School Of Engineering & Technology Infrastructure

BEC 122
SURVEYING AND FIELD WOEK

REPORT 1

TITLE: LEVELLING

SUBMISSION DATE 3/1/2011


LECTURER’S NAME Ms. NIK

AHMED ZOHAIR 093905077


MEMBER’S NAME & OTHMAN SAEED
MATRIC NUMBER
ADNAN QAID
ABDULAZIZ
Leveling 1: Obtaining the height of the temporary bench mark (TBM)

Objective : to obtain the new temporary bench mark (TBM)

Equipment : a. level equipment and tripod


b. 2 level staff
c. staff air bubble

CP 5
Setup 6
Setup 5

CP 1 BM A
Setup 1 Kerb CP 4

Setup 2 Kerb Setup 4


Kerb

CP 3
CP 2
Setup 3
To obtain the temporary bench mark we did the following steps:-

Step 1. We measured the height of the TBM with the help of the level mounted on top of the
tripod, this is (setup 1), which gives us the reading on the staff

Step 2. After taking the backsight of setup 1 to the TBM we take the foresight from setup 1 to
point 1.

Step 3. Move the equipment to another point (setup 2), we take the backsight to point 1, then the
height of the kerb, and then we take the foresight of point 2

Step 4. Move the equipment to another point (setup 3), we take the backsight to point 2, then we
take the foresight to point 3

Step 5. Move the equipment to another point (setup 4), we take the backsight to point 3, then the
height of the kerb, and then we take the foresight of point 4

Step 6. Move the equipment to another point (setup 5), we take the backsight to point 4, then the
height of the kerb, and then we take the foresight of point 5

Step 7. Move the equipment to another point (setup 6), we take the backsight to point 5, then we
take the foresight to point TBM