Introduction

2011.05.12.

Planning
The selection of the route
The selection of the construction methods

Geotechnical investigation
Investigating soil structure, soil strength,

permeability, ground water condition etc.

Staking out of the construction (layout)


Using coordinate system or reference system
Tools: tape measure, theodolite, electronic

distance measurement devices, GPS

2011.05.12.

Construction of the Tunnel

Cut-and-cover methods
Mining methods
Special methods

Construction of the Stations

Cut-and-cover methods
Mining methods
Other methods

Other connecting operations

Solidifying the soil


Water removal works

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method
New Austrian method (NT)
Tunnel Boring Machines (shields)

Special methods

Caisson

2011.05.12.

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method

New Austrian method (NT)


Tunnel Boring Machines (shields)
Special methods

One

One and a half

Caisson

Two

Two and a half

Levels of cut-and-cover tunnels

2011.05.12.

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method

New Austrian method (NT)


Tunnel Boring Machines (shields)
Special methods

Caisson

Ground support
Sloped trench (a)
Partly sloped (b)
Sheet pile wall (c, d)
Steel and timber

bracing (soldier piles)(e)


Slurry-wall (f)
Pile wall (f)
With propping or tie-back

2011.05.12.

Ground support
Pile wall

Budovatelu station, Prague

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method
New Austrian method (NT)
Tunnel Boring Machines (shields)

Special methods

Caisson

2011.05.12.

2011.05.12.

2011.05.12.

2011.05.12.

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method
New Austrian method (NT)
Tunnel Boring Machines (shields)

Special methods

Caisson

10

2011.05.12.

Construction of Fort George Tunnel

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method
New Austrian method (NT)
Tunnel Boring Machines (shields)

Special methods

Caisson

11

2011.05.12.

The Belgian method (proportions in m)

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method
New Austrian method (NT)
Tunnel Boring Machines (shields)

Special methods

Caisson

12

2011.05.12.

The German method (proportions in m)

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method
New Austrian method (NT)
Tunnel Boring Machines (shields)

Special methods

Caisson

13

2011.05.12.

The New Austrian method

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method
New Austrian method (NT)
Tunnel Boring Machines (shields)

Special methods

Caisson

14

2011.05.12.

Tunnelling shield at the Thames Tunnel, London

Schematic diagram of an EPB shield

15

2011.05.12.

The shields in Antwerp and Hamburg

16

2011.05.12.

TBM, Budapest
1.
2.
3.
4.
5.
6.
7.
8.

Rock environement
Cutting wheel
Supporting earth mass
Watertight steel separator wall
Hydraulic pressing jacks
Earth mass screw conveyor
Segment erector
Segment ring

17

2011.05.12.

Prefabricated
reinforced concrete
segments of the tube

The construction of Metro line 2, Budapest


The construction of the subway at the Navy
Yard, Washington DC

18

2011.05.12.

Construction
of the Tunnel

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

Belgian method
German method

New Austrian method (NT)


Tunnel Boring Machines (shields)
Special methods

Caisson

Construction of a four track tunnel in Stockholm

19

2011.05.12.

Caisson
Cutting edge types
Creating an underground
station

Construction
of the
Stations

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

One Vault method


Three Vault method
Five(six) tunnel method

Special methods

Caisson

20

2011.05.12.

Construction
of the
Stations

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

One Vault method


Three Vault method

Five(six) tunnel method


Special methods

Caisson

21

2011.05.12.

Equipment of construction
Baross tr

Ttnyi t

Mricz Zsigmond krtr

22

2011.05.12.

Ttnyi t

Bocskai t

TBM arrives to
Rkczi tr

23

2011.05.12.

Construction
of the
Stations

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

One Vault method


Three Vault method

Five(six) tunnel method


Special methods

Construction
of the
Stations

Caisson

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

One Vault method


Three Vault method
Five(six) tunnel method

Special methods

Caisson

24

2011.05.12.

Construction
of the
Stations

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

One Vault method


Three Vault method
Five(six) tunnel method

Special methods

Caisson

25

2011.05.12.

Construction
of the
Stations

Cut-and-cover methods Bottom-up methods (with different ground


support methods)
Top-down method (Milan-method)
Mining methods

One Vault method


Three Vault method
Five(six) tunnel method

Special methods

Caisson

26

2011.05.12.

Other
connecting
operations

Solidifying the soil

Freezing the soil


Grouting methods

Water removal works

Drainage
Sinking groundwater level
Watertight working pit

Wall

Wall

Solidified soil
Working
pit

Other
connecting
operations

Anchoring

Solidifying the soil

Solidified
soil

Freezing the soil


Grouting methods

Water removal works

Drainage
Sinking groundwater level
Watertight working pit

Well

Planned object
Sheet pile wall

Anchoring
Groundwater level

Working
pit

Solidified soil

Slurry wall

27

2011.05.12.

http://www.nycsubway.org/articles/irtbook_index.html
http://science.howstuffworks.com/engineering/structural/tunnel.htm
http://www.vivanext.com/gallery_subways
http://en.wikipedia.org/wiki/Tunnel
http://www.metro4.hu/hogyanepul.php

28

You might also like