ID Task Name Duration Start Finish Predecessors Resource Names 8

T
1 Web-based Training Plan 61.5 days Mon 8/10/09 Tue 11/3/09
2 Kick-off Meeting (discuss milestones and deliverables) 1 day Mon 8/10/09 Mon 8/10/09 Customer,Vendor
3 Design Phase (Storyboard) 10 days Tue 8/11/09 Mon 8/24/09
4 Design Storyboard 5 days Tue 8/11/09 Mon 8/17/09 2 Vendor
5 Review Storyboard 2 days Tue 8/18/09 Wed 8/19/09 4 Customer
6 Revise Storyboard 2 days Thu 8/20/09 Fri 8/21/09 5 Vendor
7 Approve Storyboard 1 day Mon 8/24/09 Mon 8/24/09 6 Customer
8 Development Phase 28 days Tue 8/25/09 Thu 10/1/09
9 Design Graphical User Interface (GUI) 2 days Tue 8/25/09 Wed 8/26/09 7 Vendor
10 Approve GUI 1 day Thu 8/27/09 Thu 8/27/09 9 Customer
11 Develop Presentation/Activity pages 20 days Fri 8/28/09 Thu 9/24/09 10 Vendor
12 Develop Assessments 5 days Fri 9/25/09 Thu 10/1/09 11 Vendor
13 Review Phase 21 days Fri 10/2/09 Fri 10/30/09
14 Alpha Review 5 days Fri 10/2/09 Thu 10/8/09 12 Customer
15 Revisions 10 days Fri 10/9/09 Thu 10/22/09 14 Vendor
16 Beta Review 2 days Fri 10/23/09 Mon 10/26/09 15 Customer
17 Revisions 3 days Tue 10/27/09 Thu 10/29/09 16 Vendor
18 Finalize Module(s) 1 day Fri 10/30/09 Fri 10/30/09 17 Customer
19 Integration Phase (LMS) 1.5 days Mon 11/2/09 Tue 11/3/09
20 Upload and Test in LMS 1 day Mon 11/2/09 Mon 11/2/09 18 Customer
21 Course Completion Sign-off 0.5 days Tue 11/3/09 Tue 11/3/09 20 Customer