Understanding Financial recovery on a construction site

Item of work
Q. why are we
doing this

A: Re. Instruction A: on drawing,in A: a clarification A: to get over


specification of drawings/ a dificulty
specification

Raise C.V.I Q. how do we Raise F.D.I Q. why did it


get paid? happen?

Q. Is there a Bill A: unforseen A: we got it


Item? circumstances wrong

No
Yes Q: is the Q: record work Yes Q: can we No 1.put it right
description No done and resources claim? 2.analyse why
accurate and used. Notify Arch. 3.ensure we
adequate. in writing learn from it
4.insurance claim

All is well. The Daywoks Star rate item Delay


Q.S will Disruption
measure the Prolongation
item.

Q: can we do discuss with Site Discuss with


this in a more Agent/Engineer/QS Contracts Mgr
efficient which is more Agent/QS
manner advantageous

PREPARE
CLAIM

NOTE:
Q. Question
A. Answer