OBP006095

Rio Grande Valley Levee Meetings

Monday, February 25, 2008


Location: Possibly County Courthouse Conference Room
Tim e: 1500-1700 Hours
Attendees: Loren Flossman – PF 225 Project Manager
(b) (6) – SBI TI SME
(b) (6) – SBI TI Real Estate SME
OBP Rep
J.D. Salinas – Hidalgo County Judge (not attending)
“Tito” Palacios – Hidalgo County Commissioner
Steve Crane – Hidalgo County Attorney
Godfrey Garza – HCDD Project Manager
(b) (6) – Dannenbaum Engineering (Private Sector)
(b) (6) – Dos Logistics (Engineer)
Ron Vitiello – RGV CPA (possibly attending)
(b) (6) – RGV ACPA
RGV Sector SBInet Team
Purpose: Need to meet with Mr. Garza and his project team + lawyer – purpose is to
discuss SBI requirements – this is a working management

Tuesday, February 26, 2008


Location: Possibly Harlingen Border Patrol Station
(Judge Cosco prefers to have meeting in Brownsville; In the interest of
Hidalgo Co., HRL is best mid-point site)
Tim e: 0800-0930 Hours
(Proposing 0830 start because of muster—if at BP station)
Attendees: Loren Flossman – PF 225 Project Manager
(b) (6) – SBI TI SME
(b) (6) – SBI TI Real Estate SME
OBP Rep
Carlos H. Cosco – Cameron County Judge
??? ??? – Cameron County Commissioner
J.D. Salinas – Hidalgo County Judge (possibly attending)
“Tito” Palacios – Hidalgo County Commissioner
Steve Crane – Hidalgo County Attorney
Godfrey Garza – HCDD Project Manager
(b) (6) – Dannenbaum Engineering (Private Sector)
(b) (6) – Dos Logistics (Engineer)
Ron Vitiello – RGV CPA (possibly attending)
(b) (6) – RGV ACPA
RGV Sector SBInet Team

Purpose: The purpose is to discuss Cameron interest and share the requirements for
them to team on a wall/levee project with CBP/SBI