PROJECT TO MANUFACTURE ROUND CORD (USED

IN GARMENT , SHOE LACE , BAGS ETC.)

Raw material required 125 Ton PP Yarn available from our Yarn
Manufacturing Unit

FOR ROUND PP CORD

Plant & Machine Cost 6 Head or 8 Head Cord Knitting Machine with its
accessories (Winder, Creel Stand etc)

200 M/C x 1.4 Lakhs = 280 Lakhs or 2.8Crores

Labour Job or Conversion Cost from our Own Yarn Plant @ Rs15000/- Per
Ton

Total Production of 200 M/C per 10Hrs Shift:

25 Kgs per Day x 200 M/C = 5000 Kgs or 5 Ton per Day

25 Working days x 5 Ton = 125 Ton per Month

A Total Conversion Cost:

125 Ton x Rs15, 000/- (Per Ton) = Rs18, 75,000/-

B Total Expense of Labour & Power per Month = 3.75 Lakhs

Net Profit:

A – B i.e. 18.75Lakhs – 3.75Lakhs = 15Lakh

Percent Profit:

15 x 100 = 5.3 % or 5%
280