The following activities, preceding activities, normal time and cost and crash time

and cost have been estimated from data accumulated for similar activities which
have been completed in the past preview not available
Preceding Normal Normal Crash Crash
Activity activiti time cost time cost
days Rs. days Rs.
A — 10 250 3 750
B .4 9 260 3 600
C A 7 240 3 500
D B 5 280 4 400
E C 3 300 2 450
F D, E 2 350 400
G E 4 320 3 350
H F, G 6 280 5 300
K G, if 8 400 6 500

Site costs have been estimated at Rs. 80 per day. Activities must be completed
either in t.ormal time and cost or crash time and cost.
You are required to : preview not available
(i) calculate and state the critical path using normal time, the associated time of
completion and the associated cost ;