BTS Soft Ware Installation Steps
BTS Soft Ware Installation Steps
7. Commissioning click
8. Down load Click
9. It will appear BTS SW(soft ware)
10. Chose two file first Master file
(BM2SAwj9.MSF)second(0002Aw16.DDL)
11. After Download completed you will see succeed otherwise repeat
downloading
12. After that edit window will appear and chose it BTS 900
freq10,20,30,40,50,60, freq(1800
600,610,620,630,640,650,660,670,680,690,700,710) and touch summit
13. The other window make save and leave
14. After that go Commissioning ,Remote inventory, Application part ,sectaries
and set parameter 1.1 and 1.4 and then save , manufacture click white brake
15. Inside commissioning Initialize sectors and you will see updating after
that finished
16. Inside commissioning Measurement VSWR the RF cable checking point
choose sector number and push star after few minute stop will become
active and push after push confirm threshold. Finished 3 of them.
17. Inside commissioning Fan test and choose all fan after few minute it be
running.