Data for Surge analysis

metres feet
1 FRL 344.00 m 1128.32 ft
2 MDDL 338.50 m 1110.28 ft
3 Diversion Discharge 168.00 cumec 5928.31
HRT
4 Centre line level of HRT 329.57 m 1081.00 ft
5 Length of HRT 6873.64 m 22545.54 ft
6 Diametre of HRT 7.00 m 22.96 ft
PRESSURE SHAFT
7 Centre line level of Pressure shaft m ft
8 Length of Pressure shaft 143.26 m 469.90 ft
9 Diametre of Pressure shaft m ft
PENSTOCK
10 Centre line level of Penstock 306.49 m 1005.29 ft
11 Length of Penstock 131.52 m 431.38 ft
12 Diametre of Penstock 6.00 m 19.68 ft
SURGE SHAFT
13 Surge shaft top level 366.00 m 1200.48 ft
14 Surge shaft bottom level 314.13 m 1030.35 ft
15 Surge shaft Diametre 25.00 m 82.00 ft
16 Orifice Dia 5.00 m 16.40 ft
17 Orifice area
BIFURCATION
18 Centre line level of Bifercation point 253.00 m 829.84 ft
19 Length of bifercation pipes-1 26.58 m 87.18 ft
20 Length of bifercation pipes-2 10.42 m 34.18 ft
21 Dia of Bifercation pipes 4.25 m 13.94 ft
22 Dia of Bifercation pipes at end 3.20 m 10.50 ft
TURBINE
23 Number of Turbines 2.00
24 Q(design) for each turbine 84.00 cumec 2964.15
25 Net Head on turbine
26 Total Head loss upto surge tank(hf)