Subsea Riser less P&A Solutions

Presented by:
Date:

Gary Tait, Senior P & A Advisor Global Subsea Operations,


June 2013

This document is confidential and is intended solely for


the use and information of the client to whom it is addressed.

P&A From Vessels

Pulling Crown Plug


Well Stroker

Most times Crown plugs are retrieved using Slick Line

Most common reason for not being able to pull the Crown

GS Pulling tool

plug is debris / fill on top of the plug.

The Crown plug typically has a GS profile.

Crown Plugs

Well Stroker General Description

The Well Stroker is capable of applying Axial force


downhole by the use of a bi-directional hydraulic ram. The

Stroker can be fitted with various shifting or pulling tools


for Mechanical services solutions.
Types of jobs

Pulling crown plugs


Opening/Closing valves
Opening/Closing sliding sleeves
Retrieving/Setting gas lift valves
Setting straddle packers
Fishing operations

Well Stroker

Removing debris from top of Crown plug

Well Cleaner PST (Power suction tool)


Tool body OD

2 1/8 to 5 1/2

Length (with 2 bailer sections)


Weight in air
Completion ID

21 ft*
220 lbs*
>2.2

Debris volume in 3.5 set up

7 liters/section

Max. no. of bailer sections

Varied variety of options now available to client to tackle multiple types


of debris
Ability to change the bottom nose configuration to suit i.e. Flow
through GS pulling tool.
Both Hi Flow and Hi Pressure options available
Complete Suite of Filters taken to well site

Flow Through GS Pulling tool

Well Cleaner PST (Power Suction Tool)

Removing obstructions
Well Miller

Enabling operators to mill out and


remove valves, plugs, sand,
debris, scale and other downhole
barriers on wireline

Provide operators with the possibility to perform heavy duty well


interventions with a light touch
Lower costs compared to traditional heavy intervention work

Well Miller, stuck ball valve

Well Miller, reverse circulation bit

Circulation holes
Hydraulic Puncher, none explosive

Punch force 8 ton


Diameter of hole in casing 8 mm.

Currently testing range of steal, hardness, thickness and pipe sizes


8

Plug setting
Plug Setting Tool, none explosive

General Description
Electro Hydraulic operational setting tool for plugs, packers and straddle
systems
The tool requires no form of explosives or pre-charge of pressure and is
not dependent on well pressure for operation
The WST can be used to set any plug run on Baker #20 E4 setting tool
Technical Description
Make up length: 4,2 m
Maximum OD: 3 7/8
Maximum stroke length: 14
Maximum stroke force: 55.000 lbf
Maximum operational temp: 135 C
Maximum well pressure: 10.000 psi
Setting sleeve connection: Running tool/plug connection:
-

*The stroke force can be doubled to 110.000 lbf by adding one piston stage to
the tool
The increased tool length will be 60 cm

Cut tubing/casing

Welltec Cutter, none explosive

The Welltec Cutter is a tool that enables efficient, safe drill pipe and casing recovery operations
without the need for explosives. It is self-centralizing and removes pipe incrementally so that no
shavings are generated and a smooth, polished surface remains after the cut.

The Welltec Cutter eliminates the need for explosives required by most of the industry
alternatives. Explosives can pose an operational risk, especially when simultaneous operations
are being conducted. Transfer of explosives may also cause additional logistical requirements
and significant operational delays.

Cut examples

Cutter head

Very fine debris


Cutter placement

10

Welltec Cutter

Well Cutter
4.5 5.5 Drillpipe, casing or tubing

Verify Cement Plugs


Well Stroker
Well Stroker General Description

The Well Stroker is capable of applying Axial force


downhole by the use of a bi-directional hydraulic ram. The

Stroker can be fitted with a Blind Box deployed dowbhole to


tag cement. When cement top is tagged the stroker can be
anchored and a downward force of ~10 Tons can be applied
to the top of the cement plug

Isolate Zones/Repair casing/tubing


Welltec \ Enventure Partnership

13

Isolate Zones/Repair casing/tubing


Wireline Patch

14

P&A from Vessel -What Can Welltec Do?

Use Welltec cutter tool in conjunction with the DH


snubbing jack to retrieve TH.

30
20
10
5
0

Use Well Stroker to verify cement


Integrity (10 ton downforce)

Punch hole with Welltec technology

Set plug with Welltec technology


Logging, inspection and verification of tubing and
annulus cement and potential leaks

Reservoir

Gain access to wellbore, Pull crown plug cleaning services to


remove debris, sand fill, swarf, metal or rubber, etc.

Down Hole Services for P&A

Well Stroker to pull crown plug

PST to remove debris on top of crown plug, sand fill, swarf, metal or rubber, etc.

Milling services to remove obstructions (scales, stuck valves, nipple profiles)

Cleaning services to remove debris, sand fill, swarf, metal or rubber, etc. to obtain access
for other operations

Well Cutter to cut tubing/casing

Hydraulic puncher (none explosive) to punch circulation holes

Well Tractor for conveyance in highly deviated wells

Set Plugs with Plug Setting Stroker without using explosives

Well Stroker to verify top of cement plug integrity (10-16 ton force)

Casing/Tubing patches to isolate zones/repair damaged or corroded casing/tubing

Logging, inspection and verification of annulus cement, pipe integrity and potential leaks
in conjunction with 3rd party

Thank you for your time