Brick work with fly ash lime bricks ( FALG Bricks) confirming to IS 12894- 1989, class

designation 100 kg/ cm2 average compressive strength in superstructure above plinth level

SL. NO Description Unit Quantity Rate Amount

Details of cost for 1cum

Materials :

Bricks 1000 nos 0.473 2700 1277.10

Carriage

For bricks 1000 nos 0.473 161.652 76.46

Cement Mortar 1:6 0.22 2265.522 498.41

Labour

Foreman each 0.2 250 50.00

Mason each 0.6 172.596 103.56

Beldar each 0.65 154.185 100.22

Coolie each 0.65 154.185 100.22

Waterman each 0.35 157.833 55.24

2261.22

Add for Hire & Maintenance


of mixer, pumps, water etc.
@3% 67.84

2329.05
Add for scaffolding, challis,
ropes etc @ 3% 69.87

2398.92

Add for water & electricity @


1.5% 71.97

2470.89

Add for CP & OH @ 15% 370.63

Cost of 1cum 2841.53