Professional Documents
Culture Documents
USA For U V., 1st Cir. (1993)
USA For U V., 1st Cir. (1993)
____________________
No. 93-1541
UNITED STATES OF AMERICA, for
u/b/o LUIS A. CABRERA, S.E.
A SPECIAL PARTNERSHIP,
Plaintiff, Appellee,
v.
SUN ENGINEERING ENTERPRISES, INC.,
AND CNA CASUALTY OF PUERTO RICO,
Defendants, Appellants.
____________________
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF PUERTO RICO
[Hon. Jos
_____________________
____________________
____________________
Per Curiam.
__________
the Miller
Act, 40 U.S.C.
270a-f (1986),
("Cabrera"),
subcontractor,
in the name
benefit of Luis A.
against
its
surety,
CNA
Casualty
After
of
Puerto Rico
Cabrera, S.E.
Sun
Engineering
contractor, and
("CNA").
of the
In
the
a subcontract
the District of
Cabrera
district court
improperly amended
the
pre-trial order
at
findings of
fact.
For the
evidence to support
reasons stated
the
herein, we
affirm.
I.
I.
BACKGROUND
BACKGROUND
Cabrera.
Financial Corp.,
________________
Engineering
is
contractor for
See
___
959
F.2d
345,
construction
a federal project
346 (1st
company
Cir.
which
1992).
was
the
Sun
prime
("the Project").
East West
__________
Mr.
On
detailed, item by item, the work which the Project blueprints and
specifications required with respect to supplying
and installing
-2-
the cost
of the work
to be
The
$106,707.35.1
precise terms of
the quotation.
to
Cabrera
Although
accepting
the
Cabrera's
parties had
in the quotation,
price of
$80,000, an absolute
upon.
the work
"estimated" contract
quotation.
changes to
and a reduced
Rather, Cabrera
21, l989
negotiated some
specified
agreed
December
Sun Engineering
was never
informally
on the work
Cabrera
original
perform
contract.
additional work
This
work involved
Cabrera to
installing.
Cabrera
not
encompassed
floor underlays.
by the
Mr.
commenced work.
verbally requested
it was
on the Project
by June 5, l99l.
totalling $60,726.14.
payments to Cabrera
____________________
balance of $44,769.25.
Cabrera
then
Engineering claimed
$80,000,
and
filed
therefore,
$l9,273.86.
suit.
Sun
Sun
As
its
Engineering
Engineering
defense,
also
only
claimed
Sun
price of
owed
Cabrera
that
Cabrera
into an
contract,
work
contract.
it had
performed
with
to be paid $105,495.39
on the
Project.
In accordance
The court
the
for the
found that
Because Sun
court entered
Engineering
then
Engineering makes
three arguments
contends
by allowing
that 1)
filed
this
appeal.
on appeal.
a modification
Sun
Sun
Engineering
of the
pre-trial
with
respect
to
contradicted a stipulated
the
at
trial
did
of
the
contract
cost
not
that
theory of
the
district
court's
was
not
and
responsible
for
Project
delays.
Sun
II.
II.
In the final
that "the agreed
trial, Cabrera
$106,707.35
pre-trial order,
price on said
exhibit.
introduction of this
because
relevant to the
the
different price
The
and permitted
court
believed
objected to
be the terms of
for
the
for the
court
Cabrera to
that
At
l989 quotation
Engineering
parties intended to
Sun Engineering
Sun
stipulation.
Engineering's objection
exhibit
December 21,
suggested a
that
parties stipulated
the
introduced its
as an
contradicted
the
contract,
overruled
Sun
introduce the
quotation
was
the
the contract.
On appeal,
Civ. P.
trial and
permitting
Cabrera to
introduce evidence
which contradicted
trial court
and purpose
has broad
of the
pre-trial
discretion
to preserve
order.
Roland M.
_________
the
v.
l990), cert.
_____
____________________
2
Federal Rule of
part:
in pertinent
minimal interference
with a
trial court's
interpretation of
that interpretation.
l988); Geremia v.
_______
653
(1990).
"Unless
there is
1527, at 279-286
manifest injustice
or the
district
court's ruling
will not
be disturbed.
Nickerson
_________
v. G.D.
____
Searle & Co., 900 F.2d 412, 422 (lst Cir. l990); Ram rez Pomales,
____________
_______________
839 F.2d at 3.
conference the
for trial.
the action
shall formulate
trial conference, an
action,
participants
Fed. R. Civ. P.
The interpretation of
responsibility of the
trial court.
covers any
might be
of the
embraced by
possible legal
its
language.
or factual
Geremia,
_______
theories that
653 F.2d
at
(quoting Rodr gues v. Ripley Indus., Inc., 507 F.2d 782, 787 (lst
_________
___________________
Cir. l974) (citing
Procedure
_________
6 C. Wright
-6-
Contrary to Sun
court
did not
amend the
order.
of
introduction
After
of
the
stipulation in the
also set out
theory
of the
entitled
to
performed.
Sun
Engineering
exhibit, the
court
the exhibit by
case.
be
paid
reviewed
The December
to
the
the factual
that the
with its
Pursuant to
on the
not an abuse
objected
introduction of
proposed to introduce
discretion.
court
Rather, the
the
basis
of
contract, Cabrera
the
work it
was
actually
While the factual stipulation did provide that the agreed cost of
the contract was
defy
logic to
Cabrera stipulated
Rather,
interpretation
the
of the
court
found
stipulation
it would simply
that the
absolute
the
was that
only
reasonable
it referred
to an
agreed "estimated"
within
contract cost
its discretion in
of $80,000.
The court
acted
and pre-
trial order in this manner, and we will not disturb its ruling.
III.
III.
Sun
regulations
Engineering
which
argues
purportedly
that
require
in
light
of
all
change
federal
orders
on
-7-
government
projects
insufficient
to
be
in
writing,
the
evidence
was
issued to Cabrera.
An
appellate
findings of fact
court
will
review a
district
court's
Dedham Water
____________
Co. v. Cumberland Farms Dairy, Inc., 972 F.2d 453, 457 (lst
___
____________________________
l992); Fed. R. Civ.
P. 52(a).3
when
court is
the reviewing
A
left
finding is clearly
with the
been committed.
if certain facts
erroneous
definite and
firm
to determine
Cir.
possess, or
which require
lack, legal
of law,
findings.
Id. at 990-91.
___
The
we
record
will give
effect to
supports
the
testified
the trial's
district
court's
issued to Cabrera.
that
after
Cabrera
courts
factual
Mr. Cabrera
submitted
the
____________________
3
Federal Rule of
part:
in pertinent
original
quotation to
proposed
changes to the
quotation.
Mr.
detailing
the work
Cabrera
undisputed
testimony
that after
the
contract,
respect
in the
El as also
parties
entered
contract with
and Mr. El as
to
partitions,
into
that
the
original
respect to
both testified
to do additional
was
floor
that Mr.
work with
aware
of
this
they
requirement,
were
of
however, that
government projects
the contrary,
requirement.4
Part
addresses
preparing
and
et
__
43
orders to
43.201 (1992)
of the
government
processing
seq.
____
change
There
48 C.F.R.
no
(1992).
Code
The
policies
contract
contention to
Federal
and
procedures
modifications.
regulations
Regulations
48
for
C.F.R.
are directed
____________________
4
is
subcontractors on
48 C.F.R.
generally
legal consequence.
to be legally binding.
43.000
no
to
government contracting
directly
with them.
officers and
Section 43.20l
when issuing a
Generally, the
between
the
project.
such
as
regulatory
is specifically directed at
change order to
relationship covered
the prime
by the
We have
regulation is
contractor on
subcontractors,
contractor.
contract
officer and
The
who contract
which
purports
a government
solely
requirement
that
to
with the
prime
other statutory or
control
the
prime
prime
contractor/subcontractor
relationship
is
See,
___
Arundel Corp.,
_____________
found
no oral
contractual
contracting officer, in
____________________
5
In its brief, Sun Engineering points to the testimony of
Mr. El as and Mr. Delgado, an architect who worked for the Post
Office, who both stated that change orders were generally
accomplished through written directives.
Their testimony,
however, also referred to the relationship between the government
and the prime contractor.
-10-
order to
be
valid.
those orders.
finding is
found that
in accord with
the general
See
___
DELAY CLAIM
DELAY CLAIM
contends
that
the
district
court's
by
the record.
We
disagree
Cabrera completed
after the
and find
findings.
is
that
the
Mr. Cabrera,
Mr.
on the Project.
There was
scheduled completion
date of the
in its work
Project.
With the
any
financial
testified
penalty
that
delays which
conflicting
evidence
Sun
this "delay"
translated
Sun
Engineering.
While
to
Engineering was
were in fact
testimony to
solely responsible
credit Mr.
that
into
Mr.
any
Jim nez
financially
penalized for
El as offered
the effect
that
Sun Engineering
was
refused to
the court's
-11-
DOUBLE COSTS
V.
Because
DOUBLE COSTS
appeal, we
a court
of
frivolous, it may
to the
a frivolous
appeals
996
frivolous if
the
that
appellee."
New Jersey,
__________
shall determine
an appeal
or double costs
Id.
___
17 (lst
Cir. l993).
was obvious"
or
the
An appeal
arguments
success."
is
are
and their attorney should have been aware that the appeal
chance of
is
v.
had no
Engineering's
There is no
legal
be legally binding.
the
judge's factual
trial
reasonable
findings,
and there
had to be in
amply supports
are
simply no
-12-