price
146-47.
the
Therefore, Commercial
and
agreed
recovery.
done
A. at
under
contract maximum
sum, the
prior
to by
To
to
Tilcon
represents
lien
period
analyzed.
-14-14-
an outer
says Tilcon,
had
to
be
limit
of
the extras
individually
This argument
Rhode
is imaginative
contract
The
price
relied
upon
preliminary
estimate and that the later binding price was higher, covered
only work done after
in
the contract
and not
work specified
numerous extras.
The guaranteed
decision,
defense.
Indeed, as already
noted, the
the
Superior
end,
it is
not
He
why
the Rhode
Island
lien items.
the
clear
judge
in the
reasoning urged by
the requisites
case
It is up
followed
the line
of
to Tilcon to establish
lien
Tilcon.
to the
4420 at 185,
and in
This
is
enough
for our
liability
purposes
would not
be
although we
note that
affected since--as
Lechmere's
we shall
see--
-15-15-
not prevent
in
this case
that Lechmere
in
estoppel
to prove
fact entered
at
into a
of Tilcon's
matter
claims.
case the
of law
in
Tilcon
district court
favor of
says this
Lechmere
was error
entered judgment as
on each
as to
of
Tilcon's
three claims-enrichment6--
oral assurances
to
Tilcon that
performed
series
it
at the
would
site,
be
for
and therefore
of oral agreements.
the
"extra"
work
bound Lechmere
to a
paid
only
review
is
Rich. Co.,
_________
plenary.
961
convinced that
F.2d 294,
there was
298
(1st
Cir. 1992).
insufficient evidence to
We
are
permit a
____________________
6Tilcon's remaining claims were fraud, constructive
trust, and violation of the Racketeer Influenced and Corrupt
Organizations Act ("RICO"), 18 U.S.C.
1961 et seq. The
__ ___
RICO count was dismissed prior to trial, and judgment as a
matter of law was entered on the fraud and constructive trust
counts. Tilcon does not pursue these claims on appeal.
-16-16-
reasonable
jury
to find
that
DelVicario was
an
agent of
apparent authority.
A.2d
523,
527
(R.I. 1988)
(adopting
Restatement (Second)
of Agency).
The
formulation
of
There
was
is to
no suggestion
act on
at trial
as
Lechmere's
project.
agent
Accordingly,
behalf of
of any
the former.
actual agreement
with respect
Tilcon
to
the
presses only
Bald
theory
Hill
of
apparent authority.
Apparent
authority
manifestation of such
"arises
from
authority to the
the
principal's
the
agent contracts."
in a way
that leads a
agent is authorized
authorized
to
enter
third party to
to act on the
into
contractual
arrangements
for
act on behalf
-17-17-
of the principal
267.
instructions
statement would
that
not permit
the
job
the
Commercial's man
site.
But
a reasonable person
was
on
that
to conclude
payment for
work were
opposite interpretation:
site-clearing
work
DelVicario, and
to
that Lechmere
Commercial
and
own hands
out of it.
have
motivated
been
timetable
and
Commercial.
actions
other
Tilcon
by Lechmere
in
directing Tilcon's
requirements
points
to no
affirming
imposed
other
actions
by
by Lechmere
evidence
a
on
of any
DelVicario's authority,
and
addition,
even
if
Tilcon in
fact
believed
that
DelVicario
represented Lechmere,7
no reasonable
jury could
____________________
7In fact, the trial testimony was quite equivocal as to
whether Tilcon actually believed that DelVicario represented
Lechmere. Only two witnesses testified for Tilcon: its vice
president, Thomas Gammino; and its foreman at the Bald Hill
site, Robert Pion.
Both witnesses described DelVicario as a
-18-18-
belief justifiable.
At the
outset of
the
Lechmere.
or
sought
Lechmere.
check
to
enter
into
Before beginning
on Commercial,
written
never entered
contract
but made
no such
with
a credit
inquiries regarding
Lechmere.
Nor
began.
was
submitted
a more prominent
to
Commercial,
not to
Lechmere.
Tilcon
submitted all
Lechmere
was never
its bills
to Commercial
involved in
the billing
for payment.
process, never
unpaid,
compensation.
in
a larger
until
Tilcon
did
Lechmere was
not
to
Lechmere
project developed
litigation, and
look
the need
three bills
anchor stores
by Commercial.
for a
for
It
was not
deeper pocket,
that
We
also
agree
with
the
district
judgment for
Lechmere on
recover on a
court's
entry
claim.
of
To
benefit on
the
defendant
"in
inequitable for
payment to
such
circumstances
that
be
589 A.2d
1202
equitable
(R.I. 1991).
for the
would
value thereof."
1201,
the plaintiff
it
This
under state
district court's
claim
was unjust,"
and therefore
law was
We share the
concern ourselves
done by Tilcon
participants in
other stores
the
project--including Commercial
The district
the
Tilcon offered no
____________________
8Courts
have
disagreed whether
unjust enrichment
presents a question of fact that is reviewed under a clearly
erroneous standard, or a question of law reviewed de novo.
__ ____
Compare Commodity Futures Trading Comm'n v. Heritage Capital
_______ _____________________________________________________
Advisory Servs., Ltd., 823 F.2d 171, 172 (7th Cir. 1987),
_____________________
with In re Estate of Zent, 459 N.W.2d 795, 798 (N.D. 1990).
____ _____________________
Needless to say, such an all-or-nothing choice is not
compelled.
-20-20-
for
the
site-clearing
work.
Tilcon
offered
no
the
relationship
throughout the
between
Finally,
Tilcon
the court
and
Lechmere
based on the
many of
compensation from
done at
the site.
Tilcon
ruling
done
suggests
that the
precluded the
during
opportunity
introduction of
the lien
to
court's
period
show
that
and
work
work
done
during
any evidence
during
the lien
period
also do not
was
that the
was
order
the
period
We
fraud
of
that
beneficial to Lechmere.
district court
of work
deprived Tilcon
done
collateral estoppel
to
uniquely
agree with
in
enrichment
theory.
Rather,
consistent
court
on
proof of
necessary
the
recover
Tilcon
merely
an
unjust
observed,
a benefit
See
___
R&B
___
claim, this is a
-21-21-
close cousin
to the
Historically,
equitable remedy of
district
a party to
law) promise to
Contracts,
_________
court
directed against
made clear
of a formal contract
Farnsworth,
unjust enrichment.
might not be
present.
2.20 at
103 (2d
ed. 1990).
that,
even if
this
of the
See
___
The
claim were
direct a verdict
by the court in
In
its brief in
assimilate its
stressing
as
quantum meruit
______________
to
both
chooses instead to
claim to its
claims
the
same
contract claim,
facts
concerning
such that
contract.
Tilcon can
of quasi-contract claims
fairly stress
this
affinity with
between Lechmere
imagined by
and
Tilcon.
Tilcon,
either real
See generally
___ _________
or
Farnsworth,
____________________
9The district court believed with considerable basis
that in Tilcon's complaint the quantum meruit claim, as well
______________
as the contract claim, had been directed solely against
Commercial; but in each case the district court ruled in the
alternative that the claim lacked merit so we do not discuss
the pleading issue further.
-22-22-
supra, at 107 ("Nor can a party that has made a contract with
_____
another
generally
restitution
under the
from a
disregard
third
the
person for
contract
and
performance
claim
rendered
It
may well be that Tilcon has not recovered all that it is due,
possibly because of default by the
contracted
Tilcon's
own
decision.
There
-23-
no
error in
the
-23-