Construction Updates - October 24, 2010

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Anticipated Construction Activities 10/22/2010 9:44 AM

in Cheyenne, Elbert, Lincoln and Kit Carson Counties

Week Subac / Project Hwy Beg End County Planned Planned Contacts
of Description MP MP Activities Lane Closures
10/24/10 Lincoln Area SH 86 17.2 59.0 Elbert Shoulder work and One lane closed at a time 8AM- Jr Foreman: Harold Kitzman
Maintenance pothole repair 4:30PM . No delays expected. 303-915-6501

10/24/10 NH R100-131 US 403.8 408.2 Lincoln Concrete sealant, Pilot Car operation in use 24 Proj Engr: Roger Lau
US 40/287 Hugo- 40/287 shoulder embankment, hours per day every day this Cell: 719-740-1568
East asphalt construction in week. Both directions of traffic
the closed WB lane from trailing the pilot car in the EB
MP 403.8 to 408.0 during lane starting on October 5,
pilot car operations. Also 2010. Delays of 25 minutes
CBC construction and expected. Ladybird rest area is
erosion control item closed.
installation.

10/24/10 John Area I-70 393.0 395.0 Kit Carson- Crack Pouring Alternating Lane Closures: Supervisor: Bob Johnson
Maintenance Mon-Tues Mon - WB MP 393-395 Cell: 719-760-0721
Lincoln-Thurs Tues - WB MP 391-393
Thurs - WB MP 389-391
Reduced speed to 55 MPH
8AM-4:30PM all days

Cheyenne_Elbert_Lincoln_KitCarson