MOSAIC TILES

DMM CASE STUDY

PRESENTED BY
NAVEEN YADAV
VINEET VERMA
SAIF KHAN
Case Situation

Mosaic tiles is a tile manufacturing company

Two sizes of tiles produced: Large and Small

The tiles are produced in batch sizes of 100


Process Large tile ( x ) Small tile ( y ) Avilable hours
Molding 18 mins 15 mins 60 hrs / week
Baking .27 hrs .58 hrs 105 hrs / week
Glazing 0.16 hrs 0.20 hrs 40 hrs / week
Clay derivative 32.8 pounds 20 pounds 6000 pounds /
week
Profit 190$ 240$

objective:

maximize the profit ie:


Max Z = 190 x + 240 y

Variables: x = no. of batches of 100 large tiles produced


y = no. of batches of 100 small tiles produced
Constraints

18/60 x + 15/60 y ≤ 60 (molding)


0.27x + 0.58y ≤ 105 (baking)
0.16x + 0.2 y ≤ 40 (glazing)
32.8x + 20y ≤ 6000 (clay derivative)
x,y > 0 (non negative constraint)
Graphical solution
Optimal solution for the given
case
CASE 1 (X = 0 , Y = 0 )
Z = 0

CASE 2 ( X = 0 , Y = 181.03)
Z = 43447.2

CASE 3 ( X =182.92 , Y =0 )
Z = 34754.8

CASE 4 ( X = 136.36 , Y = 76.08 )


Z = 44167.6

CASE 5 (X= 100, Y=120)


Z= 47800

CASE 6 ( X=56.75 , Y=154.63)


Z-=47893.7