Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 9

BY: FOODIE’S WORLD

ABISHISHEK MISHRA -133


AVIK SARKAR – 134
ABHISHEK KUMAR DAS - 135
INTRODUCTION
 BUSINESS GOALS:
To provide people with delicious food, to create loyal customers
and in the long run to open up a chain of restaurants all over the
state.
 CHALLENGES:
 Quality control
 Health inspections
 Marketing and promotion
 Customer retention and generating new loyal
 Customers.
 Staff retention
 Requisite materials at the cheapest price.
WORK BREAKDOWN STRUCTURE:

Selecting a Plan
Concept location Development

Excavation Obtaining
Plan Selection
Permits

Daily
Foundation Construction Operation
THE ACTIVITY LIST
ACTIVITY NAME ASSIGNED LABELS DURATION IN DAYS

Picking up a concept A 4

Selecting a location B 5

Plan Development C 2

Plan Selection D 2

Obtaining Permits E 4

Foundation F 2

Excavation G 3
Construction H 20

Daily Operation L 2
THE NETWORK DIAGRAM

• 0 •4 •9 • 11 • 13
A B C D 11
E • 17 F
• 4 •9 • 11 • 13
13
• 19
• 17

G • 19 H
• 22
• 42
• 22

L
EARLY START/ LATE START AND EARLY FINISH/ LATE
FINISH
ACTIVITY EARLY START EARLY FINISH LATE START (LS) LATE FINISH (LF) SLACK TIME
(ES) (EF) (LS-ES)

Picking up a concept 0 4 0 4 0

Selecting a location 4 9 4 9 0

Plan Development 9 11 9 11 0

Plan Selection 11 13 11 13 0

Obtaining Permits 13 17 13 17 0

Foundation 17 19 17 19 0

Excavation 19 22 19 22 0

Construction 22 42 22 42 0

Daily Operation 42 44 42 44 0
ACTIVITY LIST (EXPECTED TIME ESTIMATION
BY TIME-COST MODEL)
ACTIVITY ACTIVITY LABELS CRASH COST NORMAL COST NORMAL TIME CRASH TIME COST PER DAYS NEED
DAY

Picking up a A 12000 10000 4 1 666.67 3


concept

Selecting a location B 10000 7000 5 2 1000 3

Plan Development C 15000 10000 2 1 5000 1

Plan Selection D 2000 1000 2 1 1000 1

Obtaining Permits E 10000 7000 4 2 1500 2

Foundation F 20000 8000 2 1 6000 1

Excavation G 12000 6000 3 2 6000 1

Construction H 30,00000 24,00000 20 5 120000 15

Daily Operation L 30000 20000 2 1 10000 1


IF PROJECT DURATION IS MADE FROM
44 DAYS TO 40 DAYS:
 1st day: Crash A by 1 day: Cheapest price would be Rs. 666.67
Duration of the project: 43 days. Project cost: Rs. 24,69000 + Rs.
666.67 = Rs.24, 69, 666.67

 2nd day: Crash B by 2 days: Cheapest price would be Rs. 2000


Duration of the project: 41 days.
Project Cost: Rs. 24, 69, 666.67+ Rs. 2000 = Rs. 24, 71, 666.67

 3rd Day: Crash D by 1 day: Cheapest price would be Rs. 1000


Duration of the project: Rs. 40 days Project Cost:
Rs. 24, 71, 666.67+ Rs. 1000 = Rs. 24, 72, 666.67

 THE TOTAL COST OF THE PROJECT IF TO BE


COMPLETED WITHIN 40 DAYS IS RS. 24, 72, 666.67

You might also like