Assign Pert

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

Task ID Task Description Prerequisites

Duration

1 Build internal components none


2

2 Modify roof and floor none


3

3 Construct collection stack 1


2

4 Pour concrete and install frame 2


4

5 Build high-temperature burner 3


4

6 Install control system 3


2

7 Install air pollution device 4, 5


4

8 Inspection and testing 6, 7


2

Preceding
Activity Activity time
Activity
Start - 0
A Start 7
B Start 7
C A 2
D A 3
E B 5
F B 1
G C 4
H D,E 5
I F 5
End G,H,I 0
Preceding
Activity Time
Activity
A - 5
B - 2
C A 1.5
D A 1
E B 4
F B 1
G C 2
H D,E 4
I F 3

Task Dependencies Time(Days)


Implement Model - 5
Implement DB - 3
JSP Templates - 3
Unit Test Model Implement Model 4
Test DB Implement DB 1
Implement JSP course JSP Templates 7
Implement Resource
JSP Templates 3
Upload
Test JSP Course Implement JSP Course 3
Test Upload Implement Resource Upload 1
Unit Test Model, Test DB, Test JSP Course,
Integration Test 2
Test Upload