L&T ECCD

ZCL Site
Yerraguntla

Material Management Report for the Month of October '10 (For WLS Platforms, Cladding Runners & Top Plan Bracings)
Wagon Loading Wagon Loading Wagon Loading Top
S.no. Description UOM Total Qty. Remarks
Platform at +6.85M lvl. Cladding Runners Plan Bracings

1 ISMC 250 MT 143.78 143.78 Total - 4205 Rmtrs.

2 ISMC 200 MT 70.08 70.08

3 ISMC 100 MT 15.88 15.88

4 ISA 75 X 75 X 6 MT 5.69 5.69

5 ISA 110*100*10 MT 48.00 48.00

5 32 mm dia. Pipe MT 10.22 10.22 3296 Rmtrs. Required at site

6 25 mm dia Pipe MT 3.22 3.22 1252 Rmtrs. Required at site

Total requirement (MT) 178.79 70.08 48.00 296.87

Total Material to be Procured 296.87 MT

New Wagon loading shed final scope

S.No Items description Weight (MT)

1 Portal feames 948


Conveyor supporting platform at
2 +6.85m lvl 198
3 Top plan bracings 131
4 Purlins 185
5 Cladding runners 249
6 Section view side bracings 132
7 Platform cheqered plate 98
8 Mono rail beam with bracings 105

Platform at +10.15m lvl for old-2


& old-4 conveyors modification
9 77
10 Sagrods 8
11 Handrails 51
12 Gratings 40

Total weight in MT 2222

L&T ZCL/CTG