Inspection & Test Plan For Screed Works
Inspection & Test Plan For Screed Works
Project Name
Client
Sub-Contractor
Location
: JBR Dubai
RESPONSIBI
I/T NO
SEQUENCE OF ACTIVITY
DESCRIPTION
METHOD
Shopdrawing
Document Review
Once
Method Statement
Visual
Once
Material Inspection
Visual/Site Engr.
Daily
Method Statement
Visual
Once
Surface Preparation
Method Statement
Visual/Site Engr.
Daily
Application of Screed
Inspection Request
Visual/Engineers
per IR
Curing of Screed
Method Statement
Visual/Engineers
Daily
Method Statement
Visual/Engineers
Daily
Inspection Request
Visual/Engineers
per IR
Prepared by:
SUBMITTAL NUMBER
FREQUENCY
SUBCONTRACTOR
MAIN
CONTRACT
A - Hold Point - Work cannot proceed before it is signed off by a specified person from that group
W - Witness Point - The activity or test must be witnessed by the person or organiza
to which it applies
R - Review
O - Obeservation
SD - Shop Drawing
MS - Material Submital
ME - Method Statement
SA - Sub-contractor
Approval
RESPONSIBILITY
MAIN
CONTRACTOR
CLIENT
cannot proceed before it is signed off by a specified person from that group
W - Witness Point - The activity or test must be witnessed by the person or organization
O - Obeservation