Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Transmission & Distribution

A Under observance
lack in awareness of the power
system status caused the recent
blackout in the USA. The blackout
started with some uncritical generator outages
in northern Ohio, leaving the system with n-1 After the spate of blackouts in 2003 the first cry was for
contingency reserves. An initial key incident, more power lines and/or generation capacity. But are these
the loss of the Stuart-Atlanta 345kV the root cause of the blackouts? The basic cause often lies
transmission line due to a flashover, also did in the lack of information for the power system operators
not look serious in terms of system stability. covering a wide area. IPG reports.
Together with operator error, however, it led
to a situation where the state estimator
program at one of the EMS control centres per cent of the power flows
could not assess the system condition. Being a through the Belgian power
prerequisite for contingency analysis, these system is not accounted for by
programs could not be run either. They would previously agreed contractual
normally calculate the affects of simulated exchanges.
failures on the system and alert operators to Once the planned power
critical conditions. flow in a large interconnected
In addition, computer failures at another system has been disrupted by
EMS control centre deprived the operators of transmission or generation
the alarm functions. Unaware of the function outages, the power flow finds
loss and consequentially relying on outdated Figure 1. Many blackouts occurred in the world in 2003 and 2004; its own way via several
is the series going to continue?
information for one hour, operators could not parallel paths. Following the
see that the power system was in the initial simple law that electricity takes the path of
stages of degradation. least resistance, it sometimes makes a wide
loop through several neighbouring areas or
Italian blackout countries. This occurred in both the US and
The blackout in Italy was also caused by a Italian blackouts.
lack of power system information. September (iii) The operators lacked real-time wide
28 was a Sunday and the blackout sequence area information – in both cases the operators
started at 3 am. did not fully understand what was happening
Making use of cost advantages, Italy was and did not know the probable future course
importing about 24 per cent of its then of the disturbance. This was because of the
relatively low total demand via France, lack of real-time wide area information.
Switzerland, Austria and Slovenia. The Swiss There are two possible alternatives to
Figure 2: Time-synchronised phasor
transmission grid was heavily loaded near its measurements of RES 521 are transmitted to prevent such blackouts in future:
the PSGuard System Monitoring Centre, which
n-1 limit. A flashover caused one of the main runs applications to calculate e.g. the phase
• run power systems with more reserves
380kV lines across the Alps to trip. An angle difference between two selected locations. (n-k), which is less economic and hardly
attempt to reclose the line failed, as the phase acceptable in today’s deregulated markets
angle difference was too high due to the high started at the interconnections between areas with competition and pressure on costs
power flows. This and insufficient load or countries. These inter-area or cross-border • improve the real-time wide area
shedding in Italy caused overloading of the connections are relatively weak links information that is available to operators.
other main 380kV line, which eventually compared with the highly interconnected
sagged and also tripped due to a flashover. areas themselves. This is also reflected in the Wide area monitoring
From this point onwards a cascade failure EMS systems: there are good assessments of Wide area monitoring is a viable alternative
was inevitable. The other lines to Italy were the system security status within the areas, but as it not only increases system security, but
overloaded, it lost synchronisation with the there is insufficient real-time information also allows the power system to be run at its
rest of Europe, the remaining lines tripped available for wide area security assessment pre-defined security margin, thus saving costs.
and Italy was isolated. There was a large across borders. To achieve this, ABB has developed a new
generation deficit within the islanded Italian (ii) The power flow is unpredictable – it is technology, that provides valuable support
system and despite further load shedding the difficult to ensure that the power flow follows with the determination of the real-time power
system collapsed completely two minutes after the paths previously agreed in contracts, even system status and therefore with the
isolation. What are the lessons learnt from on a day when there are no incidents. prevention of disturbances from spreading.
these blackouts? Belgium is a good example of this. It borders PSGuard is a wide area monitoring system
(i) Interconnections are the bottlenecks – it is on France, Luxembourg, Germany and the that utilises a new source of information to
noteworthy that these and other blackouts Netherlands. On some days, more than 50 determine the stability status of the power

Subscribe to IPG at: www.hhc.co.uk/subs/IPG


T&D Protection & Control

system. It uses phasors measured at 521 at both ends of the lines and the
selected points in the power system to calculation of the voltage angle
compute the phase angle difference difference provides information on the
between them. loading of the corridor. Here a phase-
angle difference of 1° corresponds to
Phasor measurement approximately 100MW. This clear
Traditional SCADA and EMS systems relationship enables the n-1 criteria to
for power system control only use RMS be guaranteed in case of reclosure.
values whereas PSGuard uses current A highlight in the usage of PSGuard
and voltage phasors (phase angle and is in the resynchronisation of the 1st
magnitude). The RMS values are and 2nd UCTE synchronous zones in
Figure 3 shows voltage stability monitoring with early warning and
acquired cyclically, are not time- emergency alarm. October 2004 (see figure 5). The 2nd
synchronised and do not allow power zone comprising most of the Balkan
system oscillations to be measured. The States and Greece and representing a
phasors in turn are measured in real- load of 21GW was reintegrated with
time by Phasor Measurement Units the remaining UCTE area, i.e. the 1st
(PMU) such as RES 521 that are all zone with 223GW of load. The zones
time-synchronised to an accuracy of are interconnected by relatively few
<1 microsecond by the GPS. links. A RES 521 Phasor Measurement
The phase angle differences allow Unit has been installed in Greece in
abnormal power system conditions to addition to those already placed in
be detected at an early stage. Both Switzerland. These are all being used
thermal and stability limits are throughout and after the
assessed. The safety margin towards resynchronisation to monitor system
system instabilities is calculated on line. stability during operation and the
This gives operators more time to take future increase in energy trade.
Figure 4 - ETRANS uses a Wide Area Monitoring System for
the necessary counter-measures if the dynamic condition monitoring to support the operators and
margins are too small. protection engineers in achieving an increase in the security of an Future developments
important transmission corridor.
Wide Area Monitoring functions The current systems provide on-line
include: wide area monitoring, which gives the
• phase angle monitoring with early operators more observability,
warning and emergency alarm information and time, to determine
• line thermal monitoring with early appropriate remedial actions to critical
warning and emergency alarm network conditions. Future
• voltage stability monitoring for developments are in the direction of
transmission corridors and entire wide area protection and control,
networks with indication of margin to where counter-measures are
stability limit recommended and can even be
• power oscillation monitoring with initiated automatically e.g. by using
amplitude and damping of the most Flexible AC Transmission Systems
dominant oscillation mode, warnings (FACTS).
and alarms Wide Area Monitoring systems can
Figure 5 - Wide area monitoring, with installations in Switzerland,
• frequency stability monitoring with Croatia and Greece, supervises system stability and records use existing communication channels,
amplitude and damping of the most oscillations during and after the resynchronisation of the 1st and are scalable for selective
2nd UCTE synchronous zones.
dominant frequency, warnings and implementation and cost-effective to
alarms large power transfers. install. They allow optimal grid utilisation
• data storage and export for off-line ETRANS was one of the first enterprises to combined with operational and planning
analysis and grid model optimisation install PSGuard. ETRANS is the independent safety. By providing on-line information on
• event-driven data archiving for coordination company for the Swiss extra stability and safety margins for dynamic
subsequent analysis. high voltage grid and it also carries out condition monitoring, they serve as early
These functions are designed to support specific tasks for the European UCTE grid warning systems in case of potential power
utilities in making optimal usage of the association. system disturbances. Such systems are a
transmission grid capacity and in preventing The objective of installing PSGuard was to viable choice for utilities required to run their
the spreading of disturbances. monitor the effect of large power transfers on power system in the most economic way
ETRANS uses the PSGuard Wide Area the Swiss north-south corridor (see figure 4). whilst maintaining the desired levels of
Monitoring System to monitor the effects of The direct measurement of the phasors by RES security. IPG

International Power Generation - November 2004

You might also like