Production calculation of single jersey circular knitting machine:

Production per day:

Production (length) = (courses per day)/ (courses per meter)


No. Of Feeder * Cylinder R.P.M. * 60 * 24 * Efficiency
=
CPM

SPECIFICATION OF SINGLE JERSEY:

Machine dia: 32”


Gauge: 24
Feeder: 48
Yarn count: 32 Ne
Cylinder R.P.M: 19
Efficiency: 85%
Stitch length: 3 mm.

Actual Production
Efficiency = Calculated Production ∗100

No. Of Wales
Open Fabric Width = WPI

No. Of Needles
= WPI [Open Width = 2 * Tubular Width]

Open Fabric Width


So, Tubular Width = 2