Progress of Works Mohe 13.12
Progress of Works Mohe 13.12
PLASTERING
• Ground to Fifth floor – 98%
WALL TILING
• G.F to 4th FLOOR – 98% completed (Public toilet)
CERAMIC TILING
• Roof Garden - work on progress
PORCELAIN TILING
• Ground floor – 95%
• Pantry – First, second, third & fifth floor completed
STRUCTURAL GLAZING
• Progress of work – 98%
PINK CLADDING
• Progress of work – 98% (hold due to Lecture theatre)
WHITE CLADDING
• Progress of work – 97%
PAINTING PREPARATION
• Ground to Fourth Floor – 95%
• Fifth Floor progress - 87%
• One coat paint – First Floor
1. Block work area finished
2. Dry wall area – 25% completed