Professional Documents
Culture Documents
Application of Network Scheduling Techniques in The Project Management
Application of Network Scheduling Techniques in The Project Management
APPLICATION OF
NETWORK SCHEDULING TECHNIQUES
IN THE PROJECT MANAGEMENT
______________________________
1.1 What is Schedule? What is it good for?
Schedule (Noun)
Schedule (Verb)
Figure-1
The horizontal axis plots time, the vertical axis plots location
along the length of project or percentage of the work performed.
Individual activities are plotted separately and can be broken at any
time. This means that the completion of the activity in question has
been suspended. The slope of activity line can change; this indicates
that the accomplishing speed of the activity has changed for some
reason.
In the mid fifties a great deal of research was conducted to
eliminate the disadvantages of the traditional scheduling techniques.
The results of these efforts are the network based scheduling
Figure 2
Figure-5
However there are two network preplanning techniques based
almost entirely upon resources:
• Resource leveling is an attempt to eliminate the manpower peaks
and valleys by smoothing out the period-to-period resource
requirements. The ideal situation is to do this without changing the
end date. However, in reality, the end date moves out and additional
costs are incurred.
• Resource allocation is an attempt to find the shortest possible
critical path based upon the available or fixed resources. The problem
with this approach is that the employees may not be qualified
technically to perform on more than one activity in a network.
3.1.3 Project Time
Figure-6
However, the standard deviation can be used just as easily, except that
we must identify whether it is a one, two, or three sigma limit deviation.
Figure-6 above shows the critical path of Figure-5 together with the
corresponding values from which the expected times were calculated, as
well as the standard deviations. The total path standard deviation is
calculated by the square root of the sum of the squares of the activity
standard deviations using the following expression: