Tank Commissioning Procedure
Tank Commissioning Procedure
Tank Commissioning Procedure
Page
DOC. NO. :
KQKS/Site_Com-P-01
REVIEW /
DATE DOC NO DESCRIPTION REV P’PD C’KD
APPROVAL
Tank Commissioning
11-05-2010 KQKS/Site_Com-P-01 0 YWL SKE TLP/TPM/RNZ
Procedure
Rev. Page
DOC. NO. :
KQKS/Site_Com-P-01
CONTENTS
1. OBJECTIVE
2. SCOPE
3. DEFINITION
4. PROCESS DATA
5. CALIBRATION CABLE
9. ON RECEIPT OF PRODUCT
12. FIGURE
DOC. NO. :
KQKS/Site_Com-P-01
1. OBJECTIVE
The purpose of this procedure is to define and guide terminal personal in commissioning of
two (2) units of reconstructed tank T-1100A & T-1100B at Tanjung Langsat Port Oil
Terminal, Pasir Gudang, Johor Darul Takzim.
2. SCOPE
The following procedure are a guide only, they may not be applicable or practical at all
terminal, the owner together with project manager and project consultant should ensure
the specific procedure, to satisfy quality and quantity control and local requirement, are
established and complied with.
3. DEFINITION
4. PROCESS DATA
• Density: 0.7871 @ 15 oC
DOC. NO. :
KQKS/Site_Com-P-01
5. CALIBRATION CABLE
Ensure that tanks are accurately calibrated in accordance to MS ISO Standard 7507 Part
2. The calibration report shall verified and endorsed by Sirim Berhad. These documents
shall be placed at TPL terminal control room for easy reference.
Ensure that tanks are never filled above maximum tank filling height. It is importance to
determine a maximum tank filling height, that is how much product in the tank can safety
hold with consideration of internal floating roof. Safe filling height for each tank shall be
established by terminal superintendent in consultation with the project manager and
project consultant. Level alarm High-high (LAHH) installed as overfill protection level
requirement.
7.1 Under normal circumstances use tank side gauge or remote gauge if fitted.
7.2 Perform manual dip at the roof dipping hatch to ensure that the level reading of radar
gauges are accurate. Set the tank radar gauge to agree with the depth from the
manual dip at the roof dipping hatch.
7.3 For the manual dips, the dip tapes and weights of approved pattern. Take tank dips
with a standard steel tape or approved non-static electricity-generating material or
coated tape fitted with a brass dip weight, both graduated in appropriate units.
Ensure that following tank nozzle and isolation gate valve in fully open / close position.
DOC. NO. :
KQKS/Site_Com-P-01
9. ON RECEIPT OF PRODUCT
9.1 Read the tank average temperature thermometer, take and record the temperature of
the tank contents manually.
9.2 Read the tank-side gauge before receiving, and again just after staring receiving
product.
9.4 Begin the receiving at a reduced rate until that the product is pumped into the correct
tank. This will reduce the potential for the explosions caused by static electricity when
product is pumped into the empty tank at a high rate. The flow rate shall be increased
once the internal floating roof had fully floatation. Never operate liquid flow rate above
maximum flow rate.
9.5 Take hourly tank-side gauge reading or remote tank gauging while receiving product
and calculate the pumping rate.
9.6 Take upper, middle and lower shore tank samples during receiving.
9.7 Observe the internal floating roof, floatation during receiving product to check that it
travel freely to its maximum height as mentioned in clause 6.
9.8 Reduce receiving flow rates when nearing LAHH to avoid overfilling and damage
internal floating roof (internal floating roof will hit the tank roof structure) of the tanks.
9.9 Record the final tank-side gauge reading after receiving and setting of tank contents.
Take the manual dip at the dipping hatch of the tank, at the same time as other i.e
temperature and density.
9.10 Once completed receiving, fully close the correct valve at the valve manifold and
tank (20” tank inlet isolation valve.).
9.11 Dip tanks and check for the water at bottom of tanks.
Record accurately all tank measurement, i.e. product dips, water dips (if required),
densities and temperatures, preferably in bound books showing tank number, product
held, date, time and location of measurement.
Rev. Page
DOC. NO. :
KQKS/Site_Com-P-01
Water bottom should be avoided in all tanks on all grades. Water drain checks on tanks
should be made whenever the presence of water is suspected. These checks, and
removal of any water found, should be made by withdrawing at full flow all bottom drain to
the holding tank.
12. FIGURE
DOC. NO. :
KQKS/Site_Com-P-01