ID Milestone Task Name Duration

1 No Generic Project Plan - Phase 1 44.25 days


2 No Project Initiation 44.25 days
3 No Scoping 9.13 days
4 No Scoping Workshop 0.06 days
5 No Create "wish list" 0.5 hrs
6 No Prioritize 0.5 hrs
7 No Select Desired Outcomes 0.5 hrs
8 No User Requirements Spec 1.5 days
9 No Identify user community 1 hr
10 No Define reporting styles 1 hr
11 No Identify and define requisite content 1 hr
12 No Document 1 day
13 Yes Sign-off 1 hr
14 No Functional Spec 2.63 days
15 No Define Reports / Dashboards 0.5 days
16 No Build Use-Cases 1 day
17 No Document 1 day
18 Yes Sign-off 1 hr
19 No Technical Spec 2.38 days
20 No Define sources 2 hrs
21 No Define processes - i.e. frequency of loading 2 hrs
22 No Source to target mapping 1 day
23 No Document 1 day
24 Yes Sign-off 1 hr
25 No Project Charter 2 days
26 No Terms and Conditions of Engagement 1 hr
27 No Roles and responsibilities 1 hr
28 No Success Criteria 1 hr
29 No Inclusions and Exclusions 1 hr
30 No Assumptions and constraints 1 hr
31 No Communication and escalation plan 1 hr
32 No Document 1 day
33 Yes Scoping Sign-off 1 hr
34 No Implementation and Application Development 34.25 days
35 No Pre-Implemetation 6.63 days
36 No Identify Attributes 1 day
37 No Obtain Correct License Key 1 hr
38 No Asses impact to "user community" 4 hrs
39 No Review System Configuration 0.5 days
40 No Identify Issues, Make recommendations and fix if necessary 0.5 days
41 No Install v9 Components on Production Servers 1 day
42 No Configure Intelligence Server 0.5 days
43 No Set up MicroStrategy Web and Administrator 0.5 days
44 No Establish Connection to Data source 1 day
45 Yes QA Installation 1 day
46 No MicroStrategy Report Design / Development #1 27.63 days
47 No Design and build Meteadata layer 2 days