ZUWARA GENERAL HOSPITAL LIBYA

TECHNICAL REPORT

MV I LV ELECTRICAL SYSTEM IN ELECTRI,CAL STATI'ON

ZUWARA GENERAL HOSPITAL LIBYA

TECHNICAL REPORT

MV 1 LV ELECTRICAL SYSTEM IN ELECTR!ICAL STATION

1 ... -INTRODUCTION

The scope of this report is to define the M.V. & L.V. System which shall supply the required energy of the buildings which exist on the area of ZWARA GENERAL HOSPITAL.

2.-PROJECT DATA

• Operating Voltage of MV Supply System:

11.000 Volt A.C.

• Operating Voltage of LV Supply System:

4001230 Volt A.G.

• Frequency of Supply:

50 HZ.

• Maximum Voltage Drop

-On Main Distributors:

3%

-At most Distant POints of Supply:

4%

• Neutral Configuration:

TN-S

• Short Circuit Current Max:

65kA

3.-ELECTRIC SUPPLY SYSTEM

This section deals with the power supply system within the electric station whid"i will serve to all buildings in ZWARA GENERAL HOSPITAL AREA.

Electrical Equipments which wiU take place in Electrical Staiionare Switchboard Medium Voltage MV, Transformers, Diesel Generators, Low Voltage Main Distribution panel-boards and Uninterruptable Power Source.

MVSYSTEM

MV power shall be obtained from existing local network via proper XLPE type cables. Medium Voltage MV Switchboards;

81 L 1: Incoming City Line Switchgear

S2L2:

S3EM:

S4VM: 84F3:

S5TF2:

Outgoil1g City Line Switchgear (If it was needed tor existing network ring) Measuring Switchgear

Internal Power Supplier Switchgear Feeder for TR3

Feeder for TR2

..

S5TF4:

S5TF1 :

Feeder for TR4 Feeder for TR1

DRY TYPE (CAST RESINE) TRANSFORMERS

2000 KVA Rated 4 each Transfonnerwill serve to step down the 11 KV. Power to 0,4 KV.

Each Transfonner will have separate ccmosrtments with service door located in Electrical Station. DIESEL GENERATOR SETS

2500 KVA Stand by (2250 KVA Pnme power) rated 4 each Diesel Generator complete with own daily fuel: tanks wi,l:! be located in EI'ectlic Station.

4.~ELECTRIC mSTRIBUTION SYSTEM

The electrical loads of the project was distributed ,into three Low Voltage Main Distribution panelboards MDP1, MDP2, MDP3 and feed mainly by three dry type transformers TR1, TR2, TR3 with capacities of 2000 KVA.

Each of the 2000 KVA Transformer (Irt, TR2, TR3)shall be coupled and automatically connected with one 2250 KVA Diesel Generator (GEN~1, GEN-2, GEN-3) on separate bus bar in order to give continuous .energy to Ule buildings.

There will be a fourth bus-bar (TR4 % GEN4) of which one 2000 KVA Transformer and one 2250 KVA Generator are connected and this bus-bar will serve as a spare for any of operational 3 Transformers (TR1, TR2, TR3,) or Generators (GEN-l, GEN-2, GEN-3) fails,

Switching operations shall be automatically realized and' monitored by Scada and Automation System which shai'l be installed in Operation Room of Electrical Station.

Transformers -Low Voltage Main Distributionand Diesel Generator-Low Voltage Main Distribution panel-boards shall be connected' with 4000 A. Bus-bars.

In Transformer load calculations, minimum %10 percent future loads have been taken into considerations.

Transformers load distributions, diversity factors and demand a factor whi'cn was considered in transformer catculauons are indicated in detail as below.

5.-UNINTERRUPTABLE POWEIR SOURCE (UPS)

50 KVA rated Uninterruptable Power Souroe unit: shalt supply energy for the switching operanons, Scada System and security system requirements during 60 minutes in Electrical Stations.

Serhat ERTAN

Electric & Electronic Eng. Evergreen Consulting Ltd

o119-%r11-t5

Se~AJ..-f(i! &-r'!t_A'J'J~~ f2c 4 6efh"_ Co,

..Jq- JvJ-- e.rd Q_,p, e fo1) I'l . C"A

I'

ZUWARA HOSPITAL TRANSFORMER-l

Electrical Load Calculation and Transformer Selection

SECTION Connected Load
(KW)
WiNG A 1.461,44
ADMINISTRATION 906,24
GENERAL STORE 130,81
WORKSHOP 149,39
TECHNICAL ENTRANCE 16,52
EMERGENCY ENTRANCE 15,50
INCINERATOR 25,69
WASTE MANAGEMENT 16,46
VilLAS 175,00
CLINIC 50,00
PERiMETER LIGHTING 80,00
TOTAL CONNECTED LOAD 3.027,04 %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include

kW 3.027,04 kW 0,80 2.421,63 kW 0,98 2.471,05 kVA 0,80 1.976,84 kVA 2.000,00 kVA 2.250,00 kVA

A Total Connected load B Demand Factor

C {A*B} Total Demand Load

D Power Correction Factor (Cos 0 ) E (C/D) Absorbed total load

F Diversity Factor

G Absorbed total load x Diversity Factor Selected Transformer Power

Selected Diesel Generator Prime Power

ZUWARA HOSPITAL TRANSFORMER-2

Electrical Load Calculation and Transformer Selection

SECTION Connected Load
(KW)
WiNGB 3.448,87
TOT AL CONNECTED LOAD 3.448,87 %15 spare include

F Diversity Factor

G Absorbed total load x Diversity Factor Selected Transformer Power

Selected Diesel Generator Prime Power

kW 3.448,87 kW 0,70 2.414,21 kW 0,98 2.463,48 kVA 0,80 1.970,78 kVA 2.000,00 Kva 2.250,00 kVA

A Total Connected Load B Demand Factor

C (A*B) Total Demand Load

D Power Correction Factor (Cos ¢ ) E (C/D) Absorbed total load

ZUWARA HOSPITAL TRANSFORMER-3

Electrical Load Calculation and Transformer Selection

SECTION Connected Load
(KW)
WiNGC 1.461,44'
EMERGENCY 893,23
MEDicAL STORE 130,81
MORTUARY 149,39
He. STATION 38,50
BOOSTER STATION 53,13
MEDicAL GAS 82,41
TREATMENT PLANT 22,00
TREATMENT TANK 22,00
DESALATION PLANT 22,00
MAIN ENTRANCE 34,21
TOTAL CONNECTED lOAD 2.909,12 %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include %15 spare include

kW 2.909,12 kW 0,80 2.327,30 kW 0,98 2.374,79 kVA 0,80 1.899,83 kVA 2.000,00 kVA 2.250,00 kVA

A Total Connected Load B Demand Factor

C (A*B) Total Demand Load

D Power Correction Factor (Cos ¢ ) E (C/D) Absorbed total load

F Diversity Factor

G Absorbed total load x Diversity Factor Selected Transformer Power

Selected Diesel Generator Prime Power