Selecting a Plan
Concept location Development
Excavation Obtaining
Plan Selection
Permits
Daily
Foundation Construction Operation
THE ACTIVITY LIST
ACTIVITY NAME ASSIGNED LABELS DURATION IN DAYS
Picking up a concept A 4
Selecting a location B 5
Plan Development C 2
Plan Selection D 2
Obtaining Permits E 4
Foundation F 2
Excavation G 3
Construction H 20
Daily Operation L 2
THE NETWORK DIAGRAM
• 0 •4 •9 • 11 • 13
A B C D 11
E • 17 F
• 4 •9 • 11 • 13
13
• 19
• 17
G • 19 H
• 22
• 42
• 22
L
EARLY START/ LATE START AND EARLY FINISH/ LATE
FINISH
ACTIVITY EARLY START EARLY FINISH LATE START (LS) LATE FINISH (LF) SLACK TIME
(ES) (EF) (LS-ES)
Picking up a concept 0 4 0 4 0
Selecting a location 4 9 4 9 0
Plan Development 9 11 9 11 0
Plan Selection 11 13 11 13 0
Obtaining Permits 13 17 13 17 0
Foundation 17 19 17 19 0
Excavation 19 22 19 22 0
Construction 22 42 22 42 0
Daily Operation 42 44 42 44 0
ACTIVITY LIST (EXPECTED TIME ESTIMATION
BY TIME-COST MODEL)
ACTIVITY ACTIVITY LABELS CRASH COST NORMAL COST NORMAL TIME CRASH TIME COST PER DAYS NEED
DAY