Best Practice for Rack’s power Connectivity

Current Plan
Failure
Point

Failure
Points

Identified Failure Points


1. Extending the Industrial Sockets
2. Number of Outputs taken from the same socket of UPS2
Recommended Plan
Reason for the Recommendation

1. Extending the Industrial socket will increase the number of failure points.
2. It is advisable to take the output from a DB to the Racks instead of connecting
directly from the same socket of any device. Incase of any short circuit in a specific
Rack , DB will help to isolate that circuit and all other Racks connected to the DB
will not be effected.