PROJECT: PROPOSED G+1 UNIT HOUSE ON PLOT NO.

125 AT
CLIENT: MR. A.B.M ISMAIL
DESIGNED CONSULTANT: MR. SARJOON MOHAMED ISMAIL

ESTIMATED BOQ

ITEM DESCRIPTION UNIT LENGTH WIDTH HEIGHT

SUBSTRUCTURE
1 Excavation
1.1 For Rubble work fdn Ft 230
1.2 For Column fdn No. 10
1.3 For Pit Sum 1

2 Lean Concrete
2.1 Under Rubble work fdn Ft 230
Aggregate Ft3 230 2 0.25
Sand Ft3
Cement Bag

2.2 Under footing fdn No. 10


Aggregate Ft3 3 3 0.25
Sand Ft3
Cement Bag

3 Footing No. 10
Aggregate Ft3 3 3 1
Sand Ft3
Cement Bag
Re-Bar T12 No.

4 Neck Column No. 10


Aggregate Ft3 0.75 0.75 3.5
Sand Ft3
Cement Bag
Re-Bar T12 No.
Re-Bar R6 Kg
Steel set Formwork No.
5 Roubble Works
2' width Ft 230 2 1
For 9"wall - 14"width Ft 176 1.167 2
For 4.5"wall - 14"width Ft 54 1.167 2.417
Sand Ft3
Cement Bag

6 TieBeam
Brick work 4" wall bothside Ft 138 1.5 207
Brick work 8" wall bothside Ft 201 3 603
R/f & Con. work 4" high Ft 138
R/f & Con. work 8" high Ft 201
Aggregate Ft3
Sand Ft3
Cement Bag
Re-Bar T12 No.
Re-Bar R6 Kg

7 Brick work for Pit Ft2


Beam & Slab Ft2

8 Back Filling No. 40

9 Stair Case Sum


Aggregate Ft3 22.32 3
Sand Ft3
Cement Bag
Re-Bar T12 No.
Re-Bar T10 No.
Re-Bar R6 Kg
Wood Formwork Ft2

SUPERSTRUTURE
Ground Floor
10 Column No.
Aggregate Ft3 0.75 0.75 10
Sand Ft3
Cement Bag
Re-Bar T12 No.
Re-Bar R6 Kg
Steel set Formwork No.

11 First Floor Beam Ft


Aggregate Ft3 200 0.75 0.417
Sand Ft3
Cement Bag
Re-Bar T12 No.
Re-Bar R6 Kg
Wood Formwork Ft2

12 First Floor Slab Ft2


Aggregate Ft3 762 0.417
Sand Ft3
Cement Bag
Re-Bar T10 No.
Wood Formwork Ft2

13 Ground Floor Bricks


9"thick wall Ft2
4.5"thick wall Ft2
3" hight Bricks No.

22 Roof
Lower Roof Ft2
Upper Roof Ft2
USE ON PLOT NO. 125 AT HASIM ROAD, AKKARAIPATTU - 05

AIL

MATERIAL LABOUR
QTY UNIT PRICE AMOUNT QTY RATE AMOUNT

0.00 - - 230.00 25.00 5,750.00


- 10.00 150.00 1,500.00
- 1.00 2,000.00 2,000.00

4.60 2,000.00 9,200.00


115.00 -
57.50 -
10.00 -

- 1.00 2,000.00 2,000.00


22.50 -
11.25 -
3.00 -

- 10.00 2,500.00 25,000.00


90.00 -
45.00 -
16.00 -
25.00 -

- 10.00 Incl. Incl.


19.69 -
9.84 -
3.00 -
40.00 -
16.10 -
10.00 200.00 2,000.00
460.00 - 2.30 3,500.00 8,050.00
410.78 - 1.76 3,500.00 6,160.00
152.31 - 0.54 3,500.00 1,890.00
341.03
22.74

368.00 - 126.00 50.00 6,300.00


1,072.00 - 189.00 75.00 14,175.00
50.00 6,900.00
100.00 20,100.00
129.13 - -
64.56 - -
23.00 - -
55.00 - 206.00 -
242.00 -

- 206.00 -

1.00 50,000.00
66.96 -
33.48 -
10.00 -
32.00 -
6.00 -
2.38 -
150.00 -

10.00 1,000.00 10,000.00


56.25
28.13
8.00
Incl.
110.00
10.00 200.00 2,000.00

200.00 125.00 25,000.00


62.55
31.28
11.00
46.00
264.00
400.00 400.00 50.00 20,000.00

762.00 762.00 100.00 76,200.00


317.75
158.88
60.00
150.00
762.00 50.00 38,100.00

1458.00 2,300.00 33,534.00


380.00 1,500.00 5,700.00
15746.25

610.00
1,100.00 17.00 1,800.00 30,600.00
TOTAL

5,750.00
1,500.00
2,000.00

9,200.00

2,000.00

25,000.00

Incl.

2,000.00
8,050.00
6,160.00
1,890.00

6,300.00
14,175.00

-
-
-
-

50,000.00

10,000.00
2,000.00

25,000.00

20,000.00

76,200.00

38,100.00
Material Requirement

ITEM DESCRIPTION UNIT QUANTITY

SUBSTRUCTURE

1 Rubbles Cube 10 9
2 Aggregate Cube 5 6
3 Sand Cube 6 6
4 Cement Bag 88 100
5 Re-Bar T12 Nr 152 150
6 Re-Bar R6 Kg 260 300
7 Re-Bar T10 Nr 6 10
8 Backfilling Cube 30 40

SUPERSTRUTURE
Ground Floor

1 Bricks - 3" high Nr. 16,000 16000


2 Aggregate Cube 4.36 5
3 Sand Cube 2.2 2
4 Cement Bag 79 75
5 Re-Bar T12 Nr 46 50
6 Re-Bar R6 Kg 374 350
7 Re-Bar T10 Nr 150 150
8 Formworks ft2 1162 1250
9 Electrical Conduit Sum
5000 45,000.00 bitument
8000 48,000.00 4" Down pipe -2 , L - 2, joint- 1, T-1
3000 18,000.00
775 77,500.00
250 37,500.00
50 15,000.00
200 2,000.00
1500 60,000.00
Masons 150,000.00
food 25,000.00

5 80,000.00
8000 40,000.00
3000 6,000.00
750 56,250.00
250 12,500.00
50 17,500.00
200 30,000.00
50 62,500.00
5,000.00
Masons 250,000.00
food 50,000.00
Day - 1

1 Mark the FSL level on the wall from EFL - 2.5' & Transfer that level to Bompula pulla mathil
2 Break the column blocks in the Boundry Wall & keep one Block on the small length of fdn & Tie t
3 Tie the nool parallel to that nool at 4' ( not 4'9" ) better to keep permanantly make 2 kooni & cros
4 Set the thread right angle from 40' to this nool
5 Now start C/L nooling both side as per Drg.
6 Mark the column footing on the earth by neeru powder
7 Bottom of Excavation for Column is 5' 8"
8 Bottom of Excavation for RR masonry is 4' 2"
9 Near the Ladies enterance column footing size is 4'x4'

Day - 2
ompula pulla mathil
mall length of fdn & Tie the thread
ntly make 2 kooni & cross bar on that cross bar mark the nail