PROGRESS OF WORKS – MOHE

 PROJECT OVERALL PROGRESS – 85%


 MAIN BUILDING PROGRESS – 89%

 CAR PARK AREA


• K SPAN work - 95%

 SUBSTATION & SERVICE COMPOUND WALL


• Overall progress – 98%

 PLASTERING
• Ground to Fifth floor – 98%

 BOUNDARY WALL WORK


• Overall progress – 40%

 WALL TILING
• G.F to 4th FLOOR – 98% completed (Public toilet)

• 5th Floor – 100% completed (Public toilet)

• 4th & 5th Floor – VIP toilet – 14 Nos completed (70%)

• EWC fixing – 1st & 2nd Floor General Toilet completed

 FLOOR TILING – PUBLIC TOILET


• Ground to Fourth Floor – 98% completed
• Fifth Floor - 95% completed

 CERAMIC TILING
• Roof Garden - work on progress
 PORCELAIN TILING
• Ground floor – 95%
• Pantry – First, second, third & fifth floor completed

 MARBLE LAYING (MANAZEL)


• Fourth Floor – 50% completed
• VIP lobby – 1st, 2nd & 3rd Floor – 60% completed

 ACOUSTIC WALL PANELLING


• Overall progress of work – 98%

 STRUCTURAL GLAZING
• Progress of work – 98%
 PINK CLADDING
• Progress of work – 98% (hold due to Lecture theatre)
 WHITE CLADDING
• Progress of work – 97%

 PAINTING PREPARATION
• Ground to Fourth Floor – 95%
• Fifth Floor progress - 87%
• One coat paint – First Floor
1. Block work area finished
2. Dry wall area – 25% completed

 DOOR FRAME FIXING


• Ground floor – 30%
• First & Second Floor – 48%
• Third & Fourth Floor – 44%
• Fifth Floor – 30%