OBP004604

From: (b) (6)


To: (b) (6)
Cc: (b) (6)
Subject: DRAFT schedule
Date: Monday, July 23, 2007 5:58:27 PM
Attachments: Phase 1 RFP Schedule MS98.pdf

(b) (6) :

Here is the DRAFT schedule. The current baseline in our system had contract awards in OCT for El Paso
K-1. Our draft schedule attached is trying to "push schedule to the left" and as you can see, the K1
schedule has the NTP 28 Sept. As I previously stated, on that award date, dependent upon the design,
the Contractor can begin clearing and grubbing. The design will dictate how soon the fence construction
will begin.