Professional Documents
Culture Documents
Critical Path Method (CPM)
Critical Path Method (CPM)
Project Management
When to use:
n Management complex projects
Project Management n Many parallel tasks
n Deadlines and milestones must be met
n Difficult to know “ what to do first”
first”
Tuesday, May 9, 2006
n Difficult to know when project is in trouble
n Often have competition for limited resources
Project Management
Method n An activity
activityis
is any discrete part or task of a project
which takes resources and time to complete
1
Critical Path Method Critical Path Method
B A
A D
D
C
D C
C
B A 3 A
A D
D
C A 5
D B,C 2 C
C
Project Network
ES EF ES EF
LS LF LS LF
Late Late
Start Finish
Time Activity Time
Duration
2
Critical Path Method Critical Path Method
Activity Slack: S = EFT-EST = LFT-EFT Critical Path: Path with zero activity slacks
3
CPM Analysis
EE
HH
and
Start
Start 00
66
CC
33 Review Technique
BB
66
GG
55
(PERT)
FF
88
A 2 3 10
B 1 2.5 7
C 4 5 6
D 0.5 1.5 5.5 activity
a m b duration
4
PERT Analysis
PERT Analysis
Beta Distribution Assumption
Expected Time and Variance
a + 4m + b
expected
density
Expected Time =
6
duration
(b - a)2
Variance =
36
activity
a m b duration
B 3 1.0
Normal Distribution
C 5 0.111
D 2 0.694 z
5
PERT Analysis PERT Analysis
12 - 11
z= = 0.622 z = 0.622
1.778 + 0.111 + 0.694
From a Z-table for standard Normal distributions:
PERT Analysis
PERT Analysis
6
PERT Analysis
PERT Analysis
Activity Statistics Project Duration Statistics
Activity D
Activity Critical? Mean Var C.P. Var
Expected Activity Duration for “D”: A. 2 0.11
B. 6 0.44
a + 4m + b 2+4(8)+10 C. 3 0.00
ET = = = 7.33 D. 7.33 1.78
6 6
E. 6 1.00
F. 8 5.44
Variance of Activity Duration for “D”: G. 5 0.11
H. 0 0.00
(b - a)2 (10-2)2
Var = = = 1.78
36 36
BB G BB G
G G
66 55 66 55
FF FF
88 88
7
PERT Analysis PERT Analysis
x -µ 18 - 20
18 weeks: Z= = -1.61 18 weeks:
σ =sqrt(1.55) Z = -1.61 Prob(x <18) = 5.4%
Prob(x <18) = 1 - 0.9463 = 0.054 or 5.4% 20 weeks: Z = 0.00 Prob(x <20) = 50%
24 - 20 = 3.21
24 weeks: Z=
sqrt(1.55)
Prob(x <24) = 0.993 or 99.3%
PERT Analysis
8
Crashing Example Crashing G by 20 days
B 60 C 65 B 60 C 65
A E A E
D 10 D 10
5 20 5 20
F 45 F 45
G 100 G 80
170 150
B 60 C 65 B 60 C 65
A E A E
D 10 D 10
5 7 2 7
F 45 F 45
G 80 G 80
137 134
B 45 C 65 B 45 C 55
A E A E
D 10 D 10
2 7 2 7
F 45 F 45
G 65 G 55
119 109
9
Crashing C&F by 20 days
B 45 C 35
A E
D 10
2 7
F 25
G 55
89
10