Professional Documents
Culture Documents
Hodgson & Sons, Inc. v. FERC, 1st Cir. (1995)
Hodgson & Sons, Inc. v. FERC, 1st Cir. (1995)
on brief
Petitioner, Thomas
respondent,
the
Federal
the
operation
plant (China
Energy
of Hodgson's
____________________
Commission
Section 23(b) of
Regulatory
China
Mill hydroelectric
licensing jurisdiction of
Act (FPA)21 pursuant
to
1.
Section 23(b) of the original Federal Power Act, ch.
285,
23(b), 41 Stat. 1075 (1920) has been amended and
codified under 16 U.S.C.
817(1) (1988) ("Projects not
affecting navigable waters; necessity for Federal license,
permit or right-of-way"). It provides:
Any person,
association, corporation,
State,
or municipality
intending to
construct a dam or other project works
across, along, over, or in any stream or
part thereof, other than those defined in
this chapter as navigable waters, and
over which
Congress has jurisdiction
under its authority to regulate commerce
with foreign nations
and among
the
several
States
shall
before
such
construction file declaration of such
intention with the Commission, whereupon
the Commission
shall cause immediate
investigation
of
such
proposed
construction to be made, and if upon
investigation it shall find that the
interests
of
interstate or
foreign
commerce would be
affected by
such
proposed
construction,
such
person,
association,
corporation,
State
or
municipality
shall
not
construct,
maintain, or operate such dam or other
project works until it shall have applied
for and shall have received a license
under the provisions of this chapter. If
the Commission shall not so find, and if
no public lands or
reservations are
affected,
permission
is granted
to
construct such dam or other project works
in such stream upon compliance with State
-22
FERC's "post-1935
purposes of
construction" rule.
Section
23(b), shutting
more.
operating
until
Hodgson,
China Mill
its use
on
the
after
down
hydroelectric
FERC
post-1935 construction
other hand,
maintaining it
became profitable,
claims
over the
does not
amount
license were
After reviewing
pertinent
unreasonable.
case
law,
we conclude
that
that
years
to such
in the
FERC
erred in
its
China Mill
dam
was constructed
in the
late
diversion canal,
installed
prior
hydromechanical
to 1900.
to hydroelectric
was
power
which were
converted from
before 1914.
The
succession
continuously produced
configuration.
twelve
years
Power
laws.
owners,
starting in
____________________
of
1969.
The
China
Mill
its present
for approximately
parties
dispute the
and refer
to the
-33
nature of the
stoppage.
disaster initially
that the natural
the project's
stoppage
Petitioner
alleges that a
Respondent asserts
machinery and
was purely
generation,
the
uneconomical
for
that
economic.
production
China
the true
During the
of
Mill.
power
The
natural
got caught in
reason for
the
period of
non-
was
cost
of
apparently
purchasing
For reasons
in
to be
the production
stated, the
of
exact cause
electricity
does not
of the
affect
FERC's jurisdiction.
With the
federal enactment
the Limited
Electrical
of the Public
Energy
Producers Act
Mill.
Utility
In 1981 Hodgson
started to
(LEEPA),3
to produce
generate
power
at China
Mill and
FPA.
At
license and
sold power
Public Service
to the
licensed under
not object
voluntarily applied
to obtaining a
for one
in March,
1990.
____________________
2.
16 U.S.C.
824 et seq.
__ ___
3.
362-A:3.
-44
Hodgson's
In
spirit of
cooperation was
short lived.
that
included, inter
_____
alia, a
____
minimum water
flow of
fifty
plan,
improvements
and
aesthetic
Thomas Hodgson
to
the
60 F.E.R.C.
mill
building.
62,071 (1992)
______________________________
(Hodgson I).
__________
especially
Hodgson
challenging
objected
the fifty
to
these
conditions,
cfs requirement
which it
with the
FERC's
terms
and sought a
jurisdiction
and
63 F.E.R.C.
the project
that even if
had
license,
of
the
61,068
license.
(1993)
capacity of China
Mill had
been abandoned
and, therefore,
Hodgson
rehearing contesting
the terms
of its
the
the
Id. at
___
____________________
4.
Hodgson claims it has the right to withdraw a voluntary
license application. FERC does not dispute this; so we do
not address it.
-55
licensed.
Id. (emphasis
___
A second petition
of
license, petitioned
the terms
of the
this court
license.
We
for a
to
stay and
determined that
to stay or
-66
further
second
review
the order
until
FERC
considered Hodgson's
of license
terms).
In
the
second
petition
F.E.R.C.
for
rehearing,
61,202
Thomas
______
(1994) (Hodgson
_______
-77
have
jurisdiction
to
16
U.S.C.
. . . [to]
the
the
licensee . .
challenges FERC's
obtain a review of
of appeals for
. is located."
In its
such order in
requirements.
II.
II.
STANDARD OF REVIEW
STANDARD OF REVIEW
__________________
-88
On
v. F.E.R.C.,
________
993 F.2d
"[p]ure legal
937, 944
errors
467
U.S.
837
(1984).
When
a
challenge
to
an
agency
construction of a statutory provision,
fairly conceptualized, really centers on
the wisdom of the agency's policy, rather
than whether it is a reasonable choice
within a gap left open by Congress, the
challenge must fail.
Id. at 866.
___
reasons.
FERC misplaces
840.
But
of the
precedent.
two
reasonable construction
interpretation
judicial
FPA,
of the
not base
but rather
Chevron
_______
and
its
on
Clean Air
Act.
its order on
an
its reading
of
progeny
mandate
a statutory
Corp. v.
_____
interpretation."
-99
1401 (1992).
Because
FERC
did
not
base
its
jurisdiction
on
an
interpretation
its finding of
than we would
deference
to agency
interpretations does
is
construction
the final
and
must
authority
on
issues of
reject administrative
The
statutory
constructions
"The
Chevron,
_______
Supreme Court
ANALYSIS
ANALYSIS
________
hydroelectric facilities.
Originally, Section 23
projects5 on
nonnavigable waters6
could file
a declaration
____________________
5.
By "project" the FPA "means complete unit of improvement
or development, consisting of a power house, all water
conduits, all dams and appurtenant works and structures
. . . ." See 16 U.S.C
796(11).
___
-1010
Power Commission
then require
Id.
___
If
nonnavigable
a license
person
(FPC),
before
intending
Congress
licensing
amended
"intending to construct
______________________
nonnavigable
any construction
to
construct
The
could
continued.
project
on
Id. at 89.
___
the FPA
jurisdiction
1972).
FERC's predecessor,
FPC's
88 (2d Cir.
to
in 1935,
expanding the
require
that
persons
a dam
or other
project works"7
streams obtain a
license.
16
U.S.C.
on
817(1)
(emphasis
added).
"These
prospective view."
words quite
v. F.E.R.C.,
________
(4th
Co.
___
1977)
the
clearly indicate
455 F.2d at
857 F.2d
227, 229
construction
date
of
in
1935").
project
that
It
is
triggers
the
the
post-1935
licensing
____________________
6.
The FPA does not define "nonnavigable waters" but
"navigable waters," inter alia, "means those parts of . . .
_____ ____
bodies of water over which Congress has jurisdiction under
its authority to regulate commerce." See 16 U.S.C
796(8).
___
7.
By
"project works" the FPA
"means
structures of a project." 16 U.S.C.
796(12).
-1111
the
physical
All
translate
construction after
into
jurisdictional
1935 generally
work
or
however,
construction
the act.
is not
only maintains
1935,
under
restores a
557
not
the FPA
Supplemental building
post-1935 construction
project
F.2d
if the
to its
former
at 1315.
of substantial nature
jurisdiction
otherwise
over an
does
Nor
- . . .
do
confer
exempt facility."
Id.
___
at
1316.
An exception
has
been abandoned.
project,
rights.
an
After
owner
no
thirty
that such
years of
retained
its
retains
Although Aquenergy
_________
for
pre-1935
lack of
repairs
finding of abandonment.
operating
after more
in the
Id. at 229.
___
Because
rights.
it no longer
Id.
___
at
230.
licensing jurisdiction
and
than
which resulted
of a
creates an exception to
emphasized the
23(b)
and neglect
reduced to ruin.
pre-1935
a project
complete abandonment
abandonment occurred
owner in Aquenergy
_________
Section
the
longer
disuse
court
determined
the
to this
reconstruction
under
without
Section
23(b) the
the Commission's
project is not
jurisdiction if work
brought within
done in
the name
of
-1212
repair does
not so alter
alternative.
they urge
no longer
and FERC
rely
error; rather,
to
Hodgson
it is
that either
on
Puget Sound
___________
in the
an exception
The holding
and
controlling or even
relative magnitude of
relevant.
the work in
The
Puget
_____
to that
F.2d
at
230.
Accordingly,
unless
the
abandonment
Hodgson II
___________
of
power
and
III,
___
production
-1313
FERC
alone
ruled
and
that
the
without
construction
or
physical abandonment
FERC
gave
it jurisdiction
stated
its jurisdictional
resumed power
rationale
as
follows:
In determining whether abandonment has
occurred
for
purposes
of
section
23(b)(1), the question is not . . .
whether the site has
been literally
abandoned and left to fall into a state
of disrepair.
Nor is the amount of
repair or reconstruction work needed to
put the project back
into operation
relevant.
Rather, abandonment for FPA
____________________
purposes means that the hydroelectric
_________________________________________
generating function of the project has
_________________________________________
been abandoned.
______________
Hodgson III, 67 F.E.R.C.
___________
omitted).
of work to
a finding of
post-1935 construction.
at 229 (emphasis
there espouse
added), but
Aquenergy
_________
not controlling,"
at no time
does the
the existence
_________
of work
court states:
One must look to the nature of the work
and the purpose of the owner.
Major
repairs may involve much construction
activity, but the project is not brought
within the Commissions's jurisdiction if
work done in the name of repair does not
so alter the project that it is no longer
-1414
the
physical
abandonment.
The
act
needed
heart
to
of the
support
error
the importance
a
finding
in Hodgson II
___________
is generally
understood.
"abandonment."
is a
as that
question
Aquenergy
_________
goes to great
disintegrated
was no activity
maintenance";
or was
themselves"; and
"[t]he
torn down";
In
minimal
and
Abandonment
of
As the
at the project,
powerhouse
"trees
not
.
had reestablished
30 years to
at 229.
opinion the
Additionally,
court
in
two and
Aquenergy notes
_________
the
857
one-half page
period
of
the
importance
abandonment.
of
physical
as
factor
in
desertion
Aquenergy sense.
_________
and maintenance
Workers
restart.
Although
to control
-1515
and
monitor
generator
monthly.8
external
control
power
panel,
and
to
the
workers
factory
through
checked that
its
panel
constituted construction,
that
they show
the
and even
project was
meaning of Aquenergy.
_________
We
if they did,
not
believe
we believe
abandoned within
the
facts
here
the
are
owner commenced
jurisdiction.
"merely restored
specifications
'construction'."
and
to reconstruct
the repairs
It
that reconstruction
found that, because
the [project] to
configuration,"
Id. at 1316.
___
"[t]here
its original
was
no
new
____________________
8.
557 F.2d
16
before the defendant repaired and put into service two of the
four preexisting generators, the court found
under the FPA.
Id. at 1313.
___
no jurisdiction
construction if the
scope of the
original specification of
amount
work remains
the project.
Id.
___
at
1315.
Puget Sound applies directly here.
___________
no reconfiguration
the power house,
since
1935 of
the dam
"[t]he
original
and no
1316.
There was,
therefore, just as
Id.
___
here, no post-1935
none of
to appellate
review,
and
they do
jurisdiction.
not lend
The cases
support
either
to FERC's
contradict FERC's
or err for the
claim of
current
same reasons
57 F.E.R.C.
61,061
and
repairs
construction
is
reinstallation
to
an
return
to
essential
of
service
element
same
52
of
generator
and
because
actual
Section
23(b)
F.E.R.C.
61,074
-1717
of generation at flooded
where
removed
same
generator was
and
project
later replaced
was
51 F.E.R.C.
generator
of
incurred Section
61,018
greater
(1990) (after
capacity,
owners installed
abandonment
of
project
American Hydro,
______________________
Inc., 46 F.E.R.C.
____
original
62,175 (1989)
capacity
required license
dismantled
where
the
F.E.R.C.
structure
was
of
diversion
the
increase the
capacity
or
otherwise
to
years
license
and
10
construction despite
structure
with
23(b) jurisdiction
"construction must
.
for fifteen
owner surrendered
because Section
unused
62,209
replacement
after it
concrete
requires that
project's . .
significantly
. generating
modify
the
out
that the
one case
cited in
FERC's
61,061,
FERC recognized
construction.
accurately noted,
facilities
is
essential
construction' prong
project has
Id.
___
at
61,234.
abandonment,
reaching
its
"actual construction or
an
the
In
element
holding
FERC
reconstruction of
of
the
'post-1935
been abandoned
At
there was
China
no
and restarted
Mill
not
finding of
only
after 1935."
was
there no
any construction
by
FERC.
IV.
IV.
The
Mill
is
CONCLUSION
CONCLUSION
__________
reversed with
directions
to
application.
Costs awarded to petitioner.
Concurrence follows.
Concurrence follows.
dismiss the
license
-1919
CYR,
CYR,
fallacy
Circuit Judge
Circuit Judge
______________
in relying on
misinterpretation
(concurring).
(concurring).
of the
statutory
As
term "[post-1935]
necessary nor
provident
for the
panel to
16 ("[W]e
of this case.
the
conis
embrace
see supra at p.
___ _____
in the context
The
issue
on
of a
has been
appeal
of FPA
is
straightforward:
23(b)
requiring FERC
"grandfathered" facility
only in
"[post-1935] construct[ion]"
the event
encompasses
period of
question
closure?
clearly must
If, as
I respectfully
be answered
in the
submit, this
negative, FERC's
F.3d 1198,
1201
(1st Cir. 1994), and the court ought not venture further.
The majority opinion accedes to FERC's invitation to extend its licensure authority based on the reasoning
in Puget Sound and
___________
Aquenergy.
_________
In Puget Sound,
___________
however, the
had "constructed"
physical
structures anew at the "grandfathered" power facility following a devastating natural disaster.
19
assumption that
Congress could
to divest
power-plant operat-
resorted to an equitable
language
of the
jurisdiction.
The Ninth
guage
or
See id.
___ ___
as precluding
the agency's
licensure
1315.
strained
FPA
legislative
history
interpretation of
(merely
noting,
remotely
supportive of
the statutory
without
statutory lan-
citation
its
term "construct."
to
legislative
the error
227.
actions clearly
_______
Aquenergy
Systems'
came under
FERC
powerhouse) following
a voluntary closure
of the
approach, the
attempted to
Aquenergy court
_________
accommodate the
not one
___ ___
-2020
fathered" pre-1935
"operating rights."
concluding, without
"[t]he
[FPA]
existing
Quite
citation
was designed
in 1935,
but
the contrary,
exclusively
___________
on a
to legislative
to
not to
FPA
keep
event
230 (merely
history,
in operation
restore abandoned
23(b)
specific
Id. at
___
focuses
that
projects
rights").
unambiguously and
_____________
the "construction"
of
by the court in
I cannot endorse
that Aquenergy
advocated
are "controlling."
_________
Although
___________
those decisions
apparently
control
FERC
in
the
in
particularly
ironic that
and
interpretations
Aquenergy.
_________
we should
strain to
Indeed,
embrace them
project even
reopened but
61,061
no "construction"
-2121
See McRay
___ _____
after six-year
curred).
it is
"abandonment," where
of facilities
oc-