1.0
Purpose
This method statement covers the casting of blinding concrete described in
Section 03300 of the contract specification.
2.0
Scope
This method statement defines the responsibilities and describes the procedure
to be implemented during casting of blinding concrete for Parcels 601, 602, 603,
225, 805 and 800 series to conform to the approved shop drawings, contract
specification and other related standards.
3.0
Responsibilities
3.1
The Site Engineer shall be responsible for the implementation of the work
in accordance with this method statement and their responsibilities shall
be, but not limited, to the following:
3.1.1 Preparation of work schedule and casting drawing/plan.
3.1.2 Booking and ordering of only approved concrete mix and
preparation of required tools and equipment.
3.1.3 Designating skilled workers.
3.1.4 Supervising the work to ensure the work is performed properly in
accordance with this method statement and related specification of
the contract document.
3.2
The surveyor shall be responsible for setting out areas and levels for the
blinding concrete and survey check during casting.
3.3
The Site Engineer and Quality Control Engineer shall continuously monitor
all activities related to the work if implemented in accordance with this
method statement.
METHOD STATEMENT
BLINDING CONCRETE CASTING
ACADEMIC SUPPORT FACILITIES
SABAH AL-SALEM UNIVERSITY CITY, KUWAIT
UNIVERSITY
CONTRACT NO.: KU/KUCP/C1010/13-14
DOCUMENT NO. : CSCEC-C1010-MS-09, REVISION : 01
4.0
Materials
4.1
5.0
Preparatory works
5.1
5.2
The sub-grade shall be leveled and compacted and ready to receive the
blinding concrete.
5.3
6.0
Methodology
6.1
Guide lines and levels as per approved shop drawings shall be provided
by the surveyor.
6.2
6.3
6.4
METHOD STATEMENT
BLINDING CONCRETE CASTING
ACADEMIC SUPPORT FACILITIES
SABAH AL-SALEM UNIVERSITY CITY, KUWAIT
UNIVERSITY
CONTRACT NO.: KU/KUCP/C1010/13-14
DOCUMENT NO. : CSCEC-C1010-MS-09, REVISION : 01
6.6
6.7
Casted concrete shall be leveled as per the required elevation and level
shall be regularly checked by the surveyor.
6.8
6.9
The freshly casted shall be protected from premature drying as per clause
3.13 of Section III-2/03300 of the contract specification.
7.0
7.2
8.0
The Site Engineer in coordination with the Safety Officer, shall be ensuring
compliance with project HSE Plan during the implementation of this work which
shall include, but not limited to the following:
8.1
8.2