Professional Documents
Culture Documents
Volume-3 Technical Specification and Geological Report Part-1
Volume-3 Technical Specification and Geological Report Part-1
LIMITED @HPC)
CONTRACT DOCUMENTS
, -
FOR
TECHNICAL SPECIFICATIONS
AND GEOLOGICAL REPORT
DAGACHHU HYDRO POWER CORPORATION LIMITED (DHPC)
Table of Contents
Conditions of Contract
1 Instruction to Bidders (ITB)
2 Bid Data Sheet (BDS)
3 Eligibility and Qualification Criteria (EQR)
4 Bidding Forms (BDF)
5 Eligible Countries (ELC)
7 General Conditions of Contract (GCC)
8 Particular Conditions of Contract (PCC)
9 Contract Forms (COF)
6.1 INTERPRETATION
C
J
Dagachhu HPP Section 6 Employers Requirements 6.1 1nte$refllim -Ti .
TABLE OF CONTENTS
PAGE
1 DOCUMENTS COMPRISED N THE EMPLOYER'S REQUIREMENTS ........................... 1
2 PRECEDENCE OF THE DOCUMENTS COMPRISED IN THE EMPLOYER'S
REQUIREMENTS....................................................................................................................... 1
3 COGNISANCE ................................................................................................................................ 1
4 DEFINITION OF TERMS........................................................................................................... 1
5 ABBREVIATIONS ......................................................................................................................... 2
Dapachhu HPP Section 6 Emplgvcr's Rcquin'menls -
6.1 lntrrprerafion I
6.1 Interpration
6.2 Technical Specifications
6.3 Conshuction Schedule
6.4 Bill of Quantities (BOQ)
-
6.5 National Envimmnent Commission NEC Clearance
6.6 Material Test Reports
6.7 Tender Drawings
6.5 Land Survey and Key Reference Points
6.9 Geological Reporr and Drawinp
3 COGNlSANCE
The Contractor acknowledges that he has copies of all of the documents comprised in the Employer's
Requirements.
4 DEFINITION OF TERMS
Unless the contrary intention appears:
'-Plunt': or "Pmver Plmzi" means the works of Lot I Civil Works and the works of Lot 2 E&M
Equipment, which together are capable of proper and reliable production and evacuation of elecmc power
in the quality and quantity as described Section 6 Requirements.
"Completi(~n" means the state of the Works when the Employer issues the Taking- Over Cemficate;
"Divertable Fion," means the total net flow rate measmd in m3lsec that is available for diversion into the
Power Station at the Intake Point alter taking account of Compensation Flow requirements;
"Facili!ies" means those facilities (including the Power Station) developed within the Works that are to be
taken over by the Employer at Completion Date;
" H ~ r a l o means
~ ~ " the data descn3ed as Probability of Exceedance and River Row at the Intake;
"Sea Level" ineans the mean sea level datum derived From GPS survey and detailed topo-mphical survey
as described in Section 6.8 Land Survey and Key Reference Points
"BOQ" means the Bill of Quantities ,which is only indicative for Division 01,02 and 04 and has been
provided merely to assist the bidden and to support the evaluation of the Bid, but not to serve as a basis for
a unit priced Conaan It does not necessarily cover @erefore each and every item to be
delivered/constructed.Bidden shall therefore quote for the entire civil works of Division 01.02 and 04 on
a single responsibility basis.
C o n w to the Works under Division 01.02 and 04, the Works under Division 03 'Vnderground
excavation" shall be offered item by item and will be paid on an item rate basis, that means as per actual
quantities according to offered unit rates in the Bill of Quantities.
For the Bid documents the expression "Connacror" is equivalent to "Bidder" and "Bidder" becomes
"Contractor" in the event of the award of the contract
All terms defined in Volume I, Part I (Bidding Procedures -Invitation for Bids) and Part III (Conditions of
Contract and Contract F m ) and used herein shall have the meanings ascribed to them in those
documents.
5 ABBREVIATIONS
The following abbreviations have been used in Section 6 Employers Requirements:
Table of Contents
Conditions of Contract
1 Instruction to Bidders (ITB)
2 Bid Data Sheet (BDS)
3 Eligibility and Qualification Criteria (EQR)
Z 4 Bidding Forms (SUFI
5 Eligible Countries (ELC)
7 General Conditions of Contract (GCC)
8 Particular Conditions of Contract (PCC)
9 Contract Forms (COF)
TABLE OF CONTENTS
6.2 T E C H N I C A L S P E C I F I C A T I O N S
Chapter 00
GENERAL
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
. Chapter W General .u
TABLE O F CONTENTS
Lot 1 Civil Works. Volume II
Section 6.2 Technical Specifications
Chapter 00
GENERAL
PAGE
1 GENERAL ......................................................................................................................................
1
1.1 Scope of work ....................................................................................................................... 1
1.2 Key h j e c t ~ a t.....................................................................................................................
a 2
1.3 Diversion weir and Intake ...................................................................................................... 3
1.3.1 Weir Base with Integrated Part of Stilling Basin ...................................................... 3
1.3.2 Grout Curtain and Drain Holes ............................................................................... 4
1.3.3 Side Walls. Wing Walls. Intermediate Wall ............................................................. 4
1.3.4 weir ~ o d .................................................................................................................
y 4
1.3.5 Stilling Basin ............................................................................................................. 4
1.3.6 ~ntakestructure ......................................................................................................... 4
1.3.7 Weir Bridge ............................................................................................................... 5
1.3.8. Maintenance and Operation Building ........................................................................ 5
1.3.9 Hydromechanical and Electrical Equipment for Weir and Intake .............................5
1.3.10 Fish Ladder ................................................................................................................ 6
1.3.1 1 Temporary Water Diversion .Cofferdam ............................................................... 6
1.3.12 Consmction Material for Weir and Intake: .............................................................. 6
1.4 Connection Channel and Tunnel to the Desilter ..................................................................... 6
1.5 Desilter (Settlement Basin) 7
1.5.1 Hydromechanical and Electrical Equipment for Desilter ..........................................7
1.6 Headrace ................................................................................................................................. 8
1.6.1' Headrace Channec.....................................................................................................g
1.6.2 Headrace Tunnel North ............................................................................................. 8
1.6.3 Side Adit.................................................................................................................... 8
1.6.4 Headrace Tunnel South ............................................................................................. 9
1.6.5 Hydromechanical and Electrical Equipment for Headrace ....................... ............9 ...
1.7 Swg? ~ a ..............................................................................................................................
k 9
1.8 Press, Shaft and Pressure Tunnel ................................................................................... 10
1.9 Powerhou~eCavern and Transformer Cavern ...................................................................... 10
1.9.1 Powerhouse Cavern .................................................................................................10
1.9.2 Transformer Cavern ................................................................................................ 11
10 POW^,^,^^ Access Tunnel. Emergency Exit and Cable Tunnel ........................................ 11
................................................................................................................... 11
12 Tailr%ce~~~~~l and Outlet 12
3 H~dromechanicaland Electrical Equipment for Powerhouse ............................................12
I n l u m r i i ~ s ~ - ~ m m 6 q ~38.2
~ m rrm
rh~ca1WifiC#ti~~bp(~W-l.m
..
. . ...
Dagachhu HFT Section 6 -Employer's Requirements 6.2Tshaical Spcifieations
Chapter 00 General .iii
...
1.18.1 Rellablllty of Power Supply .................................................................................... 22
1 GENERAL
In addition to the following descriptions, the Tender Drawings shall be referred to.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 00 G e n d - 2
whnxnuUI. ririlw&a U
-.Im o h a l l w 0 ~ ~ ~ ~ b d b d m M . 1 Y 1 . 2 ! ~ h r ~ l ~ A ~ ~ k ~ m ~ O I
. .
Dagachhv HPP Section 6 -Employer's Requirements 6.2 Tshnical Specifications
Chapter 00 General - 3
The connection channel has a horseshoe shape and a concrete lined base and partly full concrete lining or
shotcrete lining, depending on the geological conditions.
A flushing outlet is foreseen, before the desilter, to enable the cleaning of the connection channel and
tunnel. An overflow structure at the beginning of the desilter limits the rise of the water level in case of
flow fluctuations and the spillover drops down a cliff into the Dagachbu.
,"<
//.'..
, .c.?
--,
. *,'
/
/
,-,..*,,
. , which transfers the load to the concrete. The hoist mechanism will be installed directly on the slab over the
,:\antrance flume.
',
!.,:
' . .' ,'.
* -.
I .-:
I
,('
,: ..'
< -. <- , , .
G
iiw,uqrrhhu biddlrmmm2,um I n.,i -f-va i..iidrndsita ilsslnn~~q~~ddum3
i ro~umeigdxt nao i lahart r F c i s r . ~ x o m ~ ~ h ~m8mm~~rrr
iX
,
' . - ;
/,
; :;
Dagachhu HPP Sstion 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 00 General - 8
A trash rack (fine screen) will be installed in the downstream section of each desilter basin in order to keep
debris from entering the headrace tunnel. It will consist of removable panels and horizontal support beams
with a total dimension of approx. 9.4 x 8.3 m each. The trash rack will be installed with an inclination of
approximately 72' degrees to the horizontal, which will be optimized during preparation of the final
design.
For easy handling during assembly or dismantling, the trash racks will be manufactured in several pieces
The trash rack shall be fixed firmly on the embedded parts with hook bolts or other suitable means.
There are three trash rack cleaning machines for the three trash racks installed
The supply and placing of all required anchor profiles, niches, pits, slots, cable channels and pipes cast in
the concrete structure or put in the ground is in the scope of the civil work contractor. The casting and
grouting of the rails and other embedded parts shall be carried out by the civil contractor. The foundation
for the mechanical equipment shall also be carried out as part of this contract.
The primary earthing shall be carried out by the civil contractor according to the instructions of the
contractor for the E+M Equipment.
1.6 Headrace
The ground Consists of sediments with boulders. To avoid settlement. mechanical compaction of the
ground helow the structure is required at least to a depth of 60cm, in some instances deeper.
.. .>.
."L
i i , -
.- .
.
Dld d.=urrni%ua I aril.nrri~,l iJddin~inl Iiv=n, , ~ ~ t m n 6 r n q b d d n d u m n oi b ?tanmvc.l
I rdumr 01 l . i r r
r~~firr#i~~s*lavi~mgmm
Dagachhu HPP Sstion 6 -Employer's Requirements 6.2 Tshnical Specifications
Chapter 00 General - 10
The stilling chambers below the turbines shall be steel lined with 1lOmm thick steel plates. Supply and
installation of the plates is within the scope of the Lot 1. Civil Works Contractor.
The recess for the ball valves shall be partly covered with a removable cover and designed for a uniform
load of 5kN/mz. For safety a removable railing shall be provided.
The opening of the turbine runner transport shaft shall also be covered with a removable conosion
protected steel cover designed for a load of 5kN/m2.
All cable channels shall be closed with corrosion protected, stiffened steel covers resting on steel angles,
butting onto the floor. The thickness of the steel plates shall not be less than 4mm.The circular shaped
covers around the generators in the machine hall shall be made in the same manner. The design load shall
be 2kNImz. The covers shall have lapping so that no dirt can fall through the gaps. Supply and installation
of all covers are within the scope of Civil Works.
The door separating the access tunnel from the cavem is foldable, or a robust, fire resistant two wing gate
with locking arrangement and has to be supplied and installed by the civil work contractor.
Above the gate an air ventilator will be installed by the Lot 2, E+M Contractor. The removable, fire
resistant partition around the ventilator shall be within the scope of the Lot 1, Civil Works Contractor.
The g a n ~ e for
s the 220kV transmission line and the 33kV line are placed in front of the control building
close to the embankment of the Dagachhu. The cable channels end there. The cable channels are covered
with concrete slabs. The gantries are not within the scope of the civil work contract, but river protection
work shall be camed out by the Civil Work Contractor. The entire area in front of the control building shall
be blacktopped under the civil work contract.
A watertight, covered tank with a capacity of approximately 200rn3 shall be placed 50m above the access
level in the vicinity of the powerhouse access, for fmtighting purposes in the cavern. The tank, including
the pipes outside the tunnel is within the scope of Civil Works.
The supply and installation of all required anchor profiles, niches, pits, slots, cable channels and pipes cast
in the concrete structure or put in the ground is within the scope of the Civil Works Contractor.
Dewatering System
The dewatering system will cover the drainage system of the powerhouse as well as the dewatering of the
main units. The water will be collected in a pump sump and pumped to the tailwater canal. The drainage
and dewatering pit shall be equipped with two identical submersible-type pumps. For the drainage system.
one pump will operate during normal operation and the second pump shall serve as a standby-unit. The
pumps shall be automatically controlled by float switches. The design of most of the dewatering pits shall
preferably require no pump. Provisions shall be made, that no water from outside enters the cavern through
the access and emergency tunnel by trenches.
The dewatering system also includes the pipe work, the siphons and the covers
The complete dewatering system including the pumps shall be supplied and installed by the civil
contractor.
-
Powerhouse Cranes, 2x80115t Auxiliary Cranes
In the powerhouse machine hall, two cranes each with a capacity of 801 are installed. They independently
run on one pair of crane rails but can be joined to operate synchronously and handle loads of up to 1501.
The crane installed in the powerhouse machine hall shall be an indoor overhead travelling type. It shall be
used when necessary, to handle the heaviest and largest parts of the powerhouse equipment. This crane
shall be used for the erection and for future maintenance of the turbines. valves and generators of the
power plant.
The support for the crane rails (reinforced concrete beams on columns) is erected by the Civil Work
CanUactar .
The transformer cavem shall be equipped with a crane with a capacity of St to lift and transport the SF6
switchgear into the upper part of the cavem. This crane shall be supplied and installed by the Civil Work
Contractor.
Primary Earthing
The requirement of primary earthing shall be approximately 5000m (Five thousand metre) and 300
Connection points with strips to the surface. The emhing strips have to be connected with the
reinforcement.
The material shall be galvanized Iron ship of 40mm x 5mm.
This coven weir and intake, desilter, surge shaft, powerhouse, control buildings and gantries. Small
earthing connections to doors, railings and other small metal items are not included in the above figures but
have also to be provided by the Civil Works Contractor.
Dagachhu HPP Section 6 - Employer's Requirements 6.2Technical Specifications
Chapter 00 General - I5
1.14.2 Precipitation
Figure 2 shows the long-term mean monthly precipitation observed at the Daga Dzong gauge during the
pcriod 1996 to 2005. Mean annual precipitation observed within that period is approximately 3000 mm.
Maximum precipitation typically occurs during the monsoon period from June to September. The period
from November to January is practically dry.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter W General - I6
700
600
S e a s o n a l Variation of P r e c i p i t a t i o n - Daga Dzong
1
1
I
F- 500
1 400
f 300
i :::
*
0
1 2 3 4 5 6 7 8 9 10 11 12
I1
Month
J
Figure 2: Seasonal variation of precipitation - Daga Dmng Station (1460 m asl)
1.14.3 Temperature
The seasonal variation of temperature in Daga Dzong is shown in Figure 3. The long-term mean of daily
minimum (maximum) temperature varies between 6°C (1 1°C) in January and 18°C (24°C) in June.
S e a s o n a l V a r i a t i o n of T e m p e r a t u r e . D a g a D z o n g
0 L
1 2 3
-Monthly
4 5
Mean of Daily Min Temperature
6 7 8 9
1996-2004
10 11 12
Month
-
Figore 3: Seasanal variation of ternperaturn Daga Dzong Station (1460 rn asl)
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter W General - I7
1.15 Discharge
I
p-
The design discharge duration curve for the intake location is therefore as shown in Figure 5.
I
Flow Duration Curve Dagachhu HPP (676 km3
Based on Discharge Obser~tionsatTashiding Gauging Station (814 km2) 1992-1997
200.00
180.00
160.00
14000
-
-&
$ 120.00
E
lOO.00
m
C
80.00
5
60.00
40.00
20.00
0.00 1 ! ! ,
0 10 20 30 40 50 60 70 80 90 100
%Time Discharge Equaled ore Exceeded
1 I I
Jul 1 14.30 45.60 154.42 59.28
1
L..
0
O,.Oi.19, 3112.1992 31.121533 31.121994 31.12 1995 3012.1996
The low flows at the Dagachhu HPP intake in Table 2 have been extrapolated using a Log Pearson 111
distribution for different recurrence intervals.
-
Recurrence Lowest 7-day average Lowest I-day average
Interval flow flow
-
[years] [m31s] [~~ISI
-
5 5.78 5.57
10 5.72 5.50
-
50 5.67 5.46
-
100 5.66 5.45
Table 2: Low flow magnitudes and frequencies for Dagachhu HPP based on Log Pearson In statistics
Firm flow (incl. residual flow) is in the range of 6.4 (95% time available) to 5.6 (99.9% time available),
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 00 General - 20
Figure 8: Flwd magnitudes and frequencies for Dagachhu HPP based on the Gumbel distribution
I Recumnce intmal lyeanl I Pcak discharge 1 Upper 9546 confidence bound I Lowcr95R confidence bound I
hia,
D,dd,ru.ml.un( 8 rir,cm~s,in
i-.MioilovOI 8 ,jwmrjIluminn*m*daoldum nu is zlrhn,iaf ~mlri.m~lnnrr~ni.rmIIII~IIcI~~ TWO*
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter W General - 22
1.17.1.1 -
Phuntsholing Sankosh
Phuntsholing-Semtoka-Sankosh ca. 320 km,all in Bhutan;
Road widening and improvement in progress up to Rurichhu;
Some widening of Rurichhu to Sankosh required;
9 bridges between Phuntsholing and Semtoka, bearing capacities of 30 - 70 tons, spans of 9 - 67 m:
5 bridges between Semtoka and Rurichhu, bearing capacities 18 - 241, spans of 10 - 33 m;
7 bridges between Rurichhu and Sankosh, bearing capacities of 18 - 401, spans of 17 - 85 m.
1.17.1.2 -
Sankosh Dagana
From the new bridge (design capacity 40tons. span 94m) at Sankosh, the Daga district road leads to the
project area and new access roads lead from the district road down to the various project sites. The road
distance from the Sankosh Bridge to the powerhouse is about 56km. to the intake area about 70km.
Along the district road eight rivers and streams are crossed with eleven bridges having spans between 9m
and 33m and an initial capacity of 24 tons, but have been downgraded to 12 tons. A few hairpin turns with
an outer radius of less than 9m create a bottleneck for long trucks. However, construction equipment
(excavator) on truck with a p s s weight of 28 tons has recently reached the site and the road will be
improved gradually.
The standard and length of all temporary roads required during construction are at the discretion of the
contractor, but have to be dismantled and the area reinstated to original conditions unless the employer
decides otherwise.
For further details regarding roads refer to Chapter 02 Site Installation, Clause 2.5 Access Roads.
1.19 Completeness
The Contractor shall, in cooperation with the supplier of the electrical and hydromechanical equipment,
provide all civil work for a complete and fully opeiative state-of-the-art Power Plant with reinstatement of
the natural environment disturbed during construction.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 00 General - 23
1.20 Standards
The work shall comply with the latest issue of the applicable European standards and Eurocodes or
equivalent internation~llyacceptable standards The Contractor shall identify the standards he intends to use
and shall submit copies of latest editions of relevant standards to the Employer if required.
Section 6 Employer's ~ e q u i r e m e n t s
6.2 T E C H N I C A L S P E C I F I C A T I O N S
Chapter 01
Design Works
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 01 Design Works .ii
TABLE OF CONTENTS
Chapter 01
DESIGN WORKS
PAGE
1 DESIGN WORKS ........................................................................................................................... 1
1.1 Scope of Design ...................................................................................................................... 1
1.2 Interface with Lot 2 E&M ................................................................................................... 1
1.3 Cavern Exploration Concept in the Early Construction Stage................................................1
...
1.4 General Layout of the Faclhtles.............................................................................................. 1
1.5 Standards ................................................................................................................................ 2
1.6 Apprbval of Design .............
1.7 Design Life .............................................................................................................................
1.8 Hydraulic Model Test ............................................................................................................. 3
1.9 Routine Operating and Maintenance Systems ........................................................................4
1.10 Maj~Maintenance............................................................................................................. 4
1.11 Durability, Reliability & Redundancy .................................................................................... 4
1.12 Flood Criteria.......................................................................................................................5
1.13 . . ......................................................................................................................
Seismic Cntena 5
1.14 Performance Criteria ............... . ............................................................................................ 5
1.14.1 General ......................................................................................................................5
1.14.2 Operating Rang ..............................5
1.14.3 Net Head at the ........................................................................................... 5
1.14.4 Particle Separation.....................................................................................................5
1.15 Tests at Completion ................................................................................................................ 5
1.16 "AS-built" Drawings ...........................
Dagachhu HPP Satition 6- Employer's Rquircmcnts 6.2 Techniml Spccitications
Chapter 0 I Design Wohs I-
1 DESIGN WORKS
(a) Permanent access works to the Dagachhu diversion weir and intake including Tanalum Chhu bridge,
the connection channel, the portals of the connection tunnel, the desilter, the beadrace channel, the
portals of the headrace tunnel, the side adit at Chura Chhu, the surge shaft, the access tunnel to the
headrace tunnel at the surge shaft, the control building at the access tunnel to the cavern, and the
portal of the tailrace tunnel.
@) Water conveyance system, comprising intake, channels, wnnels, penstock sequence at the side adit,
surge shaft, steel lined pressure shaft, bends, bifurcation, turbine shaft, tailwater channels in the
cavern, tailrace tunnel, outlet structures.
(c) Diversion weir and intake
(d) Connection channel including Gamla Chhu bridge
(e) Connection tunnel
(0 Desilter
(g) Headrace channel
(h) Headrace tunnel north and south including facilities at the side adit and type of lining (cast-in-place
watertight I cast-in-place open-jointed I shotcrete) according to the ground and rock overburden
conditions in order to prevent leakages
(i) Surge shaft
(i) Vertical pressure shaft
(k) Horizontal pressure shaft, tunnel for bifurcator
(I) Powerhouse cavern, the transformer cavern, generator cable tunnels, including all auxiliary tunnels for
excavation, mucking, etc.
(ml Access tunnel to caverns
(n) Tunnel for cable duct (power evacuation), air supply and emergency
(o) Tailwater tunnel
(p) Deposit areas for rock and soft ground excavation material
(q) Control buildmg
(r) All other civil work structures and facilities necessary for completeness of the Dagachhu Hydropower
Plant
(s) Structures and facilities for site installation
(t) Protection and maintenance components, including slope protection works, river embankment
protection works, steel linings, overhead travelling cranes
(u) Earthing system of all civil work structures with hydrosteel or electromechanical equipment
(v) As-built drawings and operation and maintenance manuals
A general layout of the Dagachhu Hydropower Plant and appurtenant structures is included in Section 6
and detailed requirements for each element are described in relevant chapters of this Specification.
1.5 Standards
Eurocode or equivalent standards as approved by the Employer shall be applied for the design. However,
only such standards shall be allowed, of which official english versions are available. All design works
shall follow the best practice and state of the art principle. The Coneactor shall submit 3 copies of any
standards, approved by the Employer and used for the design, to the Employer.
1.14.1 General
The power plant shell meet the following performance criteria regarding the civil works. T i e lest
methodology required for testing compliance with these performance criteria is described belouf. Any
failure of the Works to meet tl~esecriteria must be remedied prior to co~npletion.
The Contractor shall submit detailed drawings of all areas used for site installation and of all structures and
,-
-... -..
~
. ...
. . , , .
..
buildings, including the equipment of Lot 2 connected to or imbedded in the civil work structures.
Dngachhu HPP Section 6 Employer's Requirements 6.2 Technical Speclficat~ons
Chapter 02 Site Installation
6.2 T E C H N I C A L S P E C I F I C A T I O N S
Chapter 02
SITE INSTALLATION
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specificat~ons
Chapter 02 Site Installation .ii
TABLE O F CONTENTS
Lot 1 Civil Works. Volume I1
Section 6.2 Technical Specifications
CHAPTER 02
S I T E I N S T A L L A T I O N
PAGE
1 GENERAL O F SITE INSTALLATIOS ....................................................................................... 1
1.1 Installation .............................................................................................................................. I
1.2 Removal of Site Installation ................................................................................................... 1
1.3 Materials and Equipment ........................................................................................................ 1
2 EXECUTION O F WORK .............................................................................................................. 2
2.1 Site Installation ...................................................................................................................... 2
2.2 "As-built" .Drawings ............................................................................................................. 2
2.3 Auxiliary Services of Site Installation 2
2.4 Preparation of Terrain ......................................................... 2
2.5 Access Roads .......................................................................................................................... 3
2.5.1 Categories of Access Roads ................... .
.. .......................................................... 3
2.5.2 Contractor's Duties .................................................................................................... 3
2.6 Car Park Area ............... 4
2.7 Storage Areas .......................................................................................................................... 4
2.8 Power Supply .......................................................................................................................... 5
2.8.1 Single Line Diagram ............................................................................................... 6
2.8.2 Electric stand-by ........................................................................................................ 7
2.9 Water Supply and Sewage System 7
2.10 WaterDistribution 7
2.1 1 Housing. Accommodation and Facilities for the Contractor .................................................. 7
2.12 Site Laboratory ............................. 8
2.13 Storage and Workshop Area for Lot 2 Contractor .......................................................... 8
3 TESTS AND PROPERTIES ..........................................................................................................
8
4 AUXILIARY WORKS FOR SITE INSTALLATION ................................................................8
Dagachhu HPP Seclion 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 02 Site lnsrallation I
1.1 Installation
The Contractor shall present, twenty (20) calendar days prior to start of any works, drawings and
specifications sufficiently detailed to enable the Employer to determine the suitability of the proposed
constructions and their conformity with these specifications.
2 EXECUTION OF WORK
Tbe Public Roads to be maintained by the Civil Works Contractor shall be the reach between Powerhouse
take-off point and Dame Site take-off point measuring approximately 10 km. The Contractor shall keep
this reach of Public Roads motorable at all times and no extra payment shall be made.
No time extension and cost escalation/compensation shall be allowed for any road (national highway or
district road or project road) blocks continuously up to 15 days. The Contractor shall keep in stock
sufficient quantity of construction materials at site to manage such contingencies. No strengthening of
existing public roads and bridges will be carried out by the Employer for the Civil Works Contractor.
The electric power consumed by the Contractor shall he charged at fixed rates:
The Conuactor shall allow Lo[ 2 Contractor to connect to the transformers provided by the Employer.
In case that the Contractor requires other voltage levels than 400 V , all transformers and switchgear shall
be provided by the Contractor at his own cost.
Dagachhu HPP Section 6 Employer's Requirements 6.2 Technical Spec~lications
Chapter 02 Site lnstallarion - 6
DHPC
l,., I i,",,*n*Um ,L.ddin*dlnl, .durn.;;* ...,
-.,,>"h"qYdL.ndu.." 1(*i,.D",idiPrn0."~~on~hrpn01a:ri~l.!irlmnl..Oidu.~gl:~
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter02 Site Installation 7
Chapter 03
SURVEYING WORK
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter03 Surveying Work - i i
TABLE OF CONTENTS
Chapter 03
SURVEYING WORK
PAGE
3 SURVEYING WORK ................................................................................................................ 1
3.1 General ...................................................................................................................................
I
3.2 Handing-Over of Survey Data ................................................................................................ I
3.3 Instrument and Equipmen 2
3.4 Approval of Contractor's Surveys................................ 3
3.4.1 Augmentation of Basic Survey Grid ....................................................................... 3
3.4.2 Survey of Ground Profiles .........................................................................................4
3.4.3 Original Ground Profiles ........................................................................................... 4
3.4.4 Final Ground Profiles ................................................................................................4
3.4.5 Setting Out of Wo
3.4.6 Setting Out Check
3.4.7 Tunnel Alignment
3.5 Survey Records and Documentation...
3.6 As-built Drawings ...................................................................................................................5
3.7 Measurement and Payment 6
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 03 Surveying Work - I
3 SURVEYING WORK
3.1 General
The Contractor shall render all services for geodetic survey and measurements as required for the
performance of the works.
Based on the drawings, these services cover in general the establishment of axes, centerlines, alignments of
project structures and features; the setting out for construction thereof; the accompanying control surveys
for correct location, dimensions and elevations as well as the necessary surveys for measurements to permit
quantity calculations for invoicing wherever payment is being made on item rate basis. Further details are
outlined below.
Such surveys shall be based on andlor referred to a basic grid of datum points and benchmarks extended
adjacent to the Works in the project area, see section 6.8. This grid shall be the sole basis of reference for
all survey works and measurements.
Details of the grid are shown in section 6.8 Land Survey and Key Reference Points.
Further details, such as description of datum points and benchmarks, sketches of location, coordinates and
elevations will be handed over by the Employer to the Contractor prior to the commencement of works.
For the execution of the survey works the Contractor shall employ and provide experienced professionals
and auxiliary staff familiar with modem survey techniques and instruments. All survey and measurement
works shall he recorded in a professional way.
The Contractor shall provide, maintain, adjust and operate the required survey and auxiliary equipment for
the performance of the Works.
The Contractor shall submit to the Employer prior to the commencement of the survey works for his
approval a programmatic report on the required survey works, outlining in detail records of his responsible
survey staff, surveying methodologies intended, details and technical data on surveying instruments.
equipment and auxiliaries, details on accuracy guaranteed, considering methodology and inswments used.
The Contractor's attention is drawn to the fact that a considerable pan of the survey works refers to the
survey of underground structures.
Methodologies, equipment and auxiliaries to he used shall be suitable and meet the particular requirements
of underground survey.
All survey works performed by the Contractor shall be subject to approval by the Employer
All survey and measurement activities shall be recorded in maps and field-books as directed and approved
by the Employer. Where required, the production of drawings and maps shall be deemed to be part of the
Works.
Should it become necessary that basic datum points and benchmarks should need to be removed because of
foreseeable construction works, the Contractor shall inform the Employer of the need thereof and obtain
approval and instruction for the establishment of new basic datum points and benchmarks andlor auxiliary
points with the required accuracy.
If, within three (3) months upon taking over, inconsistencies within the basic grid or to datum points and
benchmarks are detected by the Contractor. he shall inform the Employer immediately thereof and produce
the evidence. The Employer shall subsequently inform and instruct the Contractor on remedial measures to
be taken. Any survey works, setting out or measurement already taken or performed prior to the detection
of such inconsistency shall be rechecked and corrected by the Contractor without any additional payment.
If no objections have been raised against the basic grid and the related data, the reference points and the
data are considered accepted by the Contractor and are deemed included under his responsibility for the
execution of the Works.
Additional basic datum points and benchmarks established by the Contractor for the convenience of his
works shall have at least the same quality and durability as those of the existing poinu and meet the
accuracy requirements.
The accuracy and reliability of additional basic datum points and benchmarks shall be established upon
performance of at least five series - measurements and two closed level loops respectively, with the
required analyses and mean value calculations.
6 . 2 TECHNICAL SPECIFICATIONS
Chapter 04
EARTH AND ROCKWORK
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 04 Eanh and Rockwork ii
T A B L E OF CONTENTS
Chapter 04
EARTH A N D R O C K W O R K
PAGE
1 CLEARING, GRUBBISG AND STRIPPING .............................................................................. 1
1.1 General .................................................................................................................................. 1
1.2 Materials .............
1.3 Execution of Wor
1.4 Tests and Properties 2
1.5
..
Auxlltary Works ..................................................................................................................... 2
2 OPEN-CUT EXCAVATION .......................................................................................................... 2
2.1 .
General .....................................................................
2.2 ...........
Materials ..................................................................
2.2.1 Class A - (soft material) ....................
2.2.2 Class B -(soft material
.... 2
DHPC
2 lahniral ~ ~ ~ 6 r r r ~ n " r h a p C r M "k"nhr i r o r l . & x
bidderumnis\/ol i rirll wrltdl* I d u r n ij'psn i~~xribn6nqV Iuld8
Dagaehhu HPP Section 6 - Employcf s Requiremehts 6.2 Technical Specifications
Chapter04 Eanh and Rockwork - iii
4.3.9 Shotcret
1.1 General
This work shall consist of clearing, grubbing and stripping the area of the Work within the limits of the Site
as defined in the Drawings and ordered by the Employer of all trees, stumps, bushes, roots, down timber,
rotten wood, rubbish, debris, humus, swamp material and any other vegetation or unacceptable material.
It shall include the removal of buildings, foundations, fences, retaining walls and other obstructions
interfering with the proposed Work, salvaging such of these materials as may be designated by the
Employer or otherwise disposing of the spoils in a manner satisfactory to the Employer before Work starts
and mutually agreed upon in a protocol and layout plan.
Generally, all materials have to be discharged and treated to limit negative impacts on the environment.
1.2 Materials
Materials suitable for use of any kind may be separated by the Contractor, if so approved by the Employer
All other materials shall be handled as described hereinafter.
13 Execution of Work
The Contractor shall perform the Work of clearing, grubbing and slripping so as to remove the material
herein specified. If he chooses to remove any waste material suitable for incorporation into or use on the
Work, the amount of suitable material shall be replaced by the Convactor at his expense. All material
removed by the clearing, gmbbing and stripping operation shall he removed from the Site or otherwise
disposed of as specified or directed by the Employer. Care shall be exercised to see that the eventual
burning of such material does not destroy or damage public or private property, and the Contractor shall he
fully responsible for any destruction, damage or nuisance.
Living trees outside of grading limits shall be cut only as specified or directed by the Employer, and all
branches or trees extending into the limits shall be mmmed carefully to give a clear height as required over
the Site.
Within areas where excavation or filling is to be carried out, the ground shall be cleared of all living or
dead trees, and stumps and root mats shall be removed to a depth of not less than 0.3 m below the surface
or a depth as directed by the Employer. With the exception of areas to be excavated, all depressions made
below the ground surface by the removal of stumps or roots shall be refilled with suitable material and
compacted to the satisfaction of the Employer. No grubbing and stripping operation will be required in
disposal areas and in areas to be excavated, unless the excavated materials shall he used in permanent fills
or cofferdams.
Fences, buildings or structures of any character upon or within the limits of the Works and not necessary
for the construction shall be removed carefully by the Contractor in whole or in part as specified or
directed. The materials so removed shall be piled on the abutting property, neatly and in an acceptable
manner or otherwise disposed of as specified or directed by the Employer.
When fences enclosing pastured land or orchards are required to be removed, the property owner shall be
notified sufficiently in advance to enable him to construct supplemental fences or make arrangements as
required.
The grubbing limits at borrow pits and the order to execute them shall be those indicated on the drawings
or as directed by the Employer. The Employer may order the suspension of the grubbing (during a period
which will not cause delay or any olher inconvenience to the Contractor) when he considers that the
borrow pits areas already grubbed may produce sufficient materials for fills.
<
DKP
grhhv Dld &wUrnnl?Ual I civil WrlrUol I rohm i<\puli # - s t h n 6 n q ( b2 r.rhnlcsl sphbrarion.khaplcr W rmh .3 m h o d . l * n l u l - O R
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 04 Eanh and Rockwork - 2
2 OPEN-CUT EXCAVATION
2.1 General
Excavation shall be executed as specified in accordance with the lines and slopes shown on the tender
drawings, or as indicated by the Employer. During the progress of the Work, it may at times be necessary
or advisable to alter the slopes or the dimensions of the excavations. Excavations shall then be done to the
required dimensions and shall be finished according to the specified lines and slopes. in a way acceptable
to the Employer. All necessary precautions shall be taken to cause the minimum possible alteration or
disturbance to the material lying under and adjacent to the excavation's final lines.
2.2 Materials
With regard to excavation methods, only three (3) classifications of open-cut excavation, two (2) of soft
(earth) and one (1) of hard (rock) materials are defined as stated below. It shall be understood that such
classification does not apply to underground excavations.
Excavation for the detour of the riverbed shall be included in the following specifications
2.2.1 -
Class A (soft material)
Top Soil: is the upper layer of soil rich in organic matter and may include humus or
clay or lmse refill.
2.2.2 -
Class B (soft material)
Includes all of the following:
Waterlogged Soil: are soil types which are, due to their high water content, of plastic to
liquid consistency and which do not dehydrate easily, as for instance
mud, etc.
Light Soil: nun-cohesive gravel-sand mixture up to a maximum size of 60 mm and
with little or no fines.
Medium-Heavy Soil: similar to light soil, but with sizes over 60 mm, as for instance crushed
stone, shingle, etc.
Cohesive Medium-Heavy Soil: soil types with a cohesive character and natural moisture content as, e. g.,
clayey sand, sandy clay, clayey silt, and silty clay. This kind of soil can
be excavated by means of excavators or tools.
Dagachhu HPP Section 6Employer's Requirements 6.2 Technical Specifications
Chaptcr 04 Eanh and Rockwork - 3
Heavy Soil: soil types very heavily compacted as for instance stiff clay, etc., or
cohesive medium-heavy soil types dried out. This kind of soil cannot be
excavated by tools and has to be loosened by equipment before
excavation.
Also included in heavy soil are medium-heavy soils and cohesive
medium-heavy soil heavily mixed with shingle, gravel, and boulders up
to I .0 m', as well as construction rubbish and compacted slag.
Light Rock: loose layer of rock or loose fissured rock, etc., and layers of marl with
content of boulders up to 1.0 m3, as well as sand and gravel layers
hardened by calcareous or fermginous cementing material, crumbly,
brittle and slatey, that can generally he loosened by tools without
blasting, even if blasted to facilitate loosening for the convenience of the
Contractor.
2.23 -
Class C (hard material)
Hard Rock: means solid rock which can be removed only by explosives, baning,
wedging or other recognized and approved methods of quarrying solid
rock, and shall furthermore mean excavation of all boulders larger than
I .0 m', existing concrete and masonry blocks in cement monar.
23 Execution of Work
23.1 General
A working schedule with explanatory repon shall be submitted prior to the start of excavation work and
shall be binding for that Work.
The schedule shall show the quantity, type and capacity of the equipment provided, the working method
envisaged, uansponation and distribution of excavated material, location of stock-piles. main storage areas
as well as the approximate number of laborers, etc. The working schedule and any amendment to it during
the construction period shall require the Employer's approval.
Bottom and slopes of opencut excavation on which concrete is to be placed, shall be finished according to
the established lines and slopes. To avoid loosening of the soil, heavy equipment such as bulldozers or
power shovels shall not operate within 30 cm of the final lines of the excavation bottom. The last 30 cm
shall be excavated by means of hand tools or light machinery.
For all fills and cuts over 1.00 m in depth, sturdy stakes shall be placed at any change of direction of the
ground, but in all cases at intervals not greater than 30 m.
Excavation of the riverbed to create retaining structures for detour shall be performed in such a way that no
water can drain into any building pit. All sealing work shall be within the unit price according to the Bill of
Quantities. The Contractor shall submit to the Employer detailed information about the intended shape,
size and sealing system of the retaining structure for approval.
Dagachhu HPP Section 6 Employer's Requirements 6.2 Technical Specifications
Chapter 04 Earth and Rockwork - 4
If somewhere, and for any reason, excavations are executed beyond the established lines and without the
Employer's previous approval, the Conuactor shall backfill with rubble concrete or other approved material
at his own expense, the volume corresponding to over-excavation, He will not receive payment for over-
excavations or the backfilling thereof.
Cavities or over-excavations at the bottom or at the sides of rock excavations against which concrete is to
be placed, whether due to lack of care on the pan of the Contractor when making the excavation, or due to
the removal of materials damaged through an excess of explosives when effecting the blasting, or by the
use of unsuitable excavation systems, without the Employer's approval, shall be fully backfilled at the
Contractor's expense, with concrete of the same quality as the concrete ofthe suucture to be erected in this
place.
The waste disposal areas and disposal of the excavated materials shall be subjed to the approval of the
Employer. Waste disposal areas shall be located in those places where they do not interfere either with tlie
natmal flow of water or with future strucnvff and where they cannot impair the general appearance of the
completed shucmes or impede access to the diffeient structures, and shall be maintained and left in such
condition that they present a neat and orderly appearance and blend with the surrounding topography.
The cost of the transportation of materials from the excavations to their final destination whether in the
Work or in tlie waste disposal areas, including any necessary and approved tempomy stockpiling and the
additional loading and transporting operations, are included in the Contract price.
2.3.6 BacMlling
Foundations and srmcnues shall be backfilled with approved material compacted in layers by suitable
equipment until optimum stability has been obtained to he satisfaction of the Employer. Compacting shall
be carried out with special care by means of pneumatic or mechanical tampers or other compactors of a
type previously proved by the Employer to avoid damage lo structures.
Surfaces receiving fill layers shall. if smooth, be previously scarified to obtain a good key between the new
fill layer and the sub grade.
Fill shall not be deposited under water without the Employer's pennission. This permission will not
normally be granted for c o h e s i ~soils or for fill of any kind where the standing water, in the opinion of the
Employer, can be pumped out or diverted. Permission may be granted to place rock fill by random
dumping in areas where the depth of water is greater than 50 cm but the methods and quality of the fill
material shall be subject to approval and when the fill level is 50 cm above the water surface, it shall be
compacted until there is no discernible settlement under the equipment used for placing or compacting fill.
Thereafter. normal backfilling and compaction shall be resumed.
Where swamps, marshes, bogs OI other similar wet areas have to be traversed by the Works, they shall be
drained as directed by the Employer according to the materials and conditions encountered. Prior to the
fonnation of backfilling, embankments, fills, etc., or any unsuitable materials occurring on the Site, shall
be removed to such depths and widths as may be directed by the Employer and the resultant excavations
shall be properly backfilled with suitable and approved excavated materials and shall be dewsited and
Dagnchhu HPP Sccrion 6 - Ernplnyn-sRequirements 6.1Techniclll Sp~vifications
Chapter 04 Earth and Roekwnrk - 6
Where backfilling is to be placed on steep sloping ground, the surface of the ground shall be benched in
steps or trenches as directed by the Employer, or where the ground is wet or spongy or likely to be
detrimentally affected by water. the Contractor shall remove unsuitable material and if necessary under-
drain the Site as may be directed by the Employer before benching and m c h i n g is carried out.
2.3.7 Blasting
Fuses, detonators or blasting caps shall not be m s p m e d or stored with dynamite or other explosives
under any circumstances. The location and desiw of the storage places, the transportation methods and the
precautions that shall be taken to prevent accidents shall be subject to the Employer's or the security forces'
approval, but it is understood that this approval does not exempt the Contractor of his responsibility with
regard to the handling of dynamite or other explosives.
Drilling and blasting plans shall be submitted well in advance for d ~ eEmployer's approval prior to
commencement of any blasting work.
All blasting shall be camed out carefully by approved experts only and the Contractor shall be fully liable
for any claims arising from damages or alleged damages, injury to the public, etc., due to blasting.
Experts for blasting shall be named to the Employer prior to the perfonnance of works
The Contractor shall insure with an approved insurance company against all claims with respect to
damages and injury arising from blasting.
The Contractor shall not obtain or make use of any explosives without the expressed permission in uliting
of the security forces or other authorities concerned.
The Contractor shall comply strictly with the replations as required by the authorities regarding purchase,
storage, issuance and use of explosives and transport of the same to and from the Site. and shall be deemed
to have included in his Bid all costs arising fmm supervision of blasting by security forces.
Blasting shaU fiuthennore be strictly and in every case subject to the Employer's permission.
When blasting is wmed out, trees, sf~~cfures,
etc. in exposed position shall be adequately protected from
damage without additional payment.
Drilling and blasting shall be arranged and, where necessary, the rock being blasted shall be protected so as
to prevent any scattering of mck liable to cause injury lo the public or damage to dwellings, buildings and
other property and the Works.
Blasting shall be carried out carefully, the methods shall be such that shock and vibration will be
minimized and the loosening of rock surfaces that are to remain intact will be avoided, particularly in those
cases where concrete is to be placed directly against these rock surfaces.
Modem controlled blasting methods such as pre-splitting. cushion blasting, smooth blasting, and where
applicable line drilling, shall be used.
The Employer may even order modified exploive charges or excavation without explosives. All these
alternatives shall be included in the relevant items of the Bill of Quantities.
During thunderstorms and other elechical disturbances, no charging or firing will be permitted.
Blasting shall be carried out at specified times to be agreed upon by the Contractor and the Employer.
Sufficient notices and bamers sllall be erected and immediately before blasting adequate warning shall be
given to workers on the Site and to tbe public so that no one may come within h e danger zone, until
blasting is finished. Upon completion of blasting an "all clear" signal shall be given. This signal Shall be
withheld by the responsible blasting master until he is satisfied that all charges loaded have been detonated
and that no delayed explosions or misfiring can be expected. The blasting master has to inform and
perform the alarm system to all other workers on Site. Adequate warning, as mentioned above, shall be
given, and the portion of the Site shall be cleared before electrical resistance measuring or testing of the
firing line is carried out.
The Contractor shall record on a p d forms, all blasting events including location, time, charge, purpose.
etc. These records shall he available to the Employer at any time.
When directed by the Etnployer, prior to each hlast in areas within 200 m of permanent structures, the
Contractor shall submit information to the Employer, about location of blast, number and depth of holes,
weight and types of powder loaded per hole, delays used in the blast. method ofwiring the blast, kilograms
of powder per delay, etc.
The Contractor shall be liable for any damage caused by scattering of rock, boulders or other material
being blasted and for the scattehg of any material whatsoever overlying, or in the immediate vicinity of
the rock, boulder or other material, which is being blasted, and all such fragment shall be removed.
Underwater blasting will not be permitted beneath waters in contact with pennanent st~uctutes.
Tbe Contractor shall follow the Bhutan Rules and Regulations for Blasting, issued by the Ministq of
Home and Cultural Affairs (MoHCA), a copy of which can he obtained from the above Ministry.
3.1 Embankment
3.1.1 General
3.1.2.1 General
The miscellaneous fill portions of embankment such as core, filter, rock zones, etc., shall be constructed of
selected/approvedmaterials from excavation for structures on the Work, from quarries or borrow areas.
The location and extent of all quarries and borrow pits within the designated areas shall be subject to the
approval of the Employer.
The Employer reserves the right to modify the limits or location of quarries and borrow pits within the
limits of the designated areas as shown on the drawings in order to obtain suitable material and to minimize
smpping o p e d o n s and the amount of waste material. All materials used to form dam embankment shall
meet the requirements of the pertinent tests described under "Test and Properties" hereunder or as directed
by the Employer.
The quantity and quality of the embankment material in its borrow area shall be investigated by means of
exploration in an adequate form before and during excavation and by laboratory and field tests.
a r h W I miurn u \ p n Y - n r i o n 6 + 2 ~ r p a m m h k h . p . p . p W ~ h Bmchnk.donIuI
,. ,
,, ,...
.
"x_
.\ ,z; <,.,.,\;
:..>
,
\*---,
Dagachhu HPP Section 6 Employer's Requirements 6.2 Technical Specifications
Chapter 04 Earth and Rockwork - I I
The suitability of quarried and excavated rock shall be tested for approval before and after placing and
compaction prior to commencement of construction.
3.13 Equipment
3.13.2 -
Compaction equipment general
The type of compaction equipment used for the various types of fill shall be in accordance with what is
specified under Execution of work. In principle, the compaction equipment shall be suitable to achieve the
required compaction rates in the most economic way. Where a piece of equipment is identified by trial fill,
the Contractor may substitute this machine, provided that he demonstrates by means of tests, that the
desired and specified properties of the fill are equal to that which can be achieved with the specified
machine. The burden of proof for attempted substitutions and the cost thereof shall be borne by the
Contractor. Written approval to substitute machinery must be obtained from the Employer prior to such
substitution. Compaction equipment, which is utilized in construction of the fill, shall be maintained in
accordance with the manufacturer's instructions.
32.1 General
-
The divisions between zones of the dam embankment shall be determined in the execution design. The
divisions of the zones shall be subject to variation at any time prior to or during construction if, the
conditions of the quany, borrow area, character and quantity of materials necessitate such variations. The
Contractor shall follow such necessities for variations.
The dam embankment shall be constructed to the lines and grades as required. A sufficient amount of extra
embankment shall be placed to compensate for settlement.
Camber on the crest of the dam embankment as well'as any extra embankment for other settlement during
construction shall not be subject to extra payment.
The embankment of the dam shall, in principle, be constructed in a manner, which will ensure the rise of
the dam in a uniform and even height throughout the dam at any stage of the work during consmction.
@,
yer, to the end that the coarser fraction in the fill are increased towards the downstream slopes.
5- , LA1 '
-
W ~ U o l l d ~ d U m I a b = ~ ~ 6 ~ a d n i s l l ~ ~ o Y ~ r r 0 ( m b b m d n a n . c * r i ~
,,,\.-.;-.
.,
19
- 3,
;
\
Dagachhu HPP Section 6 - Employr~~s
Rcquiremmfs : 6.2 Technical Spcn'fiwfians
Chspm W EYth and Rockwork 14-
Before placing embanlanent material on the foundation and on the surface of the already placed fill, each
portion in the entire area shall be properly moistened, compacted, -mded and the surface scarified in case
of fme-grained material before the following litl is placed.
Successive layas shall not be placed until the layer under the construction has been pmperly compacted.
The embankment shall, in principle, be consrmcted in a manner, \n,hich will ensure the rise of the fill in a
uniform and even height throughout the embankment at any stage of the work during consauction. The fill
of each lift shall be moistened, if required, and compacted in specified lift heights and by passing suitable
equipment, to reach the specified density.
No fill shall be placed on surfaces with pools and puddles.
312.8 Overproduction of f ~ s
In case production rates of fill material are larger than the rate of placing and compaction, the Contractor
shall adjust the production rate to avoid larger stochpilingand double or multiple handling of fill material.
bd-l.le4l..n.laI m a * n a h i . h l , m m - ~ ~ ~ m ~ i ~ 2 - l d s h m ~ a I t ( d & m h d . r o O I
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 04 Earth and Rockwork - 15
The placing and distribution of the applicable materials throughout the embankment shall be such that the
fills are free from inhomogeneities like lenses. pockets, streaks or layers of materials. differing
substantially in texture and gradation from the material specified and required. The combined excavation,
blending, treatment and placing operations for permanent construction shall be performed in the most
efficient manner, in order to reach the required degree of compaction, density and stability.
The optimum thickness of fill layers and the necessary number of passes and the required optimum water
content shall be determined in test fills during construction work.
lrmmnlrUur 1 clvll v o r h U U I ~ i u LW
m i s - m b n 6rmUZlrrhnlnl r ~ l f l r n ~ o m k b ~ ! e r W ca~r n
a chh o r i . t m z h I L U
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 04 Eanh and Rockwork - 16
Tf the surface of the prepared foundation or the compacted surface of any layer to fill is too dry, too wet or
too smooth for proper bond of the succeeding layer. the surface shall be properly prepared by wetting,
drying, scarifying or other means of treatment to suit the particular situation and prepare the surface.
In general, the zones of sealing material shall be executed and maintained approximately in horizontal
layers but, if necessary, each compacted layer shall be sloped adequately towards the upstream or
downsueam side of the embankment to facilitate draining. The thickness of compacted layers shall not
exceed 20 cm. Each layer shall be compacted to not less than 98% of Proctor-density.
Single cobbles or rock fragments, which may prevent proper compaction, shall be removed.
The type, gradation, moisture content and density of the material, when neatly in place and ready for
approval, shall meet the requirements.
These requirements shall be met by the most efficient types of equipment, thickness of lifts, number of
passes of compaction equipment and the suitable material or mixture of different materials.
The material shall be compacted by landfill tamping compactor andlor rubber aired roller by several passes
in accordance with the results from initial compaction tests. One pass shall be understood hereunder as the
single pass in only one direction.
Individual floating stones in earth fill material exceeding in grain-size of 10 cm shall be removed prior to
compaction. At contact areas with foundation rock and structures the maximum size of individual stones
shall be limited to 5 cm.
During construction, tests shall be carried out to determine the gradation. water content, density and
permeability of the placed material.
The shape of the transition and drainage layer constructed of filter material as a whole shall be true to the
lines and grades as required. The filter material shall always be placed approximately to the same elevation
as the adjacent zones and shall not exceed 40 cm in depth before being compacted by vibratory or rubber
tired roller by at least 4 single passes to 80% relative density on an average.
The number of passes on each layer for this purpose and the type of rollers shall be proven suitable by
demonstration of test fill.
It is noted, that "horizontal filter" applies to layers of filter material up to an inclination of 15 degrees
against horizontal and for the Innsition zone in the abutment also where the surface is inclined. Inclined
layers of filter material are inclined with more than 15 degrees against the horizontal.
If the embankment work is discontinued for a comparatively lengthy time, the surface of the filter-layer
shall he worked with scarifier or other suitable equipment, sprinkled and treated before the next layer of
material being placed.
Large rock and boulders shall be separated and used in the dam embankment where suitable, so as not to
interfere with workability and purpose.
During construction, tests shall be performed to determine the gradation, density, permeability, etc., of the
different type of layers.
3.3.1 General
With the assistance of the Employer, the Contractor shall prepare sheets for numerical and statistical
analysis of the field and laboratory tests as required. By means of these analyses all necessary reports of
working procedures, quantity and quality conlrols shall be elaborated by the Convactor in accordance with
the specifications.
The field and laboratory tests, shall consist of compaction and density tests, water content, grain size
distributions analysis combined with hydrometer analysis, and if required, direct shear tests, tri-axial shear
tests, Proctor tests, permeability tests and all standard soil mechanic tests as required by the Employer.
This includes all large-scale tests by means of trial fills and compaction tests for quality control for all
kinds of embankment fill material.
i
b u h l d h m n t 3 W c 1 c b w l m r k M 1 vo>ttrc -1 . ~ ~ C ~r ~n ~ ~ ~ ~ ~ ~ ~ I I ~ F ~ ~ ~ ~ ~ ~ ~ ~ ( ~ ~ ~ ~ P P P M C ~ ~ B B B L L L L L . ~ X I I I
Dagachhu HPP Seetion 6 - Employeis Requirements , 0.2 Twhnical Speciii~otiom
Chapter 04 EMh and Ruckwork - I0
The Contractor shall consider the possibility of carrying out blasting tests at Ole quames supplying
embadanent fills for obtaining the most favorable rock size gradation required for the fills without funher
crushing. screening and blending. The costs for these tests shall be considered to be included in the unit
rates for embankment fills and no extra payment will be granted. Blasting tests shall be subject to approval
by the Employer.
~-~-. - --- ~
grading tests during blasting to modify blasting methods to obtain the desired gradation.
oagaazhhuHPP -
Section 6 Employer's Ruquirerncncs : 6 2 Technical Specifications
Chapter 04 Earth and Rockwork - 20
3A Auxiliary Works
3.4.1 General
Unless otherwise specified, all and any kind of works, personnel, equipment, machinery, matwial, safety
measures, drainage, etc., required for the completion of the work specified hereunder as well as, and if so
requested by the Employer shall be provided by the Contractor.
Irrn"lo,Lm.l&lrrl.aMmklrtl ~nlumrElnanG-hhplldlldbnnbnn?b2~ab"~l~flC.l-~
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 04 Eanh and Rockwork - 21
4 SLOPE PROTECTION
4.1 General
Rip-rap shall be taken from hard rock layers of quarries or rock excavation or underground rock
excavation. The rock shall be compact, firmly bound, of uniform grain texture and absolutely weather-
resistant, shall nor have cracks, holes, laminations of detrimental materials.
The rock blocks shall be of natural irregular cubic shape and of the size as specified hereunder. Thin-sliced
blocks shall not be accepted. Any blocks covered by impurities shall be cleaned thoroughly before being
used. Moisture absorption of rock blocks shall be limited to such a quantity that any cracking, bursting. and
chipping as a result of wave action or weather influence will not occur.
Unless indicated otherwise, the Contractor shall submit rock samples to be used in the slope protection for
the approval of the Employer.
The use of rocks mixed with soil, sand, clay and decomposed or decomposable materials, or the use of
small rock fragments shall not be permitted. The Contractor shall not use weathered, Fractured, dirty,
that, in the Employer's opinion, is not sufficiently
demand compensation different from the price
Rock not meeting the specified requirements will be rejected and the Contractor shall without delay follow
insttuctions to remove such rock material from the Site. In the event of his failing to do so, the material
will be removed by the Employer at the Contractor's expense.
The Contractor shall in no circumstance be entitled to payment for rock material placed which has not been
accepted or approved.
Rip-rap Classes
The classes of rip-rap as described below shall be applied
Unit Class I C l a s I1
2,000
Weight of largest individual block 3,500
Minimum weight
Composition of Rip-rap
The rip-rap shall have the following composition:
- the largest individual block shall not exceed the above given figure
Rip-rap Class I and 11
- 50% of blocks by weight shall weigh more than the rated weight
- 50% of blocks by weight to be uniformly distributed shall weigh between the minimum and the
rated weight.
Rip-rap Class 111
- 50% of blocks by weight shall have a size larger than the rated size
- 50% of material by weight shall have sizes between the minimum and the rated size and it shall be
so graded and uniformly mixed with the larger blocks that a compact layer is obtained.
All particles shall he angular and cubical mixed with wedge-seized particles to enable proper filling of the
interstices between the larger stones.
Dagachhu HPP Section 6 - Employer's Rcquiremcnts 6.2 Technical Specifications
Chapter 04 Eanh and Rockwork - 23
4.23 Shotcrete
Shotcrete, which will be used for slope protection, shall be in accordance with the specification described
in Clause 4.3.9.
4.3.1 General
Material to be used for slope protection shall be excavated, quanied or fabricated and transported to points
of use as specified and placed within the limits of the specific Site of work.
The Contractor shall have available all required equipment and machinery, such as heavyduty clamshell or
dragline, for handling and suitable placing of rock blocks in the respective layers.
Before placing of slope protection, the slope shall be prepared as specified in Sub-chapters "Clearing and
Grubbing" and "Open-cut Excavation".
Unless otherwise stipulated under the items covering bank protection work, the Contractor shall safely
divert any ground or surface water.
To prevent damage to slope protection, structures of any kind, etc., in the event of floods, the Contractor
shall make all possible efforts to protect unfinished slopes, embankment slopes, etc., by temporary coven
or other suitable means. The material required for this purpose shall be stored by the Contractor near the
place of use.
Unless otherwise stipulated, the Contractor shall safely divert any ground or surface water without extra
payment for this work.
Dagachhu HPP Section 6 Employer's Requirements 6.2 Technical Specifications
Chapter 04 Eanh and Rockwork - 24
43.3 Rip-rap
The rock blocks in rip-rap as specified under Clause 4.2.1 need not to be compacted but shall be placed and
graded off in a manner to insure that the larger rock blocks are uniformly distributed and that the smaller
rock blocks serve to fill the interstices between the larger blocks in a manner that will result in compact
uniform layers of rip-rap of the required thickness.
Placement of rip-rap in layers parallel to the slope to obtain the required thickness shall not be allowed;
placement shall be done in such a way as to obtain the required thickness at each level in a single
operation.
Placement of the rip-rap shall not be done by methods, which may result in segregation of the rock by sizes
or cause damage to the layer serving as the foundation for the rip-rap on the embankment.
Hand placing will be required only to the extent necessary to secure the results specified above. However,
the Contractor shall at any time during the construction period and the guarantee period upon the request of
the Employer place new material or correct the existing material.
Unless otherwise specified, rip-rap shall be bedded in a continuous layer. The lowest part of the protected
area shall be made up of boulders, well placed in a ditch, forming a protective belt for the rest of the rip-
rap. Except for the rock fragments and spalls to be used as wedges, the rocks shall be irregular cubic-
shapcd and the smallest dimension of a given piece shall not be less than one-third of the largest
dimension. Funhermore, no element whose largest dimension is smaller than half the thickness of the rip-
rap, shall be placed in it. Spalls and small rock fragments shall not be piled in cenain places to make up for
the volume of larger rocks. The finishing tolerances for the rip-rap outer layers shall be equivalent to more
or less a founh of the thickness of such rip-rap layer. provided the differences in either direction are not
continuous over an area greater than twenty square meters.
Raising of selected rock fill where required shall also take place according to the progress of work of the
shell fill. The height of the shells in advance of the placing of the protective layer may be chosen by the
Conuactor so as to achieve adequate compaction, proper surface leveling and so as to prevent erosion of
the underlying shell by heavy rainfall or wave action (cofferdam). The compaction degree required shall be
as specified under Clause 3.1 as well as the tests to be applied for the fills.
43.9 Shntcrete
Placing of shotcrete for slope protection shall be as specified in Chapter 06 - Underground Excavation
43.10 Joints
Joints and holes shall be cleaned and filled with rock chips or sand or lean concrete or mortar as specified
hereunder. Large joints and holes shall he wedged with stones. Joints and holes shall be staggered so that
firm bonding will be ensured when joining the pavement by cement mortar. All rock in contact with mortar
shall be thoroughly cleaned of all adherent soil, earth or organic impurities and shall he thoroughly
removed.
The joints and holes shall be completely filled with cement mortar in a proportion 1:4, measured by
volume, with the aid of a tamping rod roughly pointed. In the event of rain, the newly prepared surface
shall be adequately protected against erosion. If requested by the Employer, any defective surfaces shall be
removed and placed afresh, and no extra payment will he made for such work.
Dagachhu HPP Section 6 Employer's Requirements 6.2 Technical Specifications
Chaptcr 04 Eanh and Rockwork - 26
43.12 Gabions
Gabions shall be provided if high strength of stone protection is required or the stone protection is used to
stabilize the slope or only small stones for protection are available.
Gabions are wire mesh boxes filled with selected gravel or rock of suitable size and shape to facilitate
packing. The grain size of the gravel or rock shall be greater than about 1.5 times the diameter of the mesh
openings, but at least 10 cm. The stone quality shall be as specified for rip-rap.
The standard type gabion shall be a flexible hotdip galvanized gabion of the type and sizes specified
below. It is made of wire mesh of the type and size and selvage as specified in the following.
The mesh shall be hexagonal woven mesh, the joints formed by twisting each pair of wires through three
half turns.
The size of the mesh shall conform to the standard specification issued by the factory and shall be not
greater than 113 of the smallest stone filled in the gabion.
All wire used in the fabrication of the gabions and in the wiring operations during construction shall be
"Mild Steel Wire", i.e., wire having an average tensile strength of 44 kg per square millimeter.
The diameter of the wire used in the fabrication of the mesh shall be 3.0 mm according to the engineering
requirements.
Test shall be made on the wire before fabrication of the gabions on a sample 30 cm long. Elongation shall
not be less than 12 %.
All wires used in the fabrication of the gabions and in the wiring operations during consuuction shall be
galvanized. The minimum weight of the zinc coating shall be 275 gr/m2.
In addition the wire shall be plastic-coated.
All edges of the standard gabions including end panels and the diaphragms, if any, shall be mechanically
selvaged in such a way as to prevent unraveling of the mesh and to develop the full strength of the mesh.
The wire used for the selvage shall have a diameter greater than that of the wire used to form the mesh.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 04 Eanh and Rockwork - 27
- For wire having a diameter of 3.0 mm, the selvage shall be of wire having a diameter equal to or
greater than 3.9 mm.
The standard gabions shall have the following dimensions:
- Length = 2.0 or 3.0 or 4.0 m
- Width = 1.0 m
- Height = 0.3 or 0.5 or 1.0 m
Sufficient lacing and connecting wire shall be supplied with the gabions for all wiring operations to be
carried out in the construction of the gahion work. The quantity of such wire is estimated to be 8 percent of
the gabions supplied.
The diameter of lacing wire shall be:
- 2.4 mm for the gabions made of wire gauge 3.0 mm
According to the engineering requirements, the gabions might incorporate diaphragms to form cells having
a length not greater than one time and half the width of the gabion.
A tolerance on the diameters of all wire in the above paragraphs of + 2.5 percent is permitted
The length of the gahions is subject to a tolerance of + 3% and the height and the width to a tolerance of
+ 5%.
In case stabilization and anchoring of gabions are required, such stabilization and anchoring (including
provision of "dead men") shall be performed.
Contracton Alternative Proposal
If not otherwise specified, the Convactor shall submit a proposal of the type and dimension of gabions, the
stone fill (type, strength, grain size), the method of placing and the time schedule for delivery andlor
construction. He shall not commence with the order andlor construction of gabions prior to the approval of
the Employer.
All threads shall be free of rust and burrs and the nut shall be free running on the bolt. The threads of the
nut and of the projecting end of the bolt, and the surfaces of the ball, machine and taper washers shall be
lubricated before tightening the nut. The expansion anchor shall be firmly seated and tightened and where
the lubricant is plastic grease, the nut on the projecting end of the bolt shall be tightened to a torque of
340 Nm (34.5 kgm). Where the lubricant is wax mastic the nut shall be tightened to a torque of 240 Nm
(24.5 kgm). The nut shall be tightened with a controlled torque impact wrench, which can be set to give a
range of torque at cutdff up to at least 340 Nm (34.5 kgm). If the bolt is tensioned by a direct tensioning
method it shall be tensioned to achieve a final load of 6 tons.
After initial installation, the Contractor shall ensure that the rock bolts continue to act as effective supports
by periodically testing rock bolts and, if necessary. retightening to the directed torque or tension. The
installations shall be tested and the bolts retightened.
If grouting of rock bolts is specified, such grouting shall only be performed immediately after final check.
4.4.1 General
Unless otherwise specified, all and any kind of works, materials, s e ~ c e s safety
, measures, etc., required
for the completion ef the Work as well as, and if so requested by the Employer, all tests and samples shall
be executed by the Contractor.
4.4.4 Gabions
Supply and placing of gabions shall include ail works for a complete slope protection by these means,
which shall include all the following operation but not being limited to:
- producing the required rock material
- manufacturing the gabions
- provision of an adequate location for manufacturing the gabions
- transportation and placing
- preparation of the foundations. leveling and compacting if required
- tying and anchoring works where required
6.2 T E C H N I C A L S P E C I F I C A T I O N S
Chapter 05
DEWATERING
TABLE OF CONTENTS
Chapter 05
DEWATERING
PAGE
1 GENERAL ..................................................................................................................................... 1
1.1 General Requirements ........................................................................................................ 1
1.2 Alteration of System ............................................................................................................... 1
1.3 Proposal of Dewatering System............................................................................................ 1
1.4 Failure of Operation ................................................................................................................ 1
...
1.5 Respons~b~hty ...................... :.................................................................................................. 1
1.6 Completion of Dewatering ..................................................................................................... 2
1.7 Scope ...................................................................................................................................... 2
2 MATERIALS AND EQUIPMENT ............................................................................................... 2
2.1 General....................................................................................................................................2
2.2 Submittals ............................................................................................................................... 2
2.2.1 Detailed data .............................................................................................................. 2
2.2.2 Test reports ................................................................................................................ 3
2.2.3 Certificates ................................................................................................................ 3
2.2.4 Construction and method drawings ........................................................................... 3
2.3 Details of Material and Equipment....................................................................................... 3
2.3.1 General ...................................................................................................................... 3
2.3.2 Diversion tunnel ....................................................................................................... 3
2.3.3 Open Pit Dewatering ................................................................................................. 3
2.3.4 Well point system ...................................................................................................... 3
2.3.5 Deep well systems ..................................................................................................... 4
2.3.6 Vacuum pumps .......................................................................................................... 4
2.3.7 Pipes and filters ..................................................................................................... 4
3 EXECUTION OF WORK ............................................................................................................ 4
3.1 General....................................................................................................................................4
3.2 Start and Duration of Dewatering ........................................................................................... 4
3.3 Dewatering Equipment ........................................................................................................... 4
3.4 Pump sumps and Channels ..................................................................................................... 5
3.5 Precaution to Avoid Dewatering............................................................................................. S
3.6
..
Ready-for-Service Condlhon ..................................................................................................S
3.7 Leakage................................................................................................................................... 5
Environmental Requirements .......................................................... :......................................S
1 GENERAL
1.5 Responsibility
The Contractor shall be solely responsible for personnel accidents and for damages and inconveniences
that may be suffered by his equipment or materials, the equipment and materials of the Lot 2 E&M
Contractor, or the executed or in-execution works, due to insufficient or inadequate control of seepage,
poor operation, or failure of the dewatering system, insufficient capacity of the pumping system, lack of
reserve units or any other reason imputable to the negligence of the Contractor or to the poor maintenance
and operation of his equipment.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 05 Dewatering - 2
1.7 Scope
This Specification covers methods and techniques of ground and surface water control by way of either:
- coffer dams
- diversion tunnel
- diversion channel
- open pit dewateringlpumping
- well point systems
- deep well systems
- deep well systems with application of vacuum
- pressure relief pumping
- removal of surface water during construction
- other applicable methods whichever system appears suitable for the existing conditions
The scope shall include the design and calculation of the dewatering system and the submission of a
proposed method and technique to the Employer for approval prior to execution.
2.1 General
Materials and equipment to be provided by the Conmctor shall be in good conditions and adequate to meet
the requirements. Materials, which are to be permanently, incorporated in any smcture shall be new and
unused, shall be in accordance with accepted standards, and shall not have been previously used for such
purposes as dewatering during construction.
2.2 Submittals
2.23 Certificates
The Contractor shall submit certificates of compliance with applicable standards in respect of the
equipment provided for the dewatering systems. The Contractor shall prepare a list of all equipment and
materials issued for the installation of the dewatering system.
23.1 General
All equipment, machinery and power supply systems for the plant to be used for dewatering the
construction pit trenches and underground structures shall be provided only from manufacturers whose
products have already proven to be reliable on other sites and been successfully in operation.
All equipment, instruments, machines, tools, etc., required for the execution of the work shall be of such
quality as to withstand the climatic conditions of this region. They shall be kept serviceable and in good
repair throughout the operating periods.
The choice of type, capacity and amount of equipment, and determination of locations for well points and
deep wells shall be left to the discretion of the Contractor.
3 EXECUTION OF WORK
3.1 General
A working schedule with explanatory reports shall be submitted prior to commencement of the relevant
works. This schedule shall show the quantity, type, capacity, stand-by equipment, age, condition,
arrangement, location, etc., of the proposed equipment.
The schedule and any amendments made thereto during the life of the Construction phase shall be subject
to the approval of the Employer.
The Contractor is obliged to inform the Employer immediately of any symptoms of risk of subsidence or
collapse.
The safety measures required by the Employer shall be performed by the Contractor without delay
Pumps and pipes may be provided at the option of the Contractor but the requirements of dewatering shall
be guaranteed. The provision of pumps shall include the complete excavation of pump sumps as required,
including sheeting, bracing, etc., the installation of electrical connections or the supply of fuel, the disposal
of water, and all other elements required to ensure an effective operational system. The pumps shall be
located away from permanent structures.
Supply of lubricants, accessories, spare parts, etc., operation and maintenance including all additional
works required for continuous functioning of the dewatering system, transport, including any intermediate
storage. as well as installation and removal of all dewatering equipment and the sealing of pipes, etc., shall
be included in the works.
Upon completion of dewatering work, all pipes shall be closed off and the pump sumps shall be removed
and tightly filled by adequate materials.
3.7 Leakage
Block+uts and pipe connections through structures and their closure, proper grouting of joints, etc.. or
repairs in the event of leakage shall be the responsibility of the Contractor.
c
hid drrurnnauo, Irluil WOrXrUo? I rnlum iw i l - x m a n 6q\6.2lrrhnlcs~rpcri6caCiomihaplerOIhrrmme.du.~lul.OS
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 05 Dewatering - 6
5 AUXILIARY WORKS
The following detailed works are, among otbers, to be considmed as part of dewatering measures and
included in the costs for it:
all pumping equipment, pipes, channels, flumes, conduits, drajns, pump sumps;
levee banks,cofferdams, guide walls, settling ponds and the like;
all fuels, lubricants, power supply and the like required for operation of pumping systems;
all labor, operator costs, including night- and holiday shifts, when required;
stand-by equipment;
maintaining of wata-tight slurry trenches or other measures preventing seepage into the pit:
provision of adequate discharge channels or pipes fmm tunnel mouth or shaft exit to accepted
collection drains;
divusion tunnel. if applied
making good any damages h m failures of installed equipment, or inadequate pmvisions for
dewatering;
sheet pile walls for pump sumps includmg its excavation, if it is only needed for dewatering
purposes;
~ c o r d i i gand monitoring of measured data such as amount of water flow, level ofwater table;
test run of the system.
6.1 General
?he entire dewatering plant shall include design, furnishing: bansport, installation, depreciation,
maintenance, operation, supplementations, improvements and relocations of the plants as well as
consmction of cofferdams, pits, trenches, pipes, etc., and restoration of the Site including all irs
accessories.
If dewatering is not defined within the Bill of Quantities, the costs shall be included within the mpective
lump sum items.
DHP
..
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation
Chapter 06
UNDERGROUND EXCAVATION
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation .ii
T A B L E OF C O N T E N T S
Lot 1 Civil Works. Volume I1
Section 6.2 Technical Specifications
Chapter 06
UNDERGROUND EXCAVATION
PAGE
1 EXCAVATION ............................................................................................................................ 1
1.I General ................................................................................................................................. 1
1.1.1 General Requirements ......................................................................................... 1
1.1.2 New Austrian Tunnelling Method (NATM) ........................................................ 1
1.1.3 Proof of rock behaviour ...................................................................................... 1
1.1.4 Lighting underground ...........................................................................................
1
1.1.5 Supply of detailed documents by the Contractor ................................................. 2
I .2 Materials and Equipment .....................................................................................................
2
1.2.1 General ...................................................2
1.2.2 Equipment ............................................................................................................ 3
. .
1.2.3 systems ..............................................................................................
Vent~lat~ng 3
1.2.4 Use of combustion engines .................................................................................. 3
1.2.5 Explosives and Detonator
1.2.6 Lightning indication system
1.2.7 Traffic lights
1.3 Execution of Work ............................................................................................................... 4
1.3.1 General ................................................................................................................. 4
1.3.2 Setting-out ............................................................................................................ 4
1.3.3 Method of excavation ........................................................................................... 4
1.3.4 Continuous Working
1.3.5 Mucking ............................................................................................................... 5
I .3.6 Field trials for blasting technique ....................................................................... 5
1.3.7 Zoning ..................................................................................................................5
1.3.8 Supporting faces of excavation ............................................................................
5
1.3.9 Implementation of Tunnel Support Works ........................................................... 6
Excavation through earth, weak or weathered rock, and rock ..........
,
d *urrmn;dPr czr,i r n . k l 1 , a lLaddrrd.,,,, !. I al!;nr a, Far; ::~n:x>n Snjbd*?lC"rn nu. ~khlp,.r"b u"diRmund.l;rarrrx>.:ru "!
Dagachhu HPP Section 6 .Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation .l i i
...\
.
. Auxiliary Works ......................... 18
.. ' [i+;
.! ;-
* .
...
~.
.
j\1356*grhhu bddurumnlr<i~r1 civil wliikrilm ILrddrndaliil 1 Vokm si- 6 m q W n d u r mo 2khap:r: U6 c ? l i c ~ r n u ~ c
:I-rclul;
Dagachhu HPP Section 6 .Employer's Requirements 6.2 Technical Specificalions
Chapter 06 Underground Excavation . iv
. . ..
1.6.2 Determinat~onof quant~tles.....................
........................................................
20
1.6.3 Overbreak due to geological conditions .............................................................
20
1.6.4 Payment of underground excavation ..................................................................20
1.6.5 Transport ......................................................................................................... I
2.1 General............................................................................................................................... 22
2.1.1 Scope of work .................................................................................................. 22
..
2.1.2 Definition ........................................................................................................... 22
2.1.3 Quality requirements .......................................................................................... 22
2.2 Material and Equipment ....................................... 22
2.2.1 Mix Design 22
2.2.2 Batching. Mixing and Transportation ................................................................ 23
2.2.3 Cement ............................................................................................................... 24
2.2.4 Aggregates .......................................................................................................... 24
2.2.5 Additives ............................................................................................................ 26
2.2.6 Water .............................. ..................................................................................26
2.2.7 Plant .................................................................................................................... 26
2.3 Execution of Work ............................................................................................................. 26
2.3.1 Dry Mix Method................................................................................................. 26
2.3.2 Commencement of work ................................................................................. 26
2.3.3 Preparation of surfaces ...... 7
2.3.4 Mixing ................................................................................................................
27
2.3.5 General requirements for placing shotcrete ........................................................27
2.3.6 Details on shotcrete operations .......................................................................... 28
2.3.7 Shotcreting in underground structures ...............................................................28
2.3.8 Reboun
2.3.9 Drain holes
2.3.10 Construction joints
2.3.1 1 Layers of shotcrete
. .
2.3.12 Surface fintsh of shotcrete .................................................................................. 29
2.3.13 Curing ................................................................................................................. 29
Tests and Properties ................................. 29
Compatibility Test - Laboratory Tests ............................................................... 29
' ~ z ! 24.1
. Suitability Tests - Field Trials ............................................................................ 30
.4.3 Quality Control ...............................................................................
! .v.
b i d ~ x ~ ~ m : M~.,.<.+!,c !A ~ & ~! x%bmc
\ I < :X
!panLv~%ec$x>n
6 e q b d d e n w r n m lkhapc<, 6 undcrgmun6 e x c n v ~ x ~ n ~0 x, s
Dagachhu HPP Section 6 .Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation .v
3 REINFORCING STEEL........................................................................................................... 35
3.1 General ............................................................................................................................... 35
3.2 Materials and Equipment ...................................................................................................
35
3.2.1 Welded Wire Fabric (Wire Mesh) ...................................................................... 35
3.2.2 Re-Bars ...............................................................................................................35
3.3 Execution of Work .............................................................................................................35
3.3.1 Wire Mesh Installation ......................................................................................35
3.3.2 Re-Bars Installation ............................................................................................ 35
3.4 Tests and Properties ...........................................................................................................
35
3.5
..
Aux~liaryWork ..................................................................................................................35
3.6 Measurement and Payment ................................................................................................36
3.6.1 Wire-mesh. reinforcement bars for Powerhouse and Transformer
Caverns ...............................................................................................................36
3.6.2 Wire-mesh. reinforcement bars for Support Classes .......................................... 36
..... . /
.,
\
\ 7 c
...
.
! ;-
,
, ! .
.-
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - viii
9 DOWNTIMES ............................................................................................................................ 71
9.1 General ....................
..................................................................................................... 71
9.2 Measurement and payment o f downtimes .........................................................................
71
..
6.2 Technical Specifications
Dagachhu HPP Section 6 -Employer's Requirernenls
Chaoter 06 Undereround Excavation - I of 71
1 EXCAVATION
1.1 General
1.2.1 General
All equipment, materials and structural components which the Contractor is to provide for the sole purpose
of underground excavation in accordance with the requirements of the Contract and which are not
permanently incorporated in the Works may be new or used materials. if used at the Contractor's option to
the satisfaction of and upon approval by the Employer.
All materials and structural components, which the Contractor is to supply and install and which are
oermanentlv incornorated in the Works, shall be new, unless otherwise specified. All installation materials
must comply with the relevant standards and requirements regarding quality and dimensions, and must be
:rdacrdaiii: I ru:;mc il!p;ln 82~rrci.n SeqLl4.xldendumn,: 2khap.r ilh undrrpuurd e n v a : x : ~ . ? w l l l dticr SIp~OS
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Spmificatmnl
Chapter 06 Underground Excavauon - 3 of 71
13.2 Equipment
Electrical. pneumatic, or diesel driven equipment may be utilized for the different operations involved in
the underground excavation. In case the latter type is used, the Contractor shall provide the necessary
facilities to remove all noxious gases resulting from the operation of the equipment. If the diesel gas
removal system is not adequate, the Employer can request, without extra cost for the Employer, the
suspension of its operation or the necessary measures to correct the defects of the removal system.
cross-sections are too small to warrant two-lane traffic. an adequate traffic light system shall
and operated. The same applies to tunnel junctions or crossings.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chaptcr 06 Undcrgmund Excavation - 4 of 71
1.3.1 General
The working method for excavation is left to the Contractor's discretion but shall be in compliance with
Sub-clause 1.1.2. In case of Contractor's delay, the Employer reserves the right to stipulate other working
methods, to result in a speedier progress. The Contractor shall not make any extra claims for such
modifications to the working method.
Survey points, benchmarks, boundary stones and the like shall not be removed or obstructed without the
Employer's written consent. Where required additional survey points (measurements) shall be placed.
Extra benchmarks to be provided by the Contractor shall be indicated by plates, approx. 25x25 cm size,
with benchmark inscriptions written in black letters on a light background with clearly legible weatherproof
oil paint.
A binding working schedule with explanatory report shall be submitted prior to the start of excavation
work. The schedule shall show the quantity, type and capacity of the equipment provided, blasting pattern
and charges, the working method envisaged for transportation and distribution of excavated material, the
location of stockpiles and main storage areas, as well as the approximate number of site operators, etc. This
working schedule and any amendments made thereto during the duration of the Contract shall be subject to
the approval of the Employer and this basis shall be binding for underground excavation if not directed
otherwise by the Employer.
Excavation shall comply with the lines and dimensions indicated in the drawings.
The Contractor's methods for the setting-out of the work and the maintenance of correct line and level of
the tunnels shall be subject to the approval of the Employer.
13.5 Mucking
A11 muck resulting from excavations shall be removed from the sjte as soon as practicable and be placed in
disposal areas as shown on the drawings or as ordered by the Employer. The Contractor may deposit
materials on disposal areas only when there are no possibilities for its further use by him or by the
Employer.
Excavated material from the Works, which is selected by the Employer for re-use shall be placed directly in
its final position, if possible. Otherwise it may be stockpiled or deposited on site as approved by the
Employer.
Muck resulting from tunnel excavations may be crushed and stockpiled in appropriate places to be used in
any Work for which it meets the specifications under this Contract. The Employer shall be the owner of the
muck resulting from rock excavations and the Contractor cannot sell or use it in works not covered by his
Contract without the Employer's previous approval.
Other entities or persons authorized by the Employer to use materials resulting from excavations may
utilize only excess material left by the Contractor. All costs of transportation, disposal and compaction and
drainage shall be included in the unit prices for underground excavation.
13.7 Zoning
The underground excavation shall follow the dimensions and details for different sections as shown in the
Drawings. The structural supports for excavations shall be installed in the different sections in accordance
with stipulations outlined below.
The Contractor shall take into account the possible variations in the quantities and limits for the different
sections when determining his unit prices for excavation. Such variations shall not modify the terms and
unit prices and shall give no rights for other claims.
1.3.10.2 Rock
The Contractor shall execute the excavation through rock by means of any appropriate method approved by
the Employer. He shall use excavation and transportation equipment which meets the requirements stated in
these specifications and has been accepted by the Employer. Supports and/or rock bolts will be called for in
sections where the quality of the rock so indicates. The excavation and support installation operations shall
be made in a coordinated way to avoid the action of unbalanced forces on the tunnel supports. Use of
Dagachhu HPP Section 6 -Employer's Requirements
Chapter 06 Underground Excavation - 7 of 71
As the excavation advances, the rock encountered shall be observed according to its fracture conditions for
determining the length and number of boreholes, the charge of dynamite per hole and the sequence of
detonation, with the purpose of reducing the overexcavation to a minimum and maintaining the periphery
as close as possible to that shown on the Drawings. If required, core drilling ahead shall be provided to
enable the selection of any appropriate excavation and support method. A systematic and permanent
inspection of the surfaces of excavated sections shall be made to determine the quality and conditions of the
supports.
The surfaces shall be cleaned with water and air jets as ordered by the Employer in order to facilitate their
inspection. All shattered pieces of rock shall be removed and rock bolts and shotcrete shall be placed where
required to maintain the excavation in a stable position. Where the removal of shattered or loose rock is not
sufficient to exclude the possibilities of cave-ins, faces shall be supported by means of support elements
specitied in this specification, as approved or directed by the Employer. When it becomes necessary to
reinforce a section of a tunnel, etc., this operation shall be completed before continuing with the
excavation. Excavation shall be done according to the profile geometries as specified on the drawings. If
the excavated surfaces which are to be supported by a shotcrete lining, show surface irregularities and
excessive deviation from the specified profiles, it shall be made good by the Contractor at his own cost,
either by trimming of the rock faces or by extra shotcrete.
- .
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 9 of 71
Blasting shall be carried out at specified times to be agreed upon between the Contractor and the Employer.
Sufficient notices and barriers shall be erected. Immediately before blasting is due, adequate warning shall
be given. Upon completion of blasting, an "all clear" signal shall be given.
This signal shall be withheld by the responsible blasting master or blasting engineer until he is satisfied that
all charges loaded have detonated and that no more delay explosions or misfvings can be expected.
Adequate warning, as mentioned above. shall be given and the required portion of the Site shall be cleared.
before electrical resistance measuring or testing of the firing line is carried out.
The blasting engineer has to inform and perform the alarm system to all other workers on site
The Contractor shall always be sure that the rail tracks. ventilation tubes and supply lines are safely
grounded, so as to prevent danger to persons from lightning and to avoid the possibility of explosions of
loaded or unloaded charges by lightning.
.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specitications
Chapter 06 Underpound Excavation - 10 of 71
In case the detonators are electric. when preparing them outside the tunnels, the base wire ends shall
be protected with insulating caps or neoprene fittings; such insulators shall be removed after
charging the holes to make the proper connections.
Each of the prepared blasting charges shall be checked by means of a galvanometer, or a special
ohmmeter, at a prudent distance, to guarantee the continuity of the complete network.
The ends of the main wires shall be connected to the detonator immediately before the blast; the
initiation system shall be kept at a minimum distance of 200 m from the front but the personnel
dispensable shall move back further.
In case that an ignition system without electric detonators is used, the manufacturer's
recommendations shall be followed.
If the Contractor is planning to use electric detonators, he shall install lightning detectors that give
information about the atmospheric electric activity continually. The Contractor shall install alarms directly
connected to the detectors at each work front. When explosives are being charged at a front where electric
detonators are used and a storm is detected, the personnel shall be quickly moved to a prudent distance until
atmospheric conditions become normal.
1.3.21 Ventilation
The Contractor shall install, maintain and operate a temporary ventilation system for underground works.
The installation and operation of the ventilation system shall follow the excavation works to provide
breathing air conditions not detrimental to the health of the labour force.
The ventilation system may be of the forced supply or forced extraction type, including local air movers or
any combination thereof.
The design of the ventilation system shall comply with the requirements of the Technical Details and shall
be subject to the approval of the Employer.
The ventilation system shall be operated during the excavation and concreting phase in accordance with the
requirements of the Technical Details but shall not be removed thereafter without the written permission of
the Employer.
All power and lighting wires shall be installed and maintained in optimal conditions of insulation and
safety.
Power and lighting cables shall be installed on one side of the tunnel and the detonator wires shall be
installed on the opposite side and sufficiently distant from telephone or communication systems wires.
All wires shall be firmly fixed on tunnel walls, by means of insulators of adequate design and capacity and
their installation shall b e made in such a way that wires do not get damaged during tunnel construction. The
minimum general lighting system shall have an intensity equivalent to that produced by a 60-Watt lamp at
6 m spacings. The lighting network voltage shall not be higher than 220 V and preferably lower; if the
Contractor so prefers, he can install a system with a high transmission voltage by means of insulated cables
of special design, acceptable to the Employer, from which the lighting network shall be derived at the
specified voltage; in this case, the Contractor shall furnish at his own cost waterproof, explosion-proof and
water-tight transformers previously approved by the Employer, for installation within the tunnels. For the
general lighting system the Contractor may use incandescent or fluorescent lamps, sodium lamps or any
other type acceptable to the Employer that provide the minimum specified intensity.
The temporary lighting shall remain in commission until tunnel construction is complete.
Without prejudice to the liability of the Contractor under the Conditions of Contract and his responsibility
to adopt all expedients for ensuring the safety of his workmen and others. the Contractor shall. in
connection with any installation for lighting, power and signalling, observe the following:
- Tunnel lighting supply underground shall be independent of the power supply for any plant or small
tools.
- All lamp holders shall be of approved nonconductive material.
- All wiring shall be properly insulated with vulcanized rubber or other approved material, particular
care being taken to insulate connections to the approval by the Employer.
- All wiring shall be securely fixed clear of any moving plant, man access, source of heat or other
likely damage.
- All circuits shall be sub-divided and protected by fuses of low current rating.
- Lighting in running tunnels shall generally consist of not less than one 60-Wall lamp at 6 m centres
or equivalent with proportionate increase in enlargements.
- Power supplies to fixed plant and equipment, tunnelling machines and the like shall be protected
adequately against unauthorized or accidental damage and shall be marked with the liable maximum
voltage. All cables shall be proof to continuous immersion in water, contact with hydraulic fluid, and
vibration from moving machinery, heat, abrasion and mechanical damage.
- High voirage step-dawn transfomecs inc\u&ng the related switchgear shaN be instat\& in recesses
outside of the excavation lines.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technicdl Specifications
Chapter 06 Underground Excavation - 12 of 71
1.3.23 Communication
The Contractor shall provide and maintain the following minimum communication system throughout all
underground works. A robust two-way telephone system shall be installed between each working face, each
fire point. a continuously manned control point, and the Employer's and Contractor's Site Offices, the first
aid station, batching plants and other important facilities, as deemed necessary by the Contractor andlor
instructed by the Employer.
1.3.26 Access
Without prejudice to the liability of the Contractor under the Conditions of Contract and his responsibility
to adopt all expedience for ensuring the safety of his workmen and others, the Contractor shall in
connection with the provisions of safe access to the Works observe the following requirements:
Walkways shall be provided through all underground works providing a minimum clear space of 1800 mm
high and 750 mm wide with a walking surface of not less than 400 mm wide. The walking surface shall be
free from irregularities and sufficiently rough to provide an adequate fwthold. Water should not he allowed
to stand or accumulate at or above walkway level at any point. Any accidental spillage of spoil or other
material shall be removed immediately.
1.3.27 Drainage
All works required in connection with the dninage of water escapes and inrushes shall be carried out
according to the chapter "Dewatering" and after consultation with the Employer. Only skilled personnel
shall he employed for such work, particularly if shotcrete or a concrete lining is placed on the water escape
surface. The Contractor shall make all necessary arrangements to prevent the penetration of ground or
service water into the area of adjacent works. The Employer may only install construction drains subject to
approval.
The Contractor shall have available pumps, pipes, etc., in an adequate amount and capacity for dewatering
during construction.
Dewatering shall be continued until the respective works or sections of the works are temporarily accepted
by the Employer. The water has to be collected, channelled and piped out of the tunnel.
Water out of fissures or faults, running over the rock surface to be shotcreted, shall be collected jn
drainpipes and channel formed by rapid hardening mortar prior to shotcreting.
After placing of primary lining a systematic drainage along the tunnel shall be executed prior to placing of
stmctural concrete.
--.
If-..
unexpected severe influx of water is encountered from faults or fracture zones. it may be necessary to
'
-,...reduce the inflow of water by grouting.
.,:. 0 ..
,
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 13 of 71
Notwithstanding the Contractor's liability under the Conditions of Contract and the requirements and
recommendations of the local fire fighting authorities, the Contractor shall observe the following
requirements, where applicable:
- Fire fighting equipment shall be in compliance with internationally recognized standards.
- Vulnerable areas, such as material stores, shall be provided with individual fire points.
- An alarm procedure shall be developed for any type of emergency that they may be called upon to
tackle.
- Burning and welding underground shall be kept to a minimum and propane shall be used in
preference to acetylene. Gas cylinders shall not be stored below ground and shall be removed after
use. Sand buckets and extinguishers shall be immediately available when cut-welding is carried out.
- Storage of combustible materials below ground shall be kept to that required for immediate or
emergency use only. Waste shall be removed at the end of each shift.
- A Site fire squad shall be designated and trained to use apparatus, monitor its readiness, check and
report on unsafe practices.
- Access to the Site for emergency vehicles shall be maintained at all times.
1 3 3 0 Cave-ins
The Contractor shall, at all times, take the measures deemed necessary or ordered by the Employer to avoid
cave-ins in tunnels, caverns, shafts, etc.
In case a cave-in occurs or signs indicating the possibility of its occurrence are observed, the Contractor
shall take all necessary measures to avoid it and prevent accidents: he shall then immediately notify the
Employer. In such cases, the Contractor shall take all measures ordered by the Employer. He shall execute
such measures ordered by the Employer, and all works required to control the cave-in shall be the
Contractor's responsibility: the removal of cave-in materials, the necessary repairs and the accident that
may occur shall also be the Contractor's responsibility. The cost for such operation shall be included in the
Contract price.
! v u k m libm ? w r r i x , n 6 r y W c r z d u z r? >ihmlc?Munderpnlund
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 14 of 71
The Contractor shall be responsible for all cave-ins, erosion and over-excavation of tunnels in earth. He
shall take all necessary measures. at his cost, to control the excavation and make all the repairs ordered by
the Employer.
1.4.1 General
At the Employer's request, the Contractor shall at all times supply rock, soil, and water samples for testing
purposes. Any change in rock and soil conditions shall immediately be reported to the Employer. In the
event of large inflows of water, the quantity shall be determined at the Employer's request.
Additional anchor bearing tests may be required by the Employer.
.
,Twomethods
-
.- are to be applied, namely:
,
a
. Convergency measurements, where the distance between placed bolts in a profile section will be
measured severally by mechanical means.
,
-
.4 -.
...
I r#vhlw~rks\lul:.aO*c*Cd!n: : virlum >*rrl i - u . l u n
,*' , 6cq\addmndul no 2thap.r 06 un-mud niia~~i~r~:rr0
.---
. \ : c
I
. . -
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 16 of 71
- Roof settlements, where the movement of a bolt placed at the crown of the cross-section will be
measured by precision levelling.
Convergency measurements are generally taken in sections of 50 m distance along the tunnel alignment.
However, in areas where potential deformations are expected, the Employer may locally shorten the
distance.
Roof settlement measurements shall be taken at 25 m intervals between two and at regular convergency
measurement sections.
I CW:! I rCClldtllll%:
nridil~; : v,xlonc ::\pan iirrlwln 6r.9Wcndum n. lkhrplcr (6;ndcrgaidd
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underpound Excavation - 17 of 71
The Employer shall plot all measurements within 4 hours of the readings on agreed diagrams, which shall
be accessible at any time for consultation. The graphs shall show date, time of measurement, deformation
and distance from the excavation face.
If evaluations and plotted graphs show that the speed of deformations do not decrease within specified
periods. additional strengthening of the support shall be proposed by the Contractor or directed and
approved by the Employer. Monitoring shall continue in an agreed pattern until deformations tend to zero.
"C" Line
Payline for excavatim
P. ,/'
Construction Tolerance
Shotcrete Thickness - Defonatlon Tolerance , INCLUDED
as per Support Class drawings i IN UNIT
' PRICE OF
Unavoidable Overbreak
as per Support Class drawings i EXCAVATlON
"B" Line
..
.'u C
.o ...
* - -
131
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specificationr
Chapter 06 Underground Excavation - 20 of 71
-
Dagachnu HPP Section 6 - Employer's Requiremen- 6.2 Technical Specifications
Chapter 06 Underground Excavation - 21 of 71
However, such prices shall not include the installation of all support elements, which shall be paid for as
indicated in the respective Clause.
1.6.5 Transport
"Extra over" for transport will not be paid. The unit prices in the Bill of Quantities shall cover all transport
to final positions, stockpile areas or waste deposits.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 22 of71
2 SHOTCRETE
2.1 General
2.1.2 Definition
Shotcrete is an intimate mixture of Portland cement, aggregates, water and additives, if applicable, shot into
place by means of compressed air through a spray nozzle. If shotcrete is properly proportioned, mixed,
placed and cured, it forms a very hard, high-strength concrete. Rebound is defined as the constituents of
shotcrete that rebound from the surface during the application of shotcrete.
During hot weather periods the water content of the aggregates for the dry process shall be kept above 4 %.
in order to avoid cement loss at the rotor of the shotcrete machine.
2.2.3 Cement
Cement shall be Portland cement of approved type. Its material uniformity shall be guaranteed.
Where chemically aggressive ground water occurs, a special type of cement, probably with an admixture of
additives shall be used.
Compatibility of the binder with the intended additive and the percentages of the same to be added shall be
tested by the Contractor prior to use.
2.2.4 Aggregates
Aggregates for shotcreting shall be uniformly graded. Dense, hard particles are required to avoid crumbling
and the forming of fine powder by the grains when passing through the nozzle.
The grain form shall be compact, i.e. it may differ only slightly from a spherical or cubic shape.
Unless otherwise approved by the Employer, the percentages of fine and coarse aggregate shall conform to
the grading, measured by weight, shown in Figure 2.2.4.
0.075 0.15 0.30 0.M) 1.18 2.36 4.75 9.50 12.5019.0
OPENINGS lmml
T o prevent dust formation as much as possible during spraying, the rock flour proportion (0.1 mm) in the
crushed aggregate shall be kept small.
Mortar made with finer sand will have a higher water requirement and correspondingly increased drying
shrinkage. If a sand is deficient in fines, the addition of diatomaceous earth (not more than 3% of the
cement. by weight) will improve the plasticity of the mix and decrease the amount of rebound. The inherent
moisture in the ready mix aggregates shall not exceed 3%.
The maximum aggregate size fractions of the ready mix shall depend on the shotcrete thickness and he
determined by suitability tests.
The water content of aggregate at the time of incorporating into the mix shall be less than approximately
five percent (5%) by weight.
Both the purity and the uniformity of the fractions to the appropriate standards shall be guaranteed
continuously.
The aggregates shall be stored in adequate quantities and in an appropriate manner so that purity and
:l~rlx?s6eqWdndum
no ZkIEhap11106gni~-enl~nderravaibnrcrO1&,ex S p 4 X
Dagachhu HPP -
Section 6 Employer's Requirements 6.2 Technical Specificarions
Chapter 06 Underground Excavation - 26 of 71
2.2.5 Additives
Only accelerating agents free from chloride shall be used. They shall not promote steel corrosion or
adversely affect the strength development and hardening pattern of the concrete. The Contractor shall be
fully responsible for the suitability of the additive. He shall protect himself through manufacturer's
guarantees.
The quantity used shall he kept to the absolute necessary minimum. The machine shall feed the additive
directly and in the exact proportion by weight. Before work is commenced, proof shall be furnished as to
how the additive influences the strength development up to the point where the final strength is reached.
2.2.6 Water
The water used in shotcrete shall be fresh, clean and free from injurious amounts of sewage, oil, acid.
alkali, salts, and organic or other undesirable matter.
2.2.7 Plant
The method of application shall be a fully developed from both material and technical point of view.
satisfying all requirements for.the particular job and employing only modem equipment approved by the
Employer.
Suitable standby equipment and a sufficient stock of spare parts shall be kept ready for use.
Standard Mixer: The rotating mixing equipment shall be capable of thoroughly dry-mixing sand and
cement within the time available to uniformly and continuously supply the mixed material to the gun.
2.3 Execution of W o r k
If, in the opinion of the Employer, operation of shotcreting equipment becomes unsatisfactory, the
Contractor shall make all necessary repairs or replacement of the equipment. The Employer may direct that
shotcreting ceases until the Employer's instructions are complied with, and the Contractor shall have no
grounds for claims on this account.
In all areas where excavation is proceeding, the Contractor shall ensure that sufficient equipment is
available to apply shotcrete at any face, as specified herein.
2.3.4 Mixing
Thorough mixing of the aggregates, cement additives and water shall be ensured for all shotmete.
The optimum mix contains a little less water than what will cause sloughing, and just enough cement for
the desired waterlcement ratio.
The waterlcement ratio of the fresh shotcrete in place shall be in general between 0.35 and 0.50.
The non-lift mixing process shall take at least two (2) minutes and the composition of the ready mix shall
constantly remain unchanged until it is applied.
During handling, the mixed concrete shall be protected from dripping water.
The use of ready mix from transit-mixing plants is allowed for subordinate structural parts only and is
subject to explicit approval by the Employer.
The Contractor shall develop operating procedures and operations to the satisfaction of the Employer to
give:
- Minimum rebound
No inclusion of rebound in the finished shotcrete
As smooth a finished surface as possible
- No hollow areas in the shotcrete
- A minimum of shrinkage cracks, and
- Good adherence of the shotcrete to rock or other surface
The flow of the material at the nozzle shall be continuous and uniform and the rate of application over any
given area shall be uniform. Slugs, sand spots, wet areas or other defects shall be cut out and corrected as
specified herein.
When shotcreting is to he performed near existing structures, the Contractor shall ensure that no damage
results to the structure and shall protect the surfaces of structures before shotcreting.
2.3.8 Rebound
Rebound shall be kept to a minimum, continuously watched, and at the request of the Employer its kind
and quantity ascertained. It shall he entirely removed and under no circumstances may it be sprayed over or
even used again as spray material.
23.13 Curing
During a period depending on local conditions and to be agreed upon with the Employer, the freshly placed
shotcrete shall be protected against sunshine, cold, rain, running water, chemical attack, and vibrations until
it hardens, and it shall be kept moist for at least seven (7) days. Timing of the shotcreting operation shall be
such that the air temperature after shotcreting shall be above freezing point for at least seven (7) days. If
shotcreting is carried out under adverse weather conditions or low temperatures, a protection of placed
shotcrete shall be provided.
In case of open-air shotcreting, the surface shall be protected from the direct rays of the sun for the first
three (3) days unless it is to be flooded as in canals. Where membrane curing is used and rebound has not
been removed, an excessive amount of sealing compound is needed for effective sealing of the rough.
porous surface. The costs of this additional amount of sealing shall be borne by the Contractor.
2.4.1 -
Compatibility Test Laboratory Tests
The compatibility of accelerating admixtures and cement shall be tested in the laboratory in order to
establish setting times and whether the addition of the accelerator leads to an excessive reduction in the
long terms compressive strength of the mix.
The setting times shall be determined by using the Vicat apparatus. Different percentages of accelerating
admixtures with a waterlcement ratio of 0.35 are subject to setting tests.
The preparation of samples and testing procedures shall be as follows:
(a) Water temperature 20 +/-I degrees Celsius, cement 'and accelerator at room temperature.
(h) Prepare a mix of cement and the relevant percentage of accelerator with a total weight of 140
grams.
In the case of liquid accelerator a mix of water and accelerator shall be prepared with a total weight of 49
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 30 of 71
(a) Fill dry mix (cement + dry accelerator or cement only) in a cylinder of 50 mm diameter mounted
on a glasslplexiglass plate, height approx. 100 mm. The cylinder must have a coupling at a height
of 40 mm.
(b) Fill 49 grams of water (or water + liquid accelerator) into a rubber bulb
(c) Combine water and dry mix quickly (start timing!) and mix very quickly by machine. Mixing
shall be finished 10 seconds after the addition of water.
(dl Quickly press the mortar into the lower part and remove the upper part of the cylinder and flatten
the surface.
(e) Quickly adjust the Vicat needle to the surface of the mortar and release it. Determine the depth of
penetration.
(0 The initial setting time is specified. when the needle stops 3 to 5 mm above the glass/plexiglass
plate.
(g) Final setting time is specified, when the depth of penetration is not more than 1 mm.
Requirements for setting of the samples in the laboratory are:
Time of initial setting: 75 sec
Time of final setting: 150 sec.
Meeting these requirements with a dosage of accelerating admixture of less than 4.5 % of the cement by
weight will provide pmof that the type of accelerator is compatible with the cement used for setting speed.
To determine the sensitivity of the cement, to each type of accelerator the laboratory tests shall be made
with various doses of accelerator between 2 % and 7 % of the cement by weight. The percentages obtained
by the compatibility tests shall not be directly transferred to shotcrete application.
In addition to the setting tests using the Vicat-Needle apparatus, the reduction of the final strength of the
concrete specimen due to the use of accelerating admixtures shall be tested. The decrease of the
compressive strength at 28 days of a test specimen made with accelerating admixtures shall not exceed 40
% compared with test specimens consisting of plain mix only. The tests for the strength decrease can be
omitted if extensive field-test for determination of the strength development and final strength are carried
out for the different types and dosages of accelerating admixtures adopted, see Sub-clause 2.4.2. following.
2.4.2 -
Suitability Tests Field Trials
Field trials shall be carried out to determine setting and strength development and establish the suitable
range of accelerator dosage of shotcrete applied in the field.
For each type of accelerating admixture found suitable by preceding laboratory tests. a trial mix shall be
sprayed into test panels (3 Nos. 500 x 500 x 200 mm per trial mix), cured under site conditions and shall be
subjected to tests. As described hereunder, at least three different dosages of each type of accelerating
admixture shall be tested. The range of accelerator dosage rates shall vary between 2 % and 7 % of the
cement in weight.
The ambient temperature for the test shall be in accordance with the actual conditions in the tunnel.
One panel shall be subjected to penetration tests using a Proctor Penetrometer. Soil-test Model CN-419,
with a penetration plunger of 9 mm in diameter. The penetration resistance measured gives an indication of
the setting and early strength development of shotcrete.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 31 of 71
The minimum penetration resistance required is specified as follows (time elapsed after spraying):
after 2 minutes: minimum 260 N
after 5 minutes: minimum 380 N
after I0 minutes: minimum 450 N
The strength development up to 1.2 N/mm2 can be determined by the Penetrometer using a plunger of
3 mm diameter, depth of penetration shall be approximately 15 mm. The penemtion resistance can be
converted to compressive strength. col~espondingto a specimen with a length to diameter ratio of 1:1, by
the following formula:
U = (Pr - 30)1550 (N/mm2)
Pr = penetration resistance in N
These strength results shall be treated as approximate values and shall mainly be used for comparison of
mixes.
The development of the compressive strength shall be tested by the crushing of cylindrical shotcrete
specimens at the age of 1.7 and 28 days. The specimens shall be prepared by means of core drilling from
the test panels, which shall be cured under similar condition to those in the tunnel and shall have a diameter
of 100 mm and be cut to a height of 100 mm. For the I-day test the cores shall be drilled not before
20 hours after spraying, the other cores shall be drilled approximately 48 hours after spraying. A minimum
distance of 100 mm shall be kept from the edges of the test panel.
Five cores shall be tested at each shotcrete age specified. The average value of the five test results shall
comply with the strength requirements specified.
2.6.1 Shotcreting
The shotcreted surface to be paid for shall be the area in square meters of the several thicknesses within the
paylines shown on the drawings or directed by the Employer. No additional payment will be made in cases
where the shotcrete average thickness is found to be greater than specified.
No payment will be made for shotcrete or the materials constituent thereof, which are lost due to improper
working methods, or rejected on account of improper mixing, or lost by leakage due to the failure of the
Contractor to caulk surface leaks, or for placing shotcrete outside the concrete payline as a result of careless
excavation, or excavation intentionally performed by the Contractor to facilitate his operations.
4
2.6.2 Shotcrete measured by volume
For shotcrete volume that will be measured and paid for at unit price per cubic meter, no payment will be
made for shotcrete material outside of the paylines shown on the drawings or directed by the Employer. No
rebound will be paid for.
. ,
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 34 of 71
3 REINFORCING STEEL
3.1 General
Welded wire fabrics (wire mesh) are the standard reinforcement for shotcrete linings. serve as
reinforcement, facilitate the application of shotcrete and improve the post-failure behaviour of shotcrete.
Small wire diameters of the wire mesh enable the installation of wire mesh in correspondence with the
excavation contours.
Reinforcing steel bars, for tunnel support purposes are required as an additional reinforcement in heavily
stressed areas, such as portal areas, junctions of tunnels and cross passages depending on the local ground
conditions.
Roof ties are support elements consisting of 2 longitudinal rebars connected by welded loops. Roof ties are
elements, which combine the carrying capacity of two or more rock bolts.
3.2.2 Re-Bars
Reinforcing steel bars shall comply with Chapter 07 of the Technical Specifications.
- All work and material for the firm fixing of wire mesh along the rock contours or previously applied
shotcrete layer
- Care and disposal of waste materials.
- All tests and samples for quality control and preliminary tests.
- All auxiliary works necessary to complete the work.
- Drilling and maintaining of drain holes.
- All equipment and labour.
4 STEELRIBS
4.1 General
This section applies to the supply and installation of the steel ribs required and used as one element to the
support in underground excavations. They shall be effective as protection and primary support immediately
after excavation and shall subsequently act as reinforcement and load distributing members for the
shotcrete lining.
The steel ribs shall be manufactured to meet the geometrical requirements for the excavation geometries for
each of the rock class including the relevant tolerances as specified.
4.2.2 Materials
Hot rolled profiles (H and TH-profiles) shall consist of structural steel with minimum yield strength of
240 N/mm2 and shall comply with the internationally acknowledged standard selected by the Contractor.
Lattice girders shall be manufactured of cormgated reinforcing bars in compliance with Chapter 07 of this
specification.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 38 of 71
4.3 Execution of W o r k
4.3.1.1 Geometry
Deviations of the assembled rib from the designed geometry shall not exceed +I- 50 mm.
Any larger deviations shall he considered in the overall construction tolerances for tunnel drivage.
4.3.1.3 Welding
The manual metal-arc welding process shall be employed. The manufacturer shall be responsible for
ensuring that the capacity of the welding plant and ancillary equipment is adequate for the welding
procedure to be used and for maintaining all welding plant and ancillary equipment in good working order.
Covered electrodes complying with German Standard DIN 1913 shall be used. Electrodes shall be selected
with regard to the particular application (welding position, joint design). Electrodes shall be stored in their
original containers in a dry, preferably heated place adequately protected from the effects of the weather
and in accordance with the manufacturer's specification.
Surfaces to be welded shall be dry. Fusion faces and the surrounding surfaces shall be free from heavy
scale, moisture oil, paint or any other substance which might affect the quality of the weld. Slag shall be
removed from each run of weld metal before a further run is superimposed. The most favourahle welding
position for each case shall be chosen.
For the cutting of the steel profiles the manual flame cutting process may be employed. Also sawing is
permitted.
Further preparation of joint and fusion faces shall be done by grinding.
Parts to be welded shall be assembled such that the joints are easily accessible and visible to the operator.
Slag shall be removed from all welds in order to allow visual inspection
A suitably trained supervisor who shall have particular production experience shall supervise welding
operations. The welding supervision is responsible for the following duties listed hereunder:
(a) Employment of the welders or skilled operators and supervision of their work.
(b) Selection, use and storage of suitable welding filler metals and auxiliary materials.
(c) Selection and use of satisfactory welding apparatus. welding plant and welding fixtures,
(d) Visual and dimensional checking of the weld seams as described under 12.
Welders shall pass the acceptance test as described under 10.
Prior to commencement of each welding connection type three nos of joints shall he manufactured by each
welder under conditions of the regular manufacturing process for inspection. The Employer shall inspect
these joints.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 39 of 71
4.3.2 Installation
Steel ribs shall be erected to the lines and levels as indicated on the drawings. The exact excavation levels
will however be determined by the Contractor to match best his equipment and construction method.
Hardwood foot blocks and wedges shall be used to bring the steel ribs to the required line and level. Tie
bars shall be provided to connect the rib to the adjacent steel rib and fix it securely in place.
Tie bars shall be made of steel rods of 16 mm diameter, bent and connected to the rib.
Steel ribs shall be embedded in shotcrete in order to get contact between rock and steel rib by solid
shotcrete packing.
The steel ribs shall be erected perpendicular to the tunnel axis.
The joints of the ribs shall be such that the slructural capacity of the cross-section is maintained
In h e case of TH-profiles, the trough shall be oriented towards the tunnel in order to enable full
embedment and therefore load transfer and to avoid cavities behind the steel profile.
4.4.1 General
The Contractor shall furnish certified copies of reports to the Employer of all tests and inspections required
to show compliance with the applicable standards and assembly instructions.
4.5 Auxiliary W o r k
All auxiliary works listed to be included in the unit rates of the BoQ items for underground excavation
shall also be applicable for the steel rib installation works. Further to the above the following works and
operations shall also be considered as auxiliary works included in the BoQ items:
- Provisions of equipment for erection of steel ribs.
- All testing of materials.
5 FOREPOLING
5.1 General
Tunnelling in loose ground material is only possible due to the dome-like, three-dimensional load transfer
in longitudinal tunnel direction across the temporarily unsupported tunnel arch. In order to reduce or avoid
an overstressing of the arch and face, loose ground has to be reinforced by suppon ahead of the face. These
support measures ahead of the face protect or prevent ground deformation. An excavation according to the
theoretical profile induces shorter span and hence the displacements in the tunnel and on the surface are
reduced to a minimum. The installation of advance support depends to a high extent on the quality of
workmanship.
Forepoling is an auxiliary support element required as safety precaution and overhead protection for the
application in the actual working area of the tunnel excavation works. Forepoling shall be applied in rock
and soil conditions, which tend to produce overbreak. collapses or material inflows immediately following
excavation. Forepoling may be applied locally or systematically, as the circumstances require.
5.2.1 General
Steel pipes with an inner diameter of 30 to 35 mm shall be used unless otherwise specified.
Wall thickness of steel pipes shall not be less than 3 mm unless otherwise specified.
The length of the steel pipes shall be at least 1.50 m longer than the instructed length of round (as given by
the relevant suppon class).
Grout mortar shall comply with the properties given in Clause 7 of this Chapter of the Technical
Specifications.
5.2.2.1 Spiles
Spiles are cormgated reinforcement bars with a diameter of 26 mm and a length of 3 to 4 m. They can be
driven into fine to medium coarse, loose to medium dense layered grounds by a special adapter on a boom
at 20 to 30 cm distances. The ground in the vicinity of the spiles will be compacted and receives a type of
"prestressing", hence spiles achieve good profile shapes.
53 Execution of Work
The aim of any advance support is to install the suppon elements into the ground ahead of the face in the
shape of the excavation profile, so that the excavation profile can be achieved without major overbreak.
Due to the installation of advance suppon the ground experiences a certain disturbance which is to he
compensated with appropriate grouting measures.
The use of steel ribs is a precondition for the installation of the advance support. The combination of steel
ribs with shotcrete forms the support of the advance-support at the place of the nearest rib to the face. The
effectiveness of the advance support also depends on the length of round. Advance support with forepoling
bars or spiles is only effective with lengths of rounds of less than 1.2 meters in loose ground.
I
When installing advance-support, the shotcrete lining above the steel rib shall be kept open for installation
of forepoling. Only once the advance support has been placed, shall the shotcrete be applied at these
locations, in order to achieve an appropriate support and embedment for forepoling at the steel rib next to
the face. Attention shall be taken so that forepoling is also embedded in shotcrete between the steel rib next
to the face and the tunnel face, which will result in a minimum overbreak during the excavation of the next
round.
As the grout mortar shall have sufficient strength before opening the next excavation step, the use of
accelerated cement is favourable. The use of accelerated cement increases time available for cleaning and
wear. In certain cycles normal cement can be used if the working cycle can be planned in such a way that
the time between grouting and the opening of the face can be used for activities such as the installation of
rock bolts or the invert arch.
The selection of the length of advance-support shall consider that the steel rods or pipes must have
sufficient support lengths in the ground and on the steel ribs.
Forepoling pipes shall not have grout holes for approximately 1 m at its ends so that the issue of the grout
at the tunnel face is avoided. Prior to grouting. the mouth of the boreholes shall be sufficiently sealed in
order to achieve sufficient grouting embedment of the pipes. In order to enable a certain build up grouting
pressure, a reusable mechanical packer including a tap shall be attached at every end of the pipes.
In loose ground, the flushing of self-drilling rods shall be carried out by means of cement grout, as this
method warrants best results without any loosening effects.
Longer advance-support with self-drilling bolts of 6 m length, which may only be installed every second
round have turned out to be not ideal, as the material tends to overbreak at least as far as to the installed
rods. This "saw-tooth" profile therefore requires an uneconomical excess of shotcrete.
6.1 General
Steel Lagging (sheet piles) shall be employed mainly in weak ground with low cohesion with the purpose
of preventing the collapse of material during and immediately after excavation.
7 ROCKBOLTS
7.1 General
The provisions contained hereunder apply to all rock bolts installed either locally or in a systematic pattern
in the roof, sidewalls, and invert of the tunnels. Rock bolts are part of the primary support, with the purpose
of activating the composite action between the surrounding rock and the shotcrete, contributing to the load
bearing capacity of the primary tunnel lining. Rock bolts occasionally required for the support of the tunnel
face during the advance are covered likewise under these provisions.
Rock bolts shall be used as the conditions may require and shall be installed according to the lengths and
rock bolt patterns shown on the drawings for each relevant standard support system.
Under this clause, the Contractor shall furnish and install support bolts and anchors complete with all
required accessories including but not limited to bearing plates, wedges, expansion anchors, nuts and
washers, etc., and shall drill holes for and install rock bolts and anchors, chain link fabrics or special types
of anchors complete with all required accessories as outlined hereafter or as directed by the Employer.
Rock bolts or anchors shall be used in the zones indicated on the drawings. or in those places where the
Employer orders it according to the rock conditions.
7.1.2 Definitions
SN-Bolts are made of deformed steel bars and fully bonded with the surrounding rock by cement mortar.
The hole is filled with grout before insertion of the bolt. The abbreviation SN descends from the pit "Store
Norfors" in Norway where applied first.
PG-Bolts (post-grouted or injection bolts) are made of deformed steel b a n with a hose attached. Grouting is
done after installation of the bolt through the hose.
Self-Drilling Rock-Bolts are a combined system of rock bolt and drill rod. During drilling, the bolt is used
as the drill rod fixed with a drill bit. Rod and bit remain in the hole as a rock bolt. which is grouted through
the flushing hole. In case of collapsing boreholes, this system still enables the installation of rock bolts.
Swellex Rock Bolts (friction anchored rock bolls) are mechanically folded steel tubes. High water pressure
inflates the tube and adapts its shape to the irregularities of the borehole.
So-and anchors are made of steel cables and fully bonded with the surrounded rock by cement mortar.
Grouting is carried out after installation of the anchor using a hose and packer. The anchors are pre-stressed
and relaxation is possible.
Permanent bar anchors are pre-stressed anchors of high load-bearing capacity (higher than 350 kN) and
relaxation is possible. Grouting is carried out after installation of the anchor using a hose and packer.
- -.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 45 of 71
Anchor plates with a size of 200 x 200 and a thickness of 5 mm shall be used unless instructed otherwise by
the Employer based on support necessities. The shape shall allow a uniform seat, even if the bolt is not
installed exactly perpendicular to the surface below.
Washers and nuts shall allow the secure transfer of the anchor force to the anchor plate.
7.2.6 -
Cement Mortar Grout
The cement mortar grout shall consist of sand, cement and water or neat cement and water.
Only Portland cement shall be used.
Sand for grouting purpose shall be clean, mineral sand. uniform in quality and from an approved source.
Water shall be clean, free from oil, acid, alkaline. organic and other deleterious substances.
Additives for the improvement of workability may be used.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 TechnicalSpecificat~onr
Chapter 06 Underground Excavation - 47 of 71
Boreholes for all rock bolts shall he drilled to !he depths as required by the lengths of rock bolts specified
for the respective rock class and at diameters, which ensure best workability for grouting. coupling and
installation. The minimum diameter of the boreholes shall be 10 mm larger than the diameter of the rock
bolts/couplings installed.
The boreholes shall be cleaned of all drill cuttings, sludge and debris. The installation of rock holts shall
follow the drilling and preparation of the borehole within 3 hours.
Prior to the installation of the rock bolt, the entire borehole shall be filled with cement mortar by inserting
the grout hose to the full depth of the hole and withdrawing as the grout is pumped in. The nozzle shall be
kept buried in the grout as the pipe is withdrawn so that air is displaced as the hole is filled. The bolt is then
pushed into the hole.
The nut of the grouted rock bolts shall be tightened not later than 2 rounds behind the face or 24 hours after
installation to achieve a force at the anchor plate of approx. 20 m.
The required torque to achieve this
force shall be calibrated by suitable means (pressure cell, torque wrench).
In case of confined working space andlor great length of rock bolts, coupling shall he permitted. The
number of coupled parts shall be kept on a minimum. However, the load capacity of such coupled rock
bolts shall not be less than that of a standard integral rock bolt. Special attention shall he paid to the
grouting procedure in order to ensure full embedment of the bolt by grout.
In case of boreholes tending to collapse. grouting may be done after installation of the bolt. The hole is then
grouted by a special attachment, which allows the mouth of the borehole to be sealed whilst the grout is
pumped in. Air is displaced from the hole via a tube, which is attached to the full length of the rock bolt as
it is installed. Grout is then pumped in and the hole can be seen to be full, when grout escapes from the end
of the tube.
The boreholes shall be cleaned of all drill cuttings, sludge and debris. The installation of rock holts shall
follow the drilling and preparation of the borehole within 3 hours.
The nut of the grouted rock bolts shall be tightened not later than 3 rounds behind the face or 24 hours after
grouting to achieve a force at the anchor plate of approx. 20 kN. The required torque to achieve this force
shall be calibrated by suitable means (pressure cell. torque wrench).
used to improve workability. The influence of the additive to the strength development
tests as described under this Sub-clause.
be tested on cubes 5 x 5 x 5 cm. The cubes shall he cured in water.
The grout shall have a minimum compressive strength of 8 NlmmZ after 24 hours and 20 Nlmmz after 28
days.
Five numbers of cubes shall be prepared for each compressive strength test. The resultant strength is the
average evaluated from the three remaining values after elimination of the highest and the lowest.
During construction, ten cube samples shall be taken weekly at each drivage from the grouting hose at the
nozzle. Preparation and evaluation shall follow the procedure as described above.
8.1 General
The excavation and support classes described in the following Clause detail excavation techniques and the
associated appropriate supporting measures required for the construction of the listed underground works.
All items mentioned in the support descriptions have been described in Clauses 2 - 7 of this Chapter
(Underground Excavations) of the Technical Specifications. Support classes. sequences, expected
unavoidable overbreak and defomation tolerances are shown in the Tender Drawings.
Descriptions of the rock expected to be encountered are given in Sub-clause 1.4.4. The cross reference to
the support classes is purely descriptive and shall not govern the determination of support classes.
The determination of the support classes shall be governed by the following cost-influencing factors:
the length of round with which the excavation can be done in a save manner and at an acceptable
accuracy of profile shape
the quantity of tunnel support required for reaching a new state of equilibrium, derived from the
cease of deformations within a defined period of time
the excavation- and support sequence
Determination of support class shall be done by the Contractor and acknowledged by the Employer.
Unacknowledged determination of support classes shall not be accepted for payment. Upon diverging
viewpoints all efforts shall be undertaken to reach consensus. The Contractor shall undertake all necessary
action for improving workmanship if so required by the Employer, as described in Sub-clause 1.3 of this
chapter in order to keep the rock mass intact to the best possible extent and hence minimize tunnel support.
The interpretation of the geotechnical monitoring programme results shall play a decisive role in finding
consensus. The lack of consensus does not entitle the Contractor to stop works and apply for time
extension.
Determination of support classes shall be recorded and kept on site and shall be accessible to both Parties at
any one time. The delermination shall be valid until the Contractor or the Employer requests a modification
of the same at any one time. The request of examining the valid determination of support classes shall not
be denied by the other Party.
sd drnmnvdiul i cirll w c ~ i k l i l ~ ~l
:-ddudndr\lot i whim ci-n
.: 6 rmMdmdum nu 2khap.r ul vndr~mvndn n r a i x ~ n . a r O ! dlci L
,i* Dagachhu HPP Sectlon 6 - Employer's Requirementq 6.2 Technical Specificatrons
Chapter 06 Underground Excavation - 52 of 71
15 cm of shotcrete lining;
I layer of wire mesh (100 x 100 mm. 4 kglm2), absence of steel rib for fixing of the wire mesh
every second round to be considered;
Lattice girder steel ribs (70120130) every second round for profile control;
A systematic SN rock bolt pattern with 3 m lengths, 7 no. per round, with orientations required by
the discontinuity pattern.
adlien*i~iil I va)um iiipan :l-rc:n~n6 c:q(uidni'ic 2,s crrantx;n rev oi dnrr SWIX
ah.+~:c:Otl undrr~n~snd
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
..
Chapter 06 Undergmund Excavat~on- 53 of 71
- Either 45 driven forepoling bars of 3m length (for the next round). 45 forepoling pipes without .
mortar of 3m length or 45 forepoling bars without mortar of 4m length;
- A rock bolt pattern of self drilling bolts with 4 m lengths, 6 no. per round in the sidewalls;
- An invert arch supported with 20 cm of shotcrete and 1 layer of wire mesh (100 x 100 mm. 4
kgIm2) with steel rib for fixing of the wire mesh, installed at distances not exceeding 6m from the
tunnel face.
The sensitivity of the ground to water requires particular care.
nrnrrUnl I clvll vorkr\lor I ~ddmdaib:: r u h m ii%nu;3;-rcmn 6eqWdmmii;n n r 2bhnprr:m undewmund ndxndndndndndnd.ndvnI d a x %ep Oli
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 56 of 71
- I layer of wire mesh (100 x 100 mm. 4 kg/m2), absence of steel rib for fixing of the wire mesh
every second round to be considered:
- Lattice girder steel ribs (70/20/30) every second round for profile control;
- A systematic SN rock bolt pattern with 3 m lengths, 8 no. every round with orientations required
by the discontinuity pattern.
8.2.10.1 - -
Powerhouse Cavern Top Heading Excavation Class A (PHC TH ECA)
Excavation of top heading in the powerhouse cavern in competent orjointed rock mass by drill and blast by
means of smooth blasting technique. with lengths of rounds between 2.0 and 3.0 metres and subsequent
installation of tunnel support before the excavation of the next round. Support elements will be paid
separately.
1 c~vilwork.\lut ~ ~ r m ~ ~ c: ev,b:;-c
z ~ ~ ::\xn
> : ,:~=?w>n 6 c ~ w ~ m d unom 2kbprcrrx undergn,und C . C ~ W : H , ~ . , ~ $,,c,
~ ~ ~
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 5R of 71
i r:r::r~:;Lsli~~; i;~ddridl>ii>c
I m l v n c liban il-nrun6enjkddmdumm 2 i h . # p 8 ~ r i l b ; ~ ~ ~ ~ ? ~ : r r t i ~ r a r l ~ l r ~ r . v I I I
Dagachhu HPP Seclion 6 - Employer's Requirements 6.2 Technical Specificarians
Chapter 06 Underground Excavation - 59 of 71
- Swellex (or similar) or SN bolting with 3 m lengths, 3 no. every first round with 4 no. in every
second round, at locations required by the discontinuity pattern.
82.14 Excavation and support of the Access Tunnel to the Powerhouse Cavern (ACT)
- 15 cm of shotcrete lining;
- 1 layer of wire mesh (100 x 100 mm. 4 kglmz), absence of steel rib for fixing of the wire mesh
every second round to be considered;
- Lattice girder steel ribs (70120130) every second round for profile control;
- A systematic SN rock bolt pattern with 3 m lengths, 9 no. every round with orientations required
by the discontinuity pattern.
An invert arch supported with 20 cm of shotcrete and 1 layer of wire mesh (100 x I00 mm, 4
kglm') with steel rib for fixing of the wire mesh, installed at distances not exceeding 6m from the
tunnel face.
The sensitivity of the ground to water requires particular care.
: ~ : ~ : u ~ ; : W lLrdiircdaili~i
i,r I vulvrne (man it.anir6r-q\lddcndum ns 2irh~prrr06un8%e:ymundcxcarr1bn=rO! d i ~ ~ r S e ~ . O X
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter Oh Underground Excavation - 63 of 71
t
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Spsificationc
Chapter 06 Underground Excavation - 65 of 71
An invert arch supported with 20 cm of shotcrete and 1 layer of wire mesh (100 x 100 mm. 4
kglm2) with steel rib for fixing of the wire mesh.
The sensitivity of the rock mass to water requires particular care: Water shall be kept away from exposed
rock surfaces by suitable means approved by the Employer. Ponding water shall not be allowed.
- 20 cm of shotcrete lining;
- I layer of wire mesh (I00 x 100 mm. 4 kglm2) with steel rib for fixing of the wire mesh;
Lattice girder steel ribs (70120130) every round;
- 20 no. in every first round and 21 no. in every second round forepoling bars, 4rn length;
- A shotcrete sealing of the tunnel face with 3 cm of shotcrete;
- A systematic SN rock bolt pattern with 3 m lengths. 7 no. per round, with orientations required by
the discontinuity pattern.
1 .
' ..'
, b 1.11356Marwh ~ d / 3 ~ ! c u n ; n r s ~ n: Ci X ~wo:k\>lu:
: ~ i.ddcnd,Al,.! I ui)hmc clb7rn s u r : l < > - 6 c y W d c - d u m n a
%
> g>
\, ;'._:. I
i U' ., .
.. .~;
'..,,<'?,., ,
.
:
' ,.,.:-
Dagachhu HPP Section 6 -Employers Requirements 6.2 Technical Specifications
Chapter N Underground Excavation - 67 of 71
- 1 layer of wire mesh (100 x 100 mm, 4 kglmz) to be fixed to the rock surface;
- Swellex (or similar) or SN bolting with 3 m lengths, 4 no. every round at locations required by the
discontinuity pattern.
.: Phpmeit,shi! also include the deposition of material resulting from the excavation, including its loading
, '.i
,
- onto tran8pbtt;vansportation and appropriate deposition and landscaping of the
,.. .
~.
Additional "Downtime Days" shall be granted per 100 lin. m of tunnel as long as the specified support and
sequences are adhered to.
Dagachhu HPP Section 6 E m p l o y e r ' s Requirements 6.2 Technical Specifications
Chapter 06 Underground Excavation - 71 of 71
9 DOWNTIMES
9.1 General
Downtimes shall be considered for underground excavations in the case of geological or hydro-geological
conditions impeding regular work cycles.
6.2 T E C H N I C A L S P E C I F I C A T I O N S
Chapter 07
CONCRETE
&
REINFORCED CONCRETE
Dagachhu HPP Seclion 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete . ii
TABLE OF CONTENTS
Chapter 07
CONCRETE &
REINFORCED CONCRETE
PAGE
1 CONCRETE ..................................................................................................................1
1.1 General .................................................. I
1.1.1 Scope of work ......................................................................................................... 1
1.2 Materials and Equipment ........................................................................................................ 5
1.2.1 Binders ...................................................................................................................... 5
1.2.2 Aggregates .................................................................................................................6
1.2.3 Admixtures ................................................................................................................ 9
1.2.4 Mixing water ............................................................................................................ 9
1.2.5 Steel ........................................................................................................................... 9
1.2.6 Concrete .................................................................................................................. 11
1.2.7 Concrete formwork .................................................................................................. 18
1.2.8 Joint materials .......................................................................................................... 19
1.2.9 Delivery, storage, handling ........................ . . . ................................................... 20
1.3 Execution of Work .............................................................................................................. 21
1.3.1 General concreting .................................................................................................. 21
1.3.2 Transporting concrete to the Site..................... . . ................................................... 22
1.3.3 Handling, placing and curing the concrete
1.3.4 Hot and cold weather precautions .............
1.3.5 Formwork, false work, stripping, propping ............................................................. 25
2 STEEL REINFORCEMENT ....................................................................................................... 28
2.1 General ................................................................................................................................. 28
2.2 Fixing of Reinforcement ....................................................................................................... 29
2.3 Concrete Cover to Reinforcement ........................................................................................ 29
2.4 Bar Spacing........................................................................................................................... 30
2.5 Permissible Curvature for Reinforcement ............................................................................ 30
2.6 Anchorage of Reinforcing Bars and Fabrics ......................................................................... 30
. .
2.7 Tensile Spl~ces~nReinforcement ........................................................................................ I
2.7.1 General ........................................... 31
......................................... 31
2.8 Compressive Splices in Reinforcement ............................ . . . ............................................. 32
2.8.1 Lap splices ........................................ 2
23.2 Welded connections ................................................................................................ 33
2.8.3 Contact splices........................................................................................................ 33
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - iii
2.9 Connections 3
2.9.1 Screwed connections ...............................................................................................
33
3 JOINTS ..........................................................................................................................................34
3.1 Construction Joints ............................................................................................................... 34
3.1 .I General applicatio
3.1.2 Design joints ........ ........ . ..
4 CURING, FINISHING, REPAIR, PROTECTION ...................................................................37
4.1 Preparation of Surfaces to Receive Concrete 7
4.2 CuringMoist Curin 7
4.2.1 Genera 7
4.2.2 Moist c 8
. .
4.3 Fin~shlng . . ............................................................................................
39
4.3.1 Sprinkling with cemen 39
4.3.2 Use of chemical surfac 9
4.3.3 Specimen panels of concrete 9
4.4 Repair of Concrete ................................................................................................................ 39
4.4.1 General 9
4.4.2 Protrusions ...............................................................................................................40
4.4.3 Depressions ................... .
..
................................................................................
40
4.4.4 Sealing of cracks .....................................................................................................40
4.5 Protective Coatings and Linings ............
4.5.1 General ...............
4.5.2 External coatings
5 EMBEDDED PARTS, BLOCKOUTS, HOLES ........................................................................42
5.1 Embedded Parts 2
5.2 Embedding Steel Linin 2
5.3 Block Ou ...................................42
5.4 Drainage 43
6 PERMISSIBLE CONSTRUCTION TOLERANCES ...............................................................44
6.1 General
. .
6.2 Permlss~bleTolerances ......................................................................................................... 44
6.3 Mass Concrete ................... .
................ . .............................................................................. 46
7 TESTS A3'D PROPERTIES ........................................................................................................47
7.1 Quality Control and Assuranc ...........47
7.1.1 Personnel 47
1 CONCRETE
1.1 General
These General Technical Specifications provide for execution of Concrete and Reinforced Concrete Works.
The Contractor shall indicate in his general work plan which standards he will apply in the performance of
the works.
Within four weeks after having received the notice to proceed, the Contractor shall submit one complete set
of the relevant Standards to the Employer in the English language.
The application of other than internationally recognized Standards shall be avoided, as approval for its use
by the Employer might take considerable time, which could delay the construction works.
No concreting works shall be started unless the Employer has agreed upon the Standards applied.
1.1.1.1 Definitions
1.1.1.1.1 Materials
Concrete: Concrete is formed from a mixture of cement (or, in certain circumstances, a slag-
based cementitious material), aggregate and water and possibly with admixtures and
additives.
Aggregates: Aggregates consist of natural or artificial, dense or porous stone, with particle sizes.
which are suitable for making concrete.
Binders: Binden of concrete are cements and in special cases also slag-based cementitious
materials.
Water: Water, which is added to the concrete in the mixer, is referred to as mixing water.
The mixing water and the natural surface moisture content of the aggregates
constitute the water content " W . The water content " W plus the pore moisture
(internal moisture) is designated as the total water quantity.
Admixtures: Admixtures are substances, which are added to the concrete and which, by chemical
or physical action or by both, change the properties of the concrete, e.g., its
workability, hardening or setting.
Additives: Additives are substances of small particle size added to modify certain properties of
the concrete and which have to be taken into account as volumetric constituents
(e.g., latently hydraulic materials, (uass) body pigments).
Cement Mortar: Cement mortar is formed from a mixture of cement, and aggregates of not more
than 4 mm particle size and water - and possibly with admixtures.
Reinforced concrete is a composite consuuction material of concrete and steel (as a
rule: steel intended for the reinforcement of concrete) for components in which the
co-operation of concrete and steel is necessary to resist the load stresses.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete &Reinforced Concrete - 2
Reinforcement: The steel elements, which are embedded in the concrete and are necessary for
reinforced concrete in accordance with definition of "Reinforced Concrete", are
referred to as reinforcement.
Reinforcing bars are herein classified as plain (smooth), ribbed (also known as
deformed, that is, with irregularities protruding outwards from the otherwise
smooth surface), and indented (profiled, that is, with irregularities occurring below
the otherwise smooth surface).
Furthermore, reinforcement denotes prefabricated reinforcement consisting of steel
lattice assemblies or profiled light steel girders, possibly with factory-made
concrete chords, which may in certain circumstances serve also to support loads
exerted by floors before in-situ concrete has hardened.
The stability and adequate dimensioning of the structure and its components shall be analyzed in a
conveniently presented and readily checkable form in the calculations, if not otherwise specified.
The method of analysis in accordance with the elastic theory is optional. Dimensional design shall conform
to the principles laid down in the respective standard. If unusual formulae are employed, the source from
which they have been obtained shall be indicated if it is generally available for verification; otherwise the
derivations shall be given in sufficient detail to enable checking.
Calculations performed on computers are permissible, subject to compliance with official directives
relating thereto. These rules are particularly applicable to false work and scaffolding.
1.1.1.2.4 Specifications
Information which is necessary for the execution of the Work or for checking the Execution drawings and
structural calculations, hut which is not directly obtainable from Contractual Conditions, or where
clarification or interpretation is required, such information, clarification andlor interpretation shall he
provided by the Employer.
For pre-cast concrete structures or the structural elements, the Contractor shall give particulars of the
erection procedure, including temporary supports (propping), adjustment, and intermediate conditions of
the structure or element which will occur during erection and which are important with regard to safety.
The erection procedure shall be described with particular accuracy if the pre-cast components are to be
assembled by an erector other than the manufacturer of those components.
the intended commencement of concreting for the first time; and for multi-storey buildings, if
required, the commencement of concreting for each individual storey; and in the event of prolonged
interruption (particularly during fairly long periods of intemperate weather), the resumption of
concreting works
for pre-cast concrete structures; the commencement of erection and, if required, the commencement
of forming the connections which are important to the overall structural action.
that formwork is cleaned and erected to dimensions and levels
that reinforcement is correct to diameter and number of form
that reinforcement is properly placed in accordance with Execution drawings and Specifications
that any embedded part other than reinforcement is properly placed, secured and protected to prevent
entrance of cement slurry or other damages or dislocations
that adequate means are available to protect fresh concrete from rain, frost, vibration or other
detrimental impacts
that all equipment, plant, tools, facilities are at disposal and operational to warrant unintermpted
concreting works for the pan or section in question
commencement of important welding operations at or on the concreting site
h m n m V a Iu &
I vohmI~~~.cZcm6.^ i t&rd l 8 ~ a t ~ ~ 1 n s k ~ I O c ~ ~ ~ ke X ~, d~ . I _ m ~
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 5
When ready-mixed concrete is used: the names of the supplier and the delivery note numbers, the
concrete type schedule and the vehicles schedule. It shall also be indicated for what pan of the
structure or what job sections the concrete has been used.
The manufacture of all the concrete test specimens with their designations, dates of manufacture. and
information on the individual parts or job sections for which the concrete has been used, the testing
dates and results of the tests, and the required strength class.
These requirements shall also apply to specimens made by the ready-mixed concrete supplier or his
representative, where such specimens count as Site specimens. Records shall also be kept of the
nature and results of any verification tests for the concrete strength performed on the structure.
When applicable: the results of investigations on the fresh concrete (consistency, bulk density,
composition), tests on the cement, t e a on the aggregate (e.g., grading curves) including already-
mixed aggregate tests for checking the aggregate mix-proportions by weight in the event of volume-
batching, tests on intermediate components, etc.
Type of reinforcing steel and, when applicable. the results of tests on welds in reinforcing bars.
12.1 Binders
The main binding agent shall consist of cement in one of several varieties. Binders shall conform to the
relevant applicable Standards of the country of origin or to equivalent Standards.
1.2.2 Aggregates
1.2.2.1 General
The Contractor shall be responsible for all arrangements and costs involved in the exploitation of quarries
and borrow pits and he shall carry out any borings and investigations he deems necessary to determine the
precise location of the working and the manner in which the quarries and borrow pits may be exploited
efficiently and economically.
Quarries shall be run in a safe manner and on completion of the Works they shall be left in a tidy state. No
rocks shall be left overhanging except with the approval of the Employer. The aggregate winning and
processing operations shall be such that they do not constitute a danger to health either during their
operation or after completion of the Works (dust control). The Contractor shall ensure that his activities in
no way interfere with existing operations being carried out by others, and shall be responsible for providing
his own local accesses and all plant and facilities.
1.2.2.2 Sources
Aggregates for concrete shall be obtained from sources to be approved for this purpose by the Employer.
The Contractor shall be responsible for selecting suitable aggregates. Samples of sand and stone shall be
obtained for the tests specified in Clause 7 to be carried out before any arrangements for obtaining
aggregates from new or alternative sources are approved by the Employer. Laboratory check tests of the
aggregate may be ordered by the Employer at regular intervals to confirm their suitability for concrete and
the consistency of the grading.
1.2.2.3 Prodoction
Aggregates shall be produced to the sizes and grading specified for the various concrete mixes. If instructed
by the Employer, the Contractor shall carry out investigations to satisfy the Employer that there are
sufficient quantities of suitable aggregates available to complete the Works.
1.2.2.5 Properties
1.2.2.5.1 General
Aggregates shall be in all cases free from earth, clay, loam, soft, clayey, shaley or decomposed stone,
organic matter and other impurities like mica and shall be hard and dense.
Aggregates shall be as coarse-grained and dense-graded as possible. The maximum panicle size shall be so
chosen as to be compatible with mixing, handling, placing and working the concrete; its nominal size shall
not exceed one-third of the smallest dimension of the component to be concreted. With closely spaced
reinforcement or shallow concrete cover, the greater part of the aggregate shall consist of panicles smaller
than the distance between adjacent bars and between the bars and formwork.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 7
1 2 1 5 . 4 Moisture of aggregates
The free moisture content of the fine aggregates shall be continuously controlled and measured twice daily
in the stockpiles of the batching plant. The Contractor shall accomplish the required moisture control by
use of free drainage storage, covered transportation and storage, mechanical dewatering devices, or any
other means.
1v volume ..
<r.w<!mn 6-rn 2<whnlcds w 8 f i ~ o m k h ~ p t maOm t c d mhfwcd c o m ~ c k X > ~ ~ U 8
\*-
Dagachhu HPP Section 6Employer's Requirements 6.2 Technical Specifications
Chapter 07 Conmte & Reinforced Concrete - 9
The Contractor shall he responsible for ensuring that the combined grading of the aggregates is constant
during the Works. The percentage required to pass any sieve size as determined by approved trial mixes
shall be the target grading for all concrete of that type. The combined grading of the Works concrete shall
not vary by more than +5% from that found from the trial mixes. If the estimated or measured combined
grading of the permanent Works concrete does not meet this requirement, then a new trial mix shall be
prepared for the approval by the Employer. Modifications shall be made if the Employer is not satisfied
that the plastic properties of the mix are the same as those of the agreed trial mixes.
If at any time samples prove unsatisfactory, the Contractor will be required, at his own cost, either to
change to a new supply or to make arrangements acceptable to the Employer to remedy the situation.
1.23 Admixtures
For concrete manufacturing, the Contractor shall use admixtures only at his own cost and risk and with the
Employer's previous written approval.
The Contractor shall notify the Employer of the sources from which admixtures will be obtained and shall
fumish technical information and samples for testing at least 90 days in advance of the time when concrete
placing is expected to begin. All tests for the evaluation and approval of an admixture shall be made by the
Contractor as specified by the Employer.
Chlorides, substances containing chlorides or other substances, which promote the corrosion of steel, shall
not be added to concrete in which steel or reinforcements are embedded.
The Contractor shall state in writing the chloride content of the admixture and whether or not chloride has
been added during its manufacture.
Admixtures may be used to modify particular properties of concrete. However, as they may at the same
time adversely affect other important properties, preliminary tests with the concrete to which they are to be
added shall be performed as specified.
1.2.5 Steel
.
rvmnlrUdl I rivli ur!rb\laI mhm; b i l p n $$--an 6~\62t.rhnk~ii~ilic~l~on"rbm01ronmt~~drrinlomd
m-c~dnx
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete &Reinforced Concrete - 10
The adhesion of the coating shall be evaluated by bending samples of coated bar 12.00 mm in diameter
around a bending mandrel with a diameter equal to eight times the bar diameter. Any cracking or
disbonding of the coating which is visible to the unaided eye on the outside surface of the bent bar, shall he
considered cause for rejection.
12.6 Concrete
Concrete is classified into strength classes according to relevant standards on the basis of its characteristic
compressive strength determined in the quality control tests on cubes or cylinders tested at an age of
28 days. The term 'characteristic strength' means the value of the strength of concrete below, which no
more than 5% of the test results shall fall. The concrete characteristic strength ranges generally between 5
and 55 NImm2.
A particular compressive strength may also be necessary at an earlier age than 28 days, to satidy particular
stress conditions, e.g., for the hanspoa of precast components. Alternatively, a particular strength may be
agreed for a later point of time, e.g., if this is appropriate in special cases when slow-hardening cement is
used and if it is permissible with regard to the stresses to which the concrete will be subject Concrete
grades of more than 45 Nlmm2 are intended for precast concrete components manufactured under factory
conditions.
In-situ concrete, which is intended to serve integrally in a structural way with precast reinforced concrete
components, shall have a minimum compressive strength of 15 NImmZ.
Concrete may also he classified with respect to consistency ranges for fresh concrete, amording to relevant
standards. Within these ranges the consistency shall, if necessary, be more precisely specified by a
particular value for the compaction or the flow- table spread.
The consistency of the fresh concrete shall be determined before the start of work, taking due account of
the conditions of placing and working the concrete during construction (e.g., type of compaction).
Dngachhu HPP Seelion 6- Empluyris Requiremcnrs 6 2 Tcchnicnl Specificntiwr
Chapter 07 Con&c & Reinforced C o n m c - 12
i I I
CLASS i
=Strength / Cement Type 1
Minhnum
Cemea WIC-Ratio mnr. ! Strength
[N/mm2] :
I
after 28 f
! Content
i ikdm31 to
11 Free-water
related
f [NlmmZ]
after 7 days
i
days i ensure i
!
1
durability ii ;
16 i
'-----.
OPC f 2.20
--- 0.80 i 12
I
225
-- OPC 240 i-- 0.80
i 17
30 OPC 240 1 0.70 23
The cement content derived by trial mixes to reach a certain concrete sfrength has to be checked against the
minimum cement content for the requirement of durability (see above table) and the greater of the two
values has to be adapted.
Note: Using cement according to Indian Standards requires amuchhighercement content
1.2.6.1.3 Admixtures
In the event of the Employer's permission being obtained for the use of a proposed admixture, the concrete
tests described in this Section shall be carried out with the correct proportion of admixtures incorporated in
the concrete to ensure that the specified strengths are achieved and comparison shall be made with concrete
manufactured without the admixture to prove that the density has not been reduced. If air-enuaining agents
are used, the density shall not be reduced by more than 5%.
When admixtures are used in the concrete very strict control shall be maintained to ensure that the correct
quantity of admixture is used at all times. The equipment to be used for dispensing and the method of
incorporating the admixture in the concrete shall be to the approval of the Employer. The dispensing unit
shall be translucent such that the operator can see the discharge of the admixture.
In the event of the Employer's permission for using a proposed fly ash being obtained, the concrete tests
described in this section shall be carried out with the ratio of fly ash envisaged for the purpose.
Massive structures
,..... ,
Slumps shall be measured at the batch plant and before placing of concrete as directed by the Employer.
Slump will be determined in accordance with adequate Specifications.
~ ~
.'
Dagachhu HPP Section 6 Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 14
1.2.6.33 Batching
Generally, concrete shall be batched by weight. The aggregates and the cement shall be batched by means
of efficient weight-batching machines except as otherwise approved by the Employer. The machines shall
be carefully maintained and cleaned. They shall be provided with simple and convenient means of checking
the accuracy of the weighing mechanism, and they shall be checked and adjusted when required by the
Employer.
The weight of the batched particle size fractions shall be checked frequently. This requirement shall also
apply when automatic proportioning devices are used.
Dagachhu HPP Section 6 -Ernplayer's Rcquirernents 6.2 Technical Specifications
Chapter 07 Concntc & Reinforced Concrete - 15
1.2.6.5.1 General
Pre-requisite conditions for producing concrete with special properties are that it shall be correctly
composed, mixed and placed, that it shall not segregate and that it shall be completely compacted and
carefully cured.
1.2.7.1 General
Forms shall be constructed true to dimensions and level from sound materials of sufficient strength, and
shall be properly braced, strutted and shored, to ensure rigidity throughout the placing and compacting of
the concrete, without visible deflection. Forms shall be so constructed that they can be removed without
shock or vibration to the concrete. Internal ties shall be of metal and shall either be capable of complete
removal without permanent injury to the concrete or, if remaining permanently embedded in the concrete,
be no nearer than 5 0 mm to any finished surface and the cavity shall be so formed as to permit a
satisfactory filling as specified hereafter.
All joints shall be close fitting to prevent leakage of cement slurry and at construction joints; the formwork
shall be secured tightly against previously cast or hardened concrete to prevent stepping or the formation of
ridges on exposed surfaces.
Formwork shall be constructed to provide the correct shape, lines and dimensions of the concrete shown on
the Execution drawings. Due allowance shall be made for any deflection which will occur during the
placing of concrete within the forms.
Dagachhu HF'P Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 19
Panels shall have true edges to permit accurate alignment and to provide a neat line with adjacent panels
and at all construction joints. All panels shall be fixed with their joints either vertical or horizontal, unless
othenvise specified or approved. When chamfers are to be formed, the fillets shall be cut to size accurately
to provide a smooth and continuous chamfer.
The Contractor shall make due allowance for the renewal and/or repair of formwork for which more than
one use is intended.
12.8.1 General
Materials used in the work of this clause shall conform to the latest Standards, and application shall be in
accordance with the manufacturer's instructions.
12.83 Fillers
Fillers shall be of inert mineralic origin and shall serve to increase the stability of the mastic.
12.9.2 Aggregates
Aggregates shall be delivered, stored and handled so as to avoid mixing of different sizes, segregation in a
particular size, breakage, contamination with deleterious matter and retention of water. Sufficient aggregate
shall be stored for at least 48 hours before use. Fine aggregate shall not be drawn from the bottom (50 cm)
of the stockpile. Provision shall be made for suitable equipment to effect spraying or sprinkling of
aggregates during hot periods.
Each size of aggregate or defined combined fractions thereof shall be stored separately.
The storage bins shall be emptied and cleaned and the grading of the aggregates checked at intervals.
subject to the appmval by the Employer.
Sufficient aggregate shall be maintained at Site at all times to assure continuous placement of concrete at a
rate consistent with the requirements of the appmved concreting schedule. In no case shall concreting of
any lift he started unless sufficient aggregate is on hand to complete the lift.
13 Execution of Work
For concrete the hatching of the aggregate or of individual particle size fractions by volume shall he
permissible only if automatic proportioning devices are used whose settings can be easily and effectively
altered when necessary and with which the fractions and the combined aggregate quantity can he measured
with the required accuracy. It shall he possible simply and reliably to check the weight of the particle size
fractions measured by these proporlioning devices.
If volume batching is applied, the weight of the batched particle size fractions shall be checked frequently.
This requirement shall also apply when automatic proportioning devices are used.
Measuring of water: The mixing water shall he added in a quantity measured with an accuracy of 3%.
The surface moisture of the aggregate shall be taken into account.
Water-absorbent aggregate shall be so moistened beforehand that it will, as far as possible, absorb no more
water during and after mixing.
For admixtures or additives special automatic devices shall be installed at the mixing plant.
1.3.5.3 Preparation of f o m w o r k
The formwork shall be coated with an approved mould oil and all excess shall be removed carefully. Mould
oil shall not be allowed to come into contact with concrete already placed or with reinforcement.
Before concrete is placed, all formwork and supports shall be cleaned thoroughly. Temporary openings
shall be provided to permit the removal of the rubbish.
Concrete shall not be placed until the relevant formwork has been inspected and approved by the Employer
though the giving of this approval shall not relieve the Contractor from the requirements as to soundness,
finish and accuracy specified elsewhere.
A period of not less than 24 hours notice shall be given to the Employer to allow for his examination and, if
satisfactory, approval of the reinforcement and form-work prior to placing concrete.
The following table is a guide to the minimum periods, which must elapse, between the completion of the
concreting operations and the removal of formwork. Notwithstanding this table, no prop or formwork shall
be removed without the permission of the Employer and the giving of such permission shall not relieve the
Contractor of this responsibility for the safety of the structure.
Vertical sides of beams, walls, columns - lift not exceeding 1.2 m 12 hours min
Vertical sides of beams, walls, columns - lift exceeding 1.2 m 36 hours min
Soffits of beams and main slabs (props left under) 5 days min
Beams and main slabs -removal of props 18 days min
After removal of formwork, no remedial works shall be attempted until the Employer has inspected the
work. If. in his opinion, any defect cannot be made good satisfactorily, he may direct the Contractor to
replace such work at the Contractor's expense.
13.5.4.1 Props
In order to minimize the deflections due to creep and shrinkage, props shall remain in position or be
installed immediately after stripping of formwork. This applies also to the composite components
comprising pre-cast concrete and in-situ concrete.
Props shall remain in position for as long a period as possible, particularly for structural components, which
are subjected to a major proportion of their design loading as soon as the formwork has been removed or
from which the formwork is removed at an early age. In multi-storey buildings, the props shall be
positioned one over another.
For beams and slabs with spans of up to about 8 m, it is sufficient to install propping at mid-span. With
longer spans, more props shall be provided. For slabs spanning less than 3 m, it is as a rule unnecessary to
use propping.
2 STEEL REINFORCEMENT
2.1 General
Steel reinforcement shall be cut, bent and fixed in accordance with relevant Standards. Generally, it shall be
bent cold in a manner, which will not damage the material. Bending hot at a cherry red heat (i.e., not
exceeding 840 degrees C) may be allowed except for bars, which depend for their strength on cold
working. Bars bent hot shall not be cooled by quenching.
If cold worked reinforcing steel is heated for the purpose of working it, it shall be considered as mild steel.
This limiting condition does not, however. apply to the heat involved in welding the steel in accordance
with Standards.
Annealed wire (e.g., for stirrups with a diameter de=3 mm) may have the properties of mild steel
Bends, cranks or other labors on reinforcing bars shall be formed carefully in accordance with relevant
Standards and with the working Execution drawings.
The number, size, form and position of all steel reinforcing bars, ties, links, stirrups and other parts of the
reinforcement shall be in accordance with the Execution drawings. All parts of the reinforcement shall be
maintained in the correct position in the forms without displacement during the process of vibrating,
tamping and ramming the concrete in place. The Contractor shall provide all necessary distance pieces and
spacer bars at his own cost to maintain the reinforcement in the correct position. Any ties, links or stirrups
connecting the bars shall be taut so that the bars are properly braced and the inside of their curved parts
shall be in actual contact with the bars around which they are intended to fit. Bars shall be bound together
with best black annealed mild steel wire approximately 1.0 mm diameter or other approved binders. Wire
binding shall be twisted tight with proper pliers. The free ends of the binding wire shall be bent inwards.
The Contractor shall also provide for support of working platforms to be used by labor during compaction
in concreting sections with high lifts.
Such support, preferably provided of reinforcement steel and welded to the reinforcement may remain in
the placed concrete.
The Contractor shall keep the records on steel weight used for auxiliary constructions within formwork
Before any steel reinforcement is embedded in the concrete, any loose rust and any oil, grease, salt
contamination, products and causes of pitting, or other deleterious matter shall be removed from it, by grit
blasting, mechanical wire-brushing and/or washing. The methods of removal to be adopted will depend on
the degree of contamination and/or corrosion and shall be to the approval of the Employer. Partially set
concrete, which may have adhered to exposed bars during previous concreting operations, shall likewise be
removed.
Reinforcement left projecting temporarily from the concrete at construction or other joints shall not be bent
out of position during the period in which concreting is suspended. except with the approval of the
Employer. When such approval is given, the reinforcement shall be bent out over a suitably sized former to
prevent any damage to or over stressing of the reinforcement.
Electric arc welding may be permitted in some locations for joining bars, subject to the approval by the
Employer. For work of this type, the use of electrodes of the covered alloy or shielded arc type will be
permitted provided that they conform to the requirements of latest editions of relevant standards. All such
connections shall be butt-welded with Standard Double V or Double U welds.
Particular care shall be taken to ensure that the reinforcing bars are positioned given the shape (including
diameter of curvature), length and position conforming to the reinforcement Execution drawings. If internal
vibrators are used to compact the concrete, the reinforcement shall be arranged in such a way that the
vibrators can be inserted at all necessary points.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 29
2.7.1 General
Tensile splices in reinforcement may be formed as follows:
- laps formed with or without hooks on the ends of the bars
- loops
- welded-on transverse bars
- welding
- screwed connections
Tensile splices in flexurally stressed cross-sections shall, as far as possible, be situated outside the regions
where the steel cross-sectional areas are fully utilized and be distributed as uniformly as possible
throughout the reinforcement in the cross- section and he staggered as much as possible in relation to one
another in the longitudinal direction. The clear transverse distarice between reinforcing bars in the vicinity
of splices shall he more than 2 de and not less than 2.0 cm.
A transverse reinforcement to resist the transverse tensile stress sball he provided in the vicinity of laps in
tensile reinforcing bars. If the diameter of the spliced hals is more than 14 mm. the transverse
reinforcement shall be located to the outside.
For welded fabric mats, it i s not necessary to provide additional uansverse reinforcement in fhe Vlcirilty of
the splice.
In the case of predominantly non-static loading, the only welded splices in reinforcing bars shall
be those formed by electric flash butt welding, and only 85% of the normal (non-welded) cross-section
shall he taken into account at the splice, and in this case, the stress due to the non-static loading must not
exceed 100 NImm2.
Fabric mats with bar diameter de 8.5 mm and comprising twin bars or pairs of bars may be spliced only if
there are several layers of mat reinforcement, in which case these mats shall be placed in an inner layer and
the spliced cross-sectional area of reinforcement shall not exceed 60% of the cmss-sectional area of
reinforcement required at the splice.
If mats in multi layer reinforcement are spliced, the splices in the individual layers shall be staggered by
amounts equal at least to the lap length (lo) plus one mesh dimension. Fabric mats composed of ribbed bars
may alternatively be spliced according to the rules for reinforcing bars without taking account of transverse
bars as contributing to anchorage.
In that case, the spliced bars with de 8.5 mm (for individual bars) or de 6.5 mm (for twin bars or pain of
bars) shall be situated on one level; however, with predominantly non-static loading, in the lapped zone of
such splices any welded-on transverse bars shall be to the inside.
The lap length (lo) for bars functioning as main reinforcement shall be as indicated in Standards, provided
that the reinforcement is not more than two-thirds utilized; if it is more highly utilized, the lap length
should be increased proportionally. i.e., its maximum length in cm, and the requisite number of meshes
should be increased. but without rounding to whole meshes.
In slabs spanning in two directions in ordinary buildings, such increase in lap length is not required for the
inside bars of a reinforcing mat.
The lap length for bars constituting the transverse reinforcement shall be as indicated in the Table given
below.
In the case of predominantly non-static loading, the lap length shall be increased by at least 5 cm and the
number of transverse ban shall be increased by at least one.
2.9 Connections
3.1.2.1 General
Joints in the concrete shall be constructed at such points and of such dimensions as are shown on the
Execution drawings. Except where indicated on the construction Execution drawings, no fixed metal
embedded in the concrete shall be continuous through an expansion joint.
The requirements stated in this Clause are applicable also to unforeseen construction joints necessitated, for
example, by weather conditions or plant breakdown.
The joints shall be dried by application of beat. The joints shall be filled immediately following the curing
period or as soon thereafter as weather conditions permit or as directed. Immediately before filling, the
joint shall be cleaned of all dust, dirt, fragments, concrete, or other objectionable material by a light
sandblasting or other approved methods.
Sawed joints shall be cut in the hardened concrete by using either a reinforced abrasive blade or a
steel blade edged with diamonds. The blade shall be cooled and lubricated abundantly with cold
water. The joints shall be sawn at from 8 hr to 48 hr or as directed after the placement has been
completed. The concrete saw shall be properly supported to yield a sawn joint 80 mm deep and true
to line and grade along its entirety.
Contraction joints shall be formed as deliberate planes of discontinuity on the concrete structure. To
form such a joint, the face of concrete slab or block first formed shall be painted with two coats of
approved rubber bitumen paint before the adjoining slab or block is concreted. The adjoining slab or
block shall be cast with a suitable groove against the joint to accept sealant. The exposed edges of
the joints shall be chamfered and sealed with an approved polysulphide rubber-sealing compound.
When in the opinion of the Employer a contraction joint is likely to be contaminated with deleterious
materials, the joint shall be sealed immediately with an approved sealing compound as soon as
strikin~of the formwork has been completed.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 36
- Expansion joints in non-water retaining structures, where specified. shall be formed in the same way
as contraction joints but in addition, an approved compressible filler of bituminous flexcell or
another non absorbent material shall be placed in the joint to allow expansion of the two adjacent
concrete slabs. The adjoining slab shall be cast with a suitable groove against the joint to accept
sealant. The exposed edges of the joints shall be sealed with approved poly-sulphide rubber sealing
compound.
- Where a design joint occurs in a water-retaining structure, or where otherwise ordered, the joint shall
be made water-tight by the provision of a continuous water stop suip as specified by the Employer,
fixed across the joint where shown on the Execution drawings. Detailed instructions can be seen in
Chapter 08. "Waterproofing". The width of each water stop shall be in accordance with the
Execution drawings. Special care shall be taken to ensure that the concrete is well worked against
the embedded parts of the strips and is free from honeycombing. Precautions shall be taken to
protect any protruding portions of the strips from damage during the progress of the Works and, in
the case of rubber and plastic, from heat and extended sunshine exposure.
The method of jointing water stops shall be in accordance with the manufacturer's insuuctions and to the
approval by the Employer. Whenever possible, complete water stop systems shall meet the specific
requirements of the Work and ensure easy and economical placement with minimum joining up on Site.
The appropriate width of water stop shall depend upon the thickness of the concrete, the size of the
aggregate and the position of the reinforcement. The following rules shall be applied to ensure a
satisfactory selection:
- The overall width of the water stop shall not be greater than the thickness of the concrete into which
it is cased.
- The distance from the face of the concrete to the water stop shall not be less than the width of the
water stop.
- To obtain satisfactory compaction, the width of water stop shall not be less than six times the largest
aggregate size.
- The water stop shall not be positioned closer to any reinforcement member than a distance equal to
twice the size of the largest aggregate, in order to avoid unsatisfactory compaction.
Where expansion joints are concerned, the maximum width of the joint shall be added to the figure
obtained by applying the above rules.
DqachhuHPF' Section 6 - Employds Rquirtmcnts 6.2 Technical Specifications
Chapter 07 Concmc & R c i n f d Conmte - 37
4.2.1 General
Immediately afrer compaction and for a sufficient period thereafter, i.e. during the mahuhg period, all
concrete shall be protected against harmful effects to the satisfaction of the Employer.
Until it has hardened sufficiently, concrete shall be protected from harmful influences, e.g., severr cwling
or heating, drying (including d q b g due to wind), heavy rain,running water, chemical and mechanical
attack, and fiom oscillations and vibrations insofar as these are liable to loosen the texture of the concrete
and endanger the bond between reinforcement and concrete. Tbis shall apply also to mortar and concrete
placed in the joints between precast concrete components.
Curing period (m general, minimum 7 days) as well as curing method and medium (water, covering, curing
comp+unds) shall be approved by the Employer.
The method of curing and its duration shall be such that the concrete will have satisfactory durability and
s-gth and that the results of movements of m o i s m or changes in temperahue in and around the
concrete will not cause any member to become defective. Curing measures shall take account of the various
factors influencing curing.
The Contractor shall have all equipments and materials needed for adequate curing and protection of the
concrete on hand and ready to use before actual concrete placement begins. The curing medium shall be
applied M, as to prevent loss of moisture fromthe concrete. Concrete shall be protected from heavy r$ns
for 12 hours and direct rays of the sun for 3 days. All concrete shall be adequately protected from damage.
No fire of excessive heat, including the heat resulting from the welding of liner plates or reinforcing bars,
shall be permitted near or in direct contact with concrete at any time. All galleries, conduits and orher
formed openings through the concrete shall he closed during the entire curing period.
Where water is to be used for curing concrete it shall be fresh water in accordance with the requirements of
this chapter.
Where the use of a curing compound is proposed, the particular compound and method of application shall
be subject to the approval of the Employer. The rate of application of an approved compound shall be
trictly in accordance with the manufachlrer's recommendations.
Dagachhu HPP Sntion 6 - EmployeCs Requirements 6 2 Technical Specifications
Chapter 07 Connelc & Reinforced Concrete - 38
Where timber or other insulating formwork is used it shall either be struck in accordance with the
Specification or be left in place until such time after the temperature peak is reached as the Employer may
diit. :-
Air cirmlation shall be prevented as far as possible along the exposed faces of concrete during the curing
period.
All concrete shall he protected iium anything likely to interfere with the process of setting. No load of any
kind shall he imposed upon any concrete members until the concrete has hardened sufficiently to resist the
imposed load.
The surfaces of the concrete shall he protected from contamination of any sort for a period of not less than
30 days from the date of pouring.
When curing membranes areused, they shaU he compatible with waterproofing or other materials that may
be applied subsequently to the surface of the concrete.
In order to slow down the shrinkage of the young concrete and to ensure that it will also harden properly at
the surface, the concrete curing shall be performed continuously, starting as soon as practicable after
placing and shall also include surfaces of forms and lamings.
~he'hardmingof concrete may be accelerated by means of heat treatment applied correctly in accordance
with the mles of concrete technology.
Cmnponents, which have been heat-mated, shall be kept moist, since hardening has, in general, not been
completed at the end of the heat treatment and the concrete dries considembly on cooling.
43 Finishing
The finished faces of all concrete work shall be sound, solid and free from defects. All exposed arises shall
have a 25 mm x 25 mm chamfer unless otherwise specified or shown on Execution drawings. No rendering
of imperfect concrete faces will be allowed and any concrete that is defective in any way, including color,
shall be cut out and replaced to such depths, or be made good in such manner, as the Employer may direct.
All concrete shall be dense, sound, even textured and free from defects both internally and externally.
43.1 Sprinkling with cement
Sprinkling of the surfaces with dry cement or any other material during finishing operations for drying off
the concrete, to facilitate trowelling or for any other purpose will not be permitted.
4.3.2 Use of chemical surface r e t a r d e n
The use of a chemical surface retarder will only be permitted as an alternative means of producing a
decorative exposed aggregate finish, subject to the approval of the Employer, of the type and rate of
application of the retarder and to demonstration by the Contractor that a finish can be achieved which is
deemed acceptable by the Employer, without detriment to the durability of the concrete which remains at
the exposed surface.
433 Specimen panels of concrete
Where required by the Employer, the Contractor shall construct and treat specimen panels of concrete to
the finish required, in order to satisfy the Employer as to the suitability and effectiveness of the proposed
method of treatment.
4.4 Repair of Concrete
4.4.1 General
Repair of surface blemishes or imperfections in concrete shall be completed within one day after removal
of forms. Fins and encrustations shall be neatly removed from exposed surfaces. Concrete that is damaged
or defective, such as that containing spalls, broken edges, rock pockets, honeycombs, or unconsolidated
concrete, shall be repaired by removing the damaged or defective concrete to sound concrete. Repair of
damaged or defective concrete shall consist of an initial cut of 2.5 cm in depth made by a diamond saw
around the damaged or defective area, chipping of the concrete inside the area to sound concrete, and
replacing with dry pack, mortar, or concrete as directed. Feather edging of replaced materials shall be
avoided. No repair of imperfections shall be undertaken until the Employer has inspected the imperfections.
The methods used to repair each individual area of imperfection shall be approved. Skilled workmen shall
perform repairs.
All fillings bonded tightly to the surfaces of the holes shall be sound and free kom shrinkage cracks and
drummy areas, shall be properly cured, and shall match the adjacent concrete in concrete colour after the
fillings have been cured and have dried.
A coating of an approved 2 component, epoxy adhesive shall be applied to all concrete for repairs.
Application shall he in accordance with manufacturer's instructions.
Where gradual and abrupt irregularities exceed the limits specified in Clause 6.2 -Permissible Tolerances -
the protrusions shall be reduced by bush hammering and grinding. Where dry pack filling is required, the
holes shall be sharp and square at the surface area, having a minimum depth of 2.5 cm and a width equal to
or greater than the depth.
Drypack shall be used for such repairs as for holes left by the removal of fasteners from the ends of the
form rods, for grout pipes and pipe recessed, and for narrow slots cut for repair of cracks. No epoxy
adhesive will be required for dry packing of tie rod holes, cracks, or small areas requiring repair.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specificationr
Chapter 07 Concrete & Reinforced Concrete - 40
4.4.2 Protrusions
Where bulges and abrupt irregularities protrude outside the specified limits, finishes and finishing on
formed surfaces the protrusions shall be reduced by bush hammering and grinding so that the surfaces are
within the specified limits. After repairing, the irregularities shall not exceed the specified limits, finishes
and finishings.
4.4.3 Depressions
General
All fillings for depressions shall be bonded tightly to the surfaces of the holes and shall be sound and free
from shrinkage cracks and drummy areas after the fillings have been cured and have dried. All fillings in
surfaces shall contain sufficient white Portland cement to produce the same color as that of the adjoining
concrete. Repairs shall be made with concrete filling, mortar filling, or drypack filling except where repairs
with epoxy concrete andlor epoxy mortar are directed to he made by the Employer. Concrete, mortar and
drypack mortar filling shall each be mixed in proportions approved by the Employer to produce a repair at
least equivalent in strength and durability to the concrete in which the repair is required.
Concrete Filling
Concrete filling shall be used for holes extending entirely through concrete sections; for holes in which no
reinforcement is encountered and which are greater than 0.1 m2 and deeper than 10 cm; and for holes in
reinforced concrete which are greater than I12 of 0.1 m2 and which extend beyond reinforcement.
Mortar Filling
Mortar filling, placed under impact by use of a mortar gun, may be used for repairing defects on surfaces
where the defects are too wide for drypack filling and too shallow for concrete filling and are no deeper
than the far side of the reinforcement that is nearest the surface.
Drypack Mortar Filling
Drypack mortar fillings shall be used for filling holes having a depth nearly equal to, or greater than, the
least surface dimension; for narrow slots cut for repair of cracks; for grout pipe recesses and for tie rod
fastener recesses as specified. Drypack monar shall not he used for filling behind reinforcement or filling
holes that extend completely through a concrete section. If removal of the ends of form ties results in
recesses, the recesses shall be filled with drypack mortar pmvided that filling of recesses in surfaces
designated to receive finish F1 will be required only where the recesses are deeper than 25 mm in walls less
than 30 cm thick.
4.5.1 General
Where detailed, concrete structures shall be protected externally with an approved proprietary
waterproofing membrane, fixed to the concrete surfaces required to be protected. The membrane shall be
placed in accordance with respective regulations.
For floor slabs the membrane shall he laid sticky side down on a layer of blinding concrete and a 50 mm
protective layer of concrete shall be placed on it before steel fixing commences. The blinding layer and the
membrane, but not the protective layer, shall be made to protrude over a margin outside the lines of the
floor slab in accordance with the manufacturer's instructions.
For vertical or near vertical faces the concreting shall be done first and the surfaces allowed to dry. They
shall be cleaned of grease and dust and primed where appropriate. A fillet shall be formed at the comer
between the wall and the protruding memhrane-covered blinding layer. The membrane shall then be backed
to the wall, brought down over the fillet, extended over the protnrding margin of the bottom membrane and
pressed firmly onto it.
At joints between sheets of the membrane. suitable overlaps shall be provided and the two sides shall be
pressed together firmly to form a watertight seal. Membranes on vertical or inclined faces shall be protected
during backfilling with cardboard or other approved material, which shall he left as a permanent protection.
On aboveground structures with protected foundations, the protection shall be continued to a minimum
height of 300 mm above finished ground level unless otherwise shown on the Execution drawings.
C
nlaUol Icivil mrWn I wlum iiW ii-enan 6 q % . Z i & r a l r p a i k a l a n r t h a w c r 07 conmtr a d mlnfomd m r m t c k ~
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 42
6.1 General
Permissible surface irregularities for the various classes of concrete surface finish as specified for finishes
and finishing are defined as finishes, and are to be distinguished from tolerances as described herein. In
general, the permissible construction tolerances for structural concrete shall conform to the requirements of
the present clause, as applicable. The specific tolerances for each structure and pan thereof shall be as
determined by the Employer. Notations on the Execution drawings of specific maximum or minimum
tolerances in connection with any dimension shall be considered as supplemental to the tolerances specified
herein and shall serve as a control. The Contractor shall he responsible for setting and maintaining concrete
forms sufficiently within the tolerance limits so as to ensure that the completed work will be within the
tolerances specified herein. Concrete work that exceeds the tolerance limits specified herein shall be
remedied or removed and replaced by the Contractor.
buried construction,
....................................
rom the plump from the specified ba
from the curved surfaces of all structures, including
lines and surfaces of columns, walls, piers, buttress
arch sections, and visible arises
- ......
Dagachhu HPP Section 6 -Employer's Requirements
Chapter 07 Concrete & Reinforced Concrete - 47
7 TESTS AND P R O P E R T I E S
7.1.1 Personnel
Making. using, and testing concrete, and the supervision of concreting operations, shall require the
employment of reliable key personnel (agents, foremen, etc.) who have already been successfully engaged
in concrete and reinforced concrete construction and who possess adequate knowledge and experience for
the proper execution of such work.
For the execution of welding operations on reinforcing steel, the requirements for personnel and equipment
shall be as laid down in the relevant Standards or in these Specifications.
On Sites the Contractor shall use only key personnel (agents, foremen, etc.) who have previously been
responsibly concerned in making, placing and curing concrete of at least grade of 25 Nlmm2.
For the preparation, erection, assembly and support of formwork the Contractor shall employ a number of
skilled and experienced carpenters under the guidance of at least one carpenter foreman being responsible
for works and equipment at the carpenter's yard and one carpenter-foreman being in charge of erection,
assembly, support and dimension alignment and load control. The latter shall also be experienced in
handling and erection etc. of steel formwork.
The Contractor shall ensure that the key personnel, the skilled personnel (e.g., machine operators)
concerned with making concrete and formwork on the Site, and the skilled personnel of the permanent
testing laboratory are, at intervals of not more than three years, instructed and trained in the making.
placing and testing of concrete so that they are able to take all steps for the proper execution of the Work,
including testing and quality control.
The Contractor or the head of the permanent concrete testing laboratory shall keep records of the training of
his skilled personnel. In the case of independent concrete testing laboratories, the facilities shall be
inspected as to equipment range and functionality and the testing capacity be appraised in order to warrant
the timely completion of testing works.
Independent Laboratories shall be designated to the Employer in due time for his approval.
The concrete testing laboratory shall be under the direction of an expert experienced in concrete technology
and concrete making (e.g., concrete engineer). His specialized knowledge of concrete technology needed
for this function shall have been certified by a document (certificate, diploma) issued by an authorized
organization.
The Contractor is allowed to use the services of an independent concrete testing laboratory only if it has
been proved that this laboratory fulfils the requirements laid down in this sub-clause.
The test results reported by the concrete testing laboratories and the experience gained on sites shall be
analyzed and utilized for the benefit of subsequent work.
7.13 Equipment
The Contractor shall provide maintain and operate sufficient testing equipment to perform promptly all
required tests as specified. He shall also provide for sufficient test material storage and handling and curing
facilities including transpon from sampling places to the laboratory. Special arrangements have to be made
for the disposal of materials tested, considering environmental requirements.
In detail, the Contractor shall provide equipment. facilities and services for:
a) testing the constituents of the concrete, e.g., sieve tests on the aggregate;
b) testing the concrete, e.g., consistency measurements, checking the cement content in the fresh
concrete:
c) making and storing the specimens for testing the compressive strength and, where applicable, the
impermeability to water.
Paragraphs b) and c) shall also apply to tests of ready-mixed concrete.
For quality control, it shall be in addition necessary to have adequate equipment available for:
a) determining the settleable solids;
b) determining the inherent moisture of the aggregate;
c) testing the composition of the fresh concrete and the bulk density of the compacted fresh concrete;
d) determining the air voids content in the fresh concrete if air-entraining agents are used (e.g., by the
pressure method);
e) nondestructive testing of concrete;
0 checking the measuring appliances (e.g., by means of test weights).
For checking in doubtful cases, paragraphs c) and e) of this clause shall also be applicable to tests of ready-
mixed concrete. All the equipment and apparatus referred to in this clause shall be checked on Site before
concreting commences for the first time and thereafter at suitable intervals as determined by the Employer
to ensure that they function properly.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technica! Specifications
Chapter 07 Concrcte & Reinforced Concrete - 49
7.2 Submissions
7.2.1.1 General
The Contractor shall submit the details specified in the following paragraphs with respect to materials
covered by this Section of the Specification. Before orders are placed the Contractor shall submit details of
the proposed supplier(s) together with sufficient information on the proposed methods of transport, storage
and certification of the cement to enable the Employer to satisfy himself that the quality and quantity
required can be supplied and maintained throughout the period of construction. Having obtained the
Employer's approval of the source(s) of supply, and the methods of transpoc storage and certification of
the cement, the Contractor shall not modify or change the approved arrangements without first having
obtained the permission of the Employer.
7.2.1.2 Aggregates
The Contractor shall submit the following details in respect of aggregates proposed to be used in the
concrete:
source(s)
petrological type@)
7.2.13 Admixtures
The Contractor shall submit the following details in respect of admixtures proposed to be used in the
concrete:
- source(s)
- type(s)
- manufacturers' technical details
7.2.1.5 Water
The Contractor shall submit the following details in respect of water proposed to be used for the mixing
and curing of concrete and mortar:
source(s)
chemical analysis
- physical analysis
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 50
7.2.3 Certificates
The Contractor shall submit certificates of compliance with the specified Standards, or other recognized
and equivalent Standards, in respect of the materials mentioned in the following paragraphs.
7.2.3.1 Cement
The Contractor shall submit to the Employer, in respect of each consignment of cement delivered to the
Site, a certificate showing the place of manufacture and the results of standard tests carried out on each
day's bulk supply from which the cement was extracted. All cements shall be certified by the manufacturers
as complying with the requirements of the appropriate Standards.
7.2.4 Samples
The Contractor shall supply the samples specified in the following list
If so instructed by the Employer the Contractor shall deliver samples to a nominated laboratory for the
further analysis and testing envisaged in these Specification
Cement
Steel reinforcement
- Aggregates
- Flyash
Dpchhu HPP Seaion 6 - Employer's Requirements 6.2 Technical Specikications
Chaptcr 07 Con- & Reinforced Concrete - 5 1
7.25.1 General
Execution drawings shan be submitted according to Sub-clause 1.1.1.22 and to the following
requirements.
All execution drawings shall include the strrngth class and any special properties of the concrete.
73 PreUminary Testing
73.1 General
The materials shall he tested at the place of manufacture (or elsewhere if convenient and appropriate) by an
approved testing agency to ensure that they comply with this Specification.
The Employer may, at his discretion, decide that any consignment of material, on arrival at the Site and
also after it has been stored at the Site prior to use, be subjected to the whole of the tests and analpes
required by this Section and no materal of that consignment shall be used in the Works until it has been
tested by the Employer andlor accepted by him as satisfactory.
Observance of the required and specified properties of cement, admixtures and additives shall be proved
regularly by the producer of the cement and independently by govemment-owned institutes or material
testing institutes officially appointed for standard tests.
Where necessary, the Employer may require further representative samples of the proposed cement,
admixtures and additives to be taken and forwarded to a nominated laboratory for analysis and testing
before the source(s) islare approved.
733 Aggregates
Tests to assess the suitability of the aggregates proposed for use in concrete to be placed in the Permanent
Works shall be carried out only by the Contractor accprding to Standards at least 6 weeks prior to the start
of concreting works.
73.4 Steel
Observance of the required and specified properties of reinforcing and pre-stressing steel shall be proved
regularly by the producer of the cement and independently by govemmentawned institutes or material
testing institutes officially appointed for standard tests.
7.3.7 Concrete
Preliminary quality control tests (trial tests) shall be performed before the concrete is used in permanent
works. These tests shall verify that the composition, intended materials and consistency can be reliably
placed and worked under the conditions of the Site in question, such that the required propenies (including,
for example, the air voids content) are ascenained.
Preliminary tests shall be repeated if there has been a significant change either in the materials from which
the concrete is made or in the site conditions on which the preliminary tests were initially based.
Preliminary testing on the site may he omitted if such testing has been carried out by the permanent
concrete testing laboratory, or if ready-mixed concrete is used, or if the requisite properties have with
certainty been obtained, under the same working conditions for concrete of the same composition and made
with the same materials, in earlier tests.
For each mix prepared for the purpose of preliminary testing, and for each intended age at testing, at least
three specimens shall be tested. If it is expected that concreting on the work will be done in cold or in very
hot weather, particularly if admixtures, additives or slow-hardening cement are used, the Contractor shall
also determine the workability, the setting time, and the hardening of the concrete under such temperature
conditions. This shall also apply to ready-mixed concrete. If heat treatment is employed, it shall be
ascertained by preliminary tests that the required strength can with certainty be attained with the intended
method.
The performance of the preliminary tests on concrete shall comply with the routine tests described in the
following.
Dagachhu HPP Scctiun 6- Employe's Requirements 6.2 Technical Specifications
Chupter 07 C o n ~ W c& Reinforced Con~mre- 55
7.4.1 General
The Contractor shall ensure that results of quality routine controls comply with the values stipulated in the
respective clauses and that the conditions for independent quality control are satisfied.
The Contractor shall be responsible for the execution and interpretation of the quality control routine tests
specified in this clause and for taking due account of the results of such tests in the execution of the Work.
If not specified othenvise in this clause, the following minimum test program shall be performed:
!
Test i No. of tests i Sampling site
Grading of coarse aggegate
Grading of fine aggregate
. :once a month
I. once a week
-. <....... - i aggregate stockpile
i awegate .stockpile
.-..- . .
Test for organic impurities in i as required i batchiig plant
sand i
Compressive strength 7,28and j once for each 200 m3 of concrete
-
....
j
--.-
mixing plant or at placing site (9
.-
Test specimens
-- .- --- - .....
S~rrfacemoisture of fine I more than 3 times a day i mixing plant
agegate i
.- -
..
.-4
Slump imore than 3 times a day / mixing plant andl or placing site as
-- .. m
.-u.--......-.....-.
i directed by the Employer
Air content in Fresh concrete j more than 3 times a day mixing plant or placing site as
1 directed by the Employer ..
--.-I-----..-- .---- ~.---..-T
7.4.2.1 Cement
For each delivery of cement, it shall be checked that the information of the package or on the delivery note
with regard to the type, strength class and quality control (quality control mark) of the cement conforms to
the particulars in the Specification.
In the case of admixtures, it shall be checked that the package is provided with a valid test mark
In the case of additives, it shall be checked that they fulfill the requirements.
The dosage specified in the Execution drawings shall not deviate by more than 2 % without the Employer's
approval.
7.4.2.2 Aggregates
Aggregate shall be regularly checked visually with regard to its granulometric composition and other
significant properties. In cases of doubt, the aggregate shall be examined more thoroughly.
The batching equipment of the concreting plant shall be accurately set to suit the quantities required for the
concreting operation. Therefore, regular checks shall he undertaken which include the following items:
- Regular control of proponioning
- Check on mixing time
- Check on number of hatches of each kind of concrete made for each concreting section (essential for
determining material consumption, spreading loss, etc.)
- Comparison of produced and placed concrete volume. This control shall he canied out after each
poured section to reveal immediately faults in the batching equipment.
7.4.2.4 Consistency
The consistency of the fresh concrete shall be constantly supervised by visual inspection during concreting.
For each type of concrete, the consistency check measurement shall be performed at the time of first
placing the concrete and every time the specimens for preliminary tests and quality control tests are made.
The consistency check measurements shall be repeated at suitable intervals, as directed by the Employer
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrere - 57
7.4.2.5 Concrete
The concrete surfaces exposed after stripping shall be inspected by the authorized personnel of the
Contractor, together with the Employer. The following Standards shall be valid for the assessment of the
concrete quality:
The appearance of the concrete surfaces must conform to the specified classification of finish
The concrete surface must be uniformly smooth, even and free of ridges and other irregularities.
The concrete must have a pore-free, dense surface on all sides with no evidence of segregation or
inadequate compaction,
No reinforcing bars may lie exposed or signs present. which indicate an inadequate concrete cover of
the reinforcing bars,
No hair cracks shall be visible.
During the inspection, the Employer will determine the type and extent of defects to be eliminated.
The Contractor shall make good any defects to the satisfaction of the Employer at his expenses,
comprising, hut not limited to:
to expose reinforcing bars, which apparently have an inadequate concrete cover, in the area
determined by the Employer and to bend them inward through suitable measures,
to caulk out honeycombs and similar defective spots, which are traceable to segregation of the
concrete,
to pressure-grout damaged areas, cracks, etc.,
to seal all hair cracks of a measured width of more than 0.1 mm, with suitable and recognized epoxy
resin material,
to fill air pores or other defects in the concrete surface with cement slurry of suitable consistency,
- to seal all holes resulting from the removal of formwork bolts and the like,
- to propose and apply any other proven system or measures according to the type and extent of the
defect, in order to achieve a result and an appearance acceptable to the Employer.
Mapping work shall begin at the latest 24 hours after stripping, however it shall in no case be undertaken
prior to carrying out the joint inspection of the concrete by the Contractor and the Employer. Patching and
repair work shall be executed only through qualified personnel using high quality and recognized materials.
e.g., concrete and cement or special mortar. A special bonding agent such as suitable epoxy resin and the
like, of first class quality shall be used where appropriate, to ensure good bonding and adequate denseness
also in the joints.
For each of the routine tests, samples of at least 5.0 kg shall be taken at a suitable location at the concrete
mixing plant during concreting operations for each part of the work and for each type of concrete used in
each such part. The cement sample of the routine test and the test specimens for the concrete quality control
shall originate from the same mixture to ensure a fair comparison of the test results obtained for the cement
as well as the concrete specimens. If pozzolanic cement or other ultra-fine materials are admixed to the
cement on Site, sampling shall take place before such materials are added.
The samples for the site tests as well as the retained samples shall be clearly marked with the number of the
relevant delivery note, and the samples for the standard specification test shall clearly show the test number
of the relevant set of concrete specimens.
For each quantity of 1,000 m3 of poured concrete, a complete standard specification test shall be carried
out. The samples taken for the purpose according to this provision shall, without special request, be
submitted to the material-testing institute together with the relevant concrete test specimens.
A completely filled-in form, in duplicate, shall accompany each sample. The sample containers shall be
clearly marked, and shall also hold corresponding identification slips.
7.4.4 Aggregates
Routine tests shall include
- Grading
- Magnesium Sulphate Soundness
- Specific Gravity and Water Absorption
- Clay, Silt and Dust Content
- Organic Impurities
- Sulphate and Chloride Content
- Aggregate Crushing Value; alternatively 10 % Fines Value or Aggregate Impact Value as decided by
the Employer
- Elongation and Flakiness Determination
- Potential Alkali Reactivity
- Abrasion Resistance
- Aggregate Drying Shrinkage
- Grain shape, flakiness and elongation index
- Inherent strength and moisture
- Settling and elutriatian far ultra-fines
- Durability
These tests may also be carried out in accordance with the appropriate Standards and the result shall
comply with the limits given therein or as otherwise stated in this chapter.
The moisture content and water absorption value of all fine and coarse aggregates shall be tested by the
Contractor twice daily.
The flakiness index and elongation index of the predominant-size fractions in each single-sized coarse
aggregate shall not exceed 20 % and 35 % by weight respectively.
Sieve analyses (tests on grading of aggregates) shall be made when the first delivery is effected and
whenever there is a changeover to a different supplierlor sources.
The grading of aggregates shall he tested by the Contractor on a weekly basis at least or after production of
each I00 m3 whichever is the sooner when concrete is being produced on a regular basis, or before the start
of production when the production of concrete is irregular.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 07 Concrete & Reinforced Concrete - 59
The grading of the combined aggregate is to be regarded as satisfactory if the percentage passing any
individual sieve does not deviate from the specified grading curve by more than 5% of the total weight, or
by not more than 5% of the total absolute volume in case of particle size fractions differing greatly in the
specific gravity of the particles, and its characteristic value for the grading or the water demand is not more
unfavorable than that for the specified grading curve. In the particle size fraction 0-0.25 mm, however, the
permissible deviation shall not exceed 3%.
Size of samples shall be as follows:
7-43 Concrete
7.4.5.1 General
Routine quality control tests shall be used to establish that the concrete made for use on the job attains the
requisite properties as specified. In case of unsatisfactory test results, the Contractor shall
- inform the Employer immediately of this fact
- search for the reasons of test failures
- shall consult the Employer on remedial actions and if agreed upon take forthwith the required action
at his own expense.
Test cubes or cylinders will be made, cured, stored and tested in accordance with respective Standards
under ambient climatic conditions.
In judging the results, it shall be bome in mind that components whose dimensions differ significantly from
those of the test specimens may attain a different degree of hardening from that of the specimens, e.g, in
consequence of differences in heat evolution in the concrete.
8 AUXILIARY WORKS
Chapter 08
WATERPROOFING
TABLE O F CONTENTS
Chapter 08
WATERPROOFING
PAGE
1 GENERAL ....................................................................................................................................... 1
2 MATERIALS ................................................................................................................................ 1
2.1 General ....................................................................................................................................1
2.2 Bituminous Materials .............................................................................................................. I
2.2.1 Undercoating materials I
2.2.2 Top coating materials. to be worked cold ................................................................. 2
2.2.3 Top-coating materials. to be worked hot 2
2.2.4 Bituminous felts. factory-finished ........ 2
2.2.5 Bituminous felt with jute-fabric inlay ..................................................................... 2
2.2.6 Bituminous felt with fiber inlay .............................................................................. 2
2.3 Insulation and Protective Foils ............................................................................................... 2
2.4 Damp Proofing of Structural Joints ........................................................................................ 3
2.5 Adhesive Compounds ........................................................................................................... 4
2.5.1 Mastics. to be worked cold ........................................................................................ 4
2.5.2 Mastics. to be worked hot ........................... . . .......................................................4
2.5.3 Priming materials ...................................................................................................... 4
2.6 Epoxy-Resin Based Material ..................................................................................................4
2.7 Cement Grout with Plastic Additive 4
2.7.1 Bitumen mixture for water-proofing ......................................................................... 4
2.7.2 PVC-Water stops .................... . ............................................................................. 5
2.7.3 Water stops of rubber ............................................................................................... 5
2.7.4 Water swelling rubber sealing materials ...................................................................7
3 EXECUTION OF WORK .............................................................................................................. 7
3.1 General .................
.............................. 7
3.2 Damp Proofing of Walls Against Rising Moisture ..............................................................8
3.3 Damp Proofing Against Lateral Moisture .............................................................................. 8
3.4 Damp Proofing on Floors with Thermoplastic Sheeting ........................................................ 8
3.5 Sealing Joints in the Protective Laye ................................. 8
3.6 Connection of the Damp Proofing to Penetrations ................................................................. 8
3.7 Damp Proofing over Construction Joints ................................................................................ 9
WATERPROOFING AGAINST PRESSURE WATER ........................................................... I0
4.1 Tanking Against Pressure Water .......................................................................................... 10
Dagachhu HPP Section 6 - Employer's Requirements '6.TTechnical Specifications
Chapter 08 Waterpmfing - iii
6.1 Genera
6.2 Requirements for the Works
7 WATERPROOFISG MEMBRAXE AXD PROTECTIVE FELT FOR TUNNELS AND
SHAFTS ...................................................................................................................................... 13
7.1 General ............................. . . ....................................
13
7.1.1 Scope ....................................................................................................................... 13
. .
7.1.2 Submssion .............................................................................................................. 13
7.2 Material and Equipment ................................................... ..I3
7.2.1 Protective felt .......................................................................................................... 13
7.2.3 Accessone
7.3.3 Preparations
7.3.4 Fixing of felt ............................................................................................................
16
7.3.5 Fixing of waterproofing membrane ......................................................................... 16
7.3.6 Protective measures ................................................................................................. 16
7.4 Tests and Properties ..............................................................................................................
17
1 GENERAL
This Specification applies to the following services:
- sealing against rising and lateral moisture
- sealing against percolating water, surface water and leakage
- sealing against pressure water
In addition, this chapter shall be deemed to comprise damp proofing against non-pressure water, damp
proofing against lateral and rising moisture; damp proofing against seepage water, surface water and the
like in the open air and indoors, as well as damp proofing against pressure water by means of bituminous
damp proofing with unbacked felts against water under hydrostatic pressure (e.g.. groundwater, held water,
pressure hill water).
All services also include supply of the materials and building components connected therewith, including
unloading and storage on the building site.
2 MATERIALS
2.1 General
Materials and building components which the Contractor has to supply and build in, i.e., they go into the
structure, must be new and unused. They must comply with standards and dimensions.
For non-standardized materials and building components, the Contractor shall supply samples and name the
manufacturer. Such materials shall be subject to the approval of the Employer.
The Conuactor shall furnish an approved manufacturer's surety bond on all waterproofing material
covering a period of ten (10) years.
All sealing materials shall conform to the latest editions of approved standards, which have to be submitted
to the Employer.
2.2 Bituminous Materials
Bituminous material shall possess the following properties: the residue remaining, when the solvent or the
water of the emulsion has evaporated normally or has been removed in some other way, is regarded as the
solid. Fillers must neither swell nor dissolve in water.
Damp proofing bituminous materials with fillers which must be acid-resistant may contain only filler
materials which dissolve in a 5% hydrochloric acid solution at +20 degrees C (permissible variation
+1 degree C) within 24 hours to a maximum of 10% by weight.
The asphalt shall be mixed with the sand and filler in proportions that will ensure a workable compound. It
is expected that 2530% asphalt by weight and 70.75% sand m d filler are likely to give such a mix. It is,
however, the responsibility of the Contractor to determine the eract proportions.
The sand and powder shall be mixed and heated up to 200 degrees C in a metal container. Simultaneously
the asphalt shall be heated in a separate boiler to the same temperature. The sandlpowder mixture shall then
be gradually added to the asphalt while continuously stirring the contents to ensure a homogeneous mix,
and the complete mixture shall be kept stirred at 200 degrees C for half an hour.
The mixture shall be applied in one layer 10 mm thick. The layer shall be applied in alternate strips about
600 mm wide with chamfered edges with infilling strips overlapping the adjacent ones by 50 mm. In
applying a layer, care must b e taken that no entrapped air is kept beween the masic and the ranel=
surface.
do-nLIUOc I aturn
Icivil YOTWO( il--run 6-i6 l=hnral ~ ~ ~ 6 ~ s ~ ~ n ' k h austrmmfinl.*mrJul4M
PerOR
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specitications
Chapter 08 Waterproofing - 6
3 EXECUTION OF WORK
3.1 General
The Contractor shall check the structural conditions for suitability of application of the damp proofing. He
shall inform the Employer in writing without delay of any objections to the intended method of application,
if it does not suit the structural conditions. Subject to this provision, objections shall have validity.
particularly in regard to:
- too rough, too porous, too smooth surfaces
- sharp edges of boarding and ridges
- deviations from the horizontal or the fall stipulated in the specification or required by the
circumstances
- non-rounded comers, edges and channeling
- stress and settlement cracks, holes
- too moist surfaces
- non-sealing of voids (e.g., in lightweight concrete)
oily surfaces, paint residue
- unsuitable type or position of penetrating structural members
- lack of provisions for connections to structural members which penetrate the damp proofing
- inadequate precautions against slipping of the structure on the damp proofmg and against slipping of
the protective layers on the damp proofing
- surface too strongly absorbent
Damp proofing works may only be carried out under favorable weather conditions not causing any
detrimental effects on the works. In case of adverse weather conditions, damp proofing works will only he
allowed to be carried out if special precautions have been taken preventing any damaging affects to the
works.
Such weather conditions could be temperatures below +5 degrees C, raining, snowing, sharp winds or
others.
During execution of such works, the Contractor shall pay attention to any conditions, which may arise
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 08 Waterproofing - 8
Upon completion of any layer of damp proofing felt, the Contractor shall carefully inspect it for possible
defects. If any damages or defects have been identified. they shall immediately be remedied. If any finished
layer of damp proofing felt has not immediately been covered by a protective layer (gravel, tiles, cement
screed or similar), the Contractor shall repeat his investigation for eventual repair before carrying out the
following layer.
The Employer shall be informed in due time prior to the investigation, giving him a possibility to take part
when examining the damp proofing layer before being covered up.
The Contractor shall protect the damp proofing felt against harmful sunrays, overheating or other damages
until placing the protective layer.
Horizontal and slightly inclined layers of damp-proofing felts (with the exception of damp proofing in
walls) must receive a protective covering immediately upon completion.
Steeply inclined and vertical layers of damp proofing felts must also be covered with a permanent
protective lining immediately after being completed in order to reduce the risk of being damaged.
Bolts of flanged pipes penetrating the damp-proof layers must be retightened before being covered up.
3.2 Damp Proofing of Walls Against Rising Moisture
Damp proofing of masonry walls against rising moisture shall be carried out with two layers of 500 g/m2
hituminized roofing felt. The felt layers shall neither be bonded to the bed nor to one another. Each layer
shall overlap by not less than 10cm.
33 Damp Proofing Against Lateral Moisture
Damp proofing of walls against lateral moisture shall be carried out with only one (I) prime coat and three
(3) top coats.
The first coat shall be a prime coat to be worked cold. The following top coatings shall only be applied
after the prime coat and each following coat has thoroughly dried.
The three (3) following coats shall be of bituminous solutions without fillers and shall be of the type to be
worked cold. The instructions of the manufacturers shall strictly be observed and the Contractor shall fully
guarantee the dampproofness of the coating.
3.4 Damp Proofing on Floors with Thennoplastic Sheeting
Damp proofing with thermoplastic sheeting shall be carried out with one layer of plastics sheeting. On
slightly inclined surfaces, the lengths shall be fixed with adhesives. The courses shall be laid with the joints
staggered. They shall overlap at least 5 cm.
The lengths shall be joined by solution welding. With solution welding, the over-lapping shall neither be
water-moist nor soiled with bitumen, adhesives, or other substances; if necessary it shall be shielded from
contamination with strips of paper. The edges of lengths which are uppermost at the overlap shall not to be
tapered or smoothed off. Unbacked 500 gIm2 bituminized felt shall be bonded to the sheet as a protective
layer. The hituminized felt shall be bonded to its bed over the entire surface by means of an adhesive
coating applied to its underside and to the bed. The upper face of the bituminized felt shall he given a top-
coating with the same adhesive. Not less than 1.0 kg of adhesive shall he applied per square meter for
bonding coats, not less than 1.5 kg per square meter for top coats.
3.5 Sealing Joints in the Protective Layers
Joints in the protective layers applied onto dampproofings of floors and slabs shall be raked out without
damaging the damp proofing and completely be filled with hot-flow bitumen sealing compound.
3.6 Connection of the Damp Proofing to Penetrations
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 08 Waterpmofing - 9
The connecting elements (fixed flanges and loose flanges) shall be cleaned to remove st and dirt. The
points which are in contact with the damp proofing shall have a prime coat applied to them immediately
after cleaning.
Bonding shall not be carried out on top of fixed flanges. Loose flanges shall not be tightened until the
undercoat has dried thoroughly and contains no more solvent. The undercoat on fixed flanges shall be free
from moisture before bonding on top of it; if necessary. special steps shall be taken to dry the surface
shortly before coating.
In the region of fixed flanges, the damp proofing shall be reinforced by applying an additional layer of
unbacked felt extending at least 30 cm beyond the flange in all directions. In the region of the fixed flanges,
the individual layers shall meet the butt joints; the joints in the individual layers shall be staggered relative
to each other.
The damp proofing felt shall be clamped between the fixed flanges and the loose flanges,
3.7 Damp Proofing over Construction Joints
Damp proofing over structural joints shall be reinforced unless stated to the conuaq in the Specifications.
Damp proofing over suuctural joints intended to allow only for the contraction and creep or only the
expansion of suuctural members shall be reinforced by putting in cup-fluted copper strip 0.2 mm thick. The
copper strip shall be bonded.
Damp praati~g overstructural joints intendedonly to allow for differentid vertical m o af d j a h~k ~ g ~
suuctural members up to a settlement differential of 1 cm shall be carried out as above. If settlcment
differentials of more than 1 cm are to be allowed for, the damp proofing shall be carried out in such a
manner that the more stringent conditions involved are satisfied. Prior to execution of damp proofing
consuuction joints, the Contractor shall inform the Employer of the designed method to be applied for
approval.
Damp proofing over structural joints designed to allow for movements resulting from temperature changes,
vibration, torsion, etc., shall be carried out in such a way that both type and extent of the expected
movements will be satisfied without damaging effects on the damp proofing. The methods of satisfying
such conditions shall be approved by the Employer prior to execution.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 08 Waterproofing - 10
For water tanks for potable water, any sealing compound andlor coatings shall comply to drinking water
quality requirements, i.e., they shall not affect taste, odor, and color nor shall they be detrimental to health
requirements.
6 AUXILIARY WORKS
6.1 General
All kinds of works, materials, services, equipment. safety measures, etc., as well as tests and samples if
requested by the Employer or which may or may not be specifically mentioned in the Contract Documents
and which may or may not be shown in the Drawings shall be included in the lump sum or respective unit
prices.
6.2 Requirements for the Works
The unit prices shall include among others:
- cleaning of base and surfaces
- provision of all scaffoldings
-
protection of executed works against damages and detrimental influences from environmental
conditions such as adverse mechanical attacks
-
averaging out, making up for minor lack of gradient or incorrect level of the base
- transportation of all materials and equipment to the place of installation
- provision of all equipment, devices, tools required for the preparation and performance of water
proofing works
- preparation of the base if surface is too rough for taking water-proof coating or membrane
- all extra works at comers, abutments. joints required for water-proofing the surfaces
-
diversion and draining of adverse water excess if conditions require.
Dagachhu HPP Scclion 6 - Employer's Rcquircmcnb 6.2 Technical Sprcificalionr
Chaprer 08 Wsrcrpmoling - 13
7.1.7. Submission
Tbe following submissions shall be h h e d for approval in accordance with the conhact requirements:
Certificates of compliance attesting that the materials meet specification requirements.
Manufactum's instructions for installation of felt backing and waterpmofing membrane, including
procedures for preparation, fixing, welding and splicing, flashing etc.
Manufacturer's and installer's qualifications to include evidence of experience of the manufacturer and the
installers, as well as resume of lining installation supervisors.
Samples as listed hereunder:
Membrane: One square meter of each typc membrane.
Protective felt: One square meter of each type of felt.
Welded splice: 1 m of welded membrane splice for each trpe of membrane
Fixings and fittings: 10 samples from different lots of rondels and nails,
2 samples of sealing flanges for projections passing through the memhrane
Shop drawings shall be submitted for approval showing all necessary installation details for felt and
waterproofing mnnbrane, including installation sequence, position of joints, treament of projections,
connection to water stops, connection to waterproofing of structures in open cut, local reinforcements etc.
Dagachhu HPP Section 6 -Employer's Rqukements 6.2 Technical Specifications
Chapter 08 Waterproofing - 14
I I alkaline solutions
at failure.
longitudinal and
transverse
no fissures
temperature of -20
degrees C
14 Behavior of the seam weld no leakage at 0.05
MPa
I I
I
1
15 Shear strength of splice with bitumen I N150 mm 2 I00
Source: Specification DS 853,020890.of ihc German Federal Railway DB
7.23 Accessories
Fixing material, flashing, reinforcement for expansion joints, sealing flanges and preparation of corners and
intersections shall be made as recommended by the manufacturer of the membrane.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 08 Warerprooting - 16
7.3.2 Application
Prior to the application of the waterproofing, all surfaces to which it shall be applied shall be inspected and
approved by the Employer.
The application shall follow the written instructions of the manufacturer. Generally procedures are the
following:
73.3 Preparations
Special preparations will he required for waterproofing at tunnel intersections and for projections passing
through the membrane. They shall be carried out according to the manufacturer's recommendation.
7.5.1 General
All kinds of works, materials, services, equipment, safety measures, etc., as well as tests and samples if
requested by the Employer o r which may or may not be specifically menrioned in the specifications and
which may or may not he shown in the tender drawings shall be included in Works or in the relevant unit
rates of the Bill of Quantities.
Chapter 09
STEEL LINING
TABLE O F CONTENTS
CHAPTER 09
S T E E L LINING
PAGE
Iiiip.da~?~CU%
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specitications
Chapter 09 Steel Lining - iii -
. .
1.6.3 Palnting systems .............................................................................................. I1
1.6.4 Surface preparation .........................................................................13
1.6.5
. .
Execution of palnting .......................... .
...
.................................................. 13
1.6.6 Quality control .............................................................................................. 14
1.7 Measurement and Payment ........................................................................ 15
I STEELLINERS
1.1 General
In the following Chapter the principle features of the steel lining are specified. All paas associated with the
pipeline, which are not specifically described, but essential for the complete plant, installation, operation
and maintenance including all lubrications, mounting and dismantling devices and spare parts shall be
deemed to be included in the relevant unit rates.
The Civil Works Cotltractor shall coardinate his design and all interrelated matters with the mechanical
and elecmcal equipment.
'
Water Level at Desilter: 841.OO m above sea level
Max.Operation Water Level (max. upsurge in the surge rank): 849.80 m asl.
Water Hammer. 15% of maximal Head
Turbine nmner centre line: 537.00 m as].
Inner diameter: 2200 - 4500 mm
Corrosion provision: 1 mm shall be added to the thickness of steel liming according to statics calculations.
1.13 Documentation
Documentation required and to be submitted to the Employer for approval relating to steel lining and
auxiliary works includes:
All statics calculations and verifications of operational strength;
A11 installation I fabrication, detailed and factory drawings, lists
Dagachhu HPP Section 6-Employds Requirements 6.2 Technical Specifications
Chaptcr 09 Steel Lining - 2 -
The documents are to be delivered to the Employer in the desired quantity, form and format
All necessaq calculations relating to steel lining should be canied out by the Contractor before fabrication
to ensure smooth progress. All calculations and dimensioning shall be checked by the Employer.
Calculations shall be delivered to the Employer so that checking of calculations by the Employer will not
impose on deadlmes for fabrication. All calculations shall be according to approved standards and delivered
to Employer in paper and elecfzonic formats.
Methods for calculations and assumptions shall be agreed with the Employer.
Calculations by the Contractor for the design of any structure shall be prefaced by a statement explaining
the principles of design and the type of analysis adopted. The statement shall also indicate the codes of
practice and specifications upon which the design is based.
The smctural calculations to be submitted shall contain at least the following details:
- Loads and horizontal thrust on which the calculation is based
- Dead weight
- Type of material of the main smcttual parts and means of jointing
- Measurements and cross-sections of all essential structural elements
- Maximum stresses as well as maximum pressures on supports and moments of all individual
structural elements and of their joints
- Evidence of stability
- Deflection of the main supporting structures.
Seismic loadings shall be assumed to result from a basic ground acceleration of not less than 0.06 g.
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter 09 Steel Lining - 3 -
12.1 General
All materials shall be new, of high quality, free of defects or imperfections and shall comply with the
specified grades and standards. The minimum steel class to be used for all steel shall be P355N according
to EN 10028-3 (Euro-Norm, European Standard) or equivalent as approved by the Employer.
The maximum allowable stress in steel components shall be 213 NIIMI*(0.6 *yield strength).
1.22 Plates
Steel plates for use as steel lining in the areas specified in the scope of work shall conform to the following
standards:
- EN 10025: Hot rolled products of non-alloy structural steels; technical delivery conditions;
- EN 10029: Hot rolled steel plates, 3 mm thick or above, tolerances on dimensions, shape and mass;
- EN 10207: Steels for simple pressure vessels; technical delivery requirements for plates, strips and
bars.
1.23 Stiffener Rings, Seepage Collars. Stiffeners, Thrust Collars and Structural Accessories
All stiffener rings, seepage collars, stiffeners, thrust collars, and suuctural accessories permanently welded
to the steel linings shall match the steel grade of the steel plates that they are welded to.
All temporary accessories such as internal bracing, tiedown rods, erection suppotts, etc. shall conform to
ASTM-A36, "Specification for Smctural Steel.", or equivalent standards.
All cover plates for grout holes shall be made of stainless steel conforming to EN 10088-2: Stainless steels
- Part 2: Technical delivery conditions for sheet plate and strip for general purposes, or equivalent
standards.
1.2.5 Source
All steel plates shall be furnished from one mill
Dagachhu HPP Section 6 Employer's Requirements 6.2 Technical Specifications
Chapter 09 Steel Lining - 4 -
13 Execution of Work
1.3.1 Fabrication
1.3.1.1 General
Fabrication, assembly, and erection shall be in accordance with these specifications and the applicable
requirements of:
EN 13445-1:2002+A3:2007: 'Unfired pressure vessels. General', or equivalent standards
EN 1344511:2W2+A2:2006: 'Unfired pressure vessels. Fabrication' or equivalent standards
ICE Recommendations, valid at the time of execution of the works
Before completion of fabrication andlor installation, tests to he carried out as well as samples shall be
agreed upon by the Contractor and Employer.
Upon completion of fabrication, the work is to be documented, with documents detailing all adopted
manuals, inspection certificates, lining segment identification etc.
The Contractor shall be liable for all damages, caused by breach of approved standards and ICE
recommendations at his fault.
1.3.13 Welding
13.13.1 General
All welding shall meet the specifications of I S 0 15607:2003: 'Specification and qualification of welding
procedures for metallic materials - General rules', and of EN101 1-2 or equivalent standards. The welding
processes are restricted to the shielded metal arc (SMAW) and submerged arc (SAW) processes. All welds
shall be continuous welds.
Before commencement of fabrication, the procedure shall be tested, (i.e. welding of samples including
choice of electrodes, welding powder and welding method) and approved by the Employer.
All procedure qualification tests must be performed on plate samples of steel to be actually used under
these specifications. Welding procedure qualification records (PQR) shall be maintained.
Assessment of quality levels for imperfections shall be as according to EN IS0 5817:2007: 'Welding.
Fusion-welded joints in steel, nickel, titanium and their alloys (beam welding excluded). Quality levels for
imperfections'.
The welders and welding operators shall initial the steel lining in colour by each hand-welded seam they
carry out.
The wansition between plate and weld shall he smooth and without notches and therefore easily testable
Depending on lining thickness and material quality, welding should be carried out pre-heated as approved
by the Employer.
13.1.5 Tolerances
If large faults in the steel plates are discovered during fabrication (e.g., doubling up, large variability in the
thickness), the respective steel plates are to be cut out and be replaced by non-faulty plates.
The following tolerances shall be kept for the fabrication:
a) The cylindrical and conical sections shall be sufficiently true to round so that the difference
between maximum and minimum diameters, with temporary bracing in place and measured inside
and outside, at any cross section along the length, shall not exceed 0.25% of the theoretical
diameter for the section.
b) After m n g e m e n t pre-welding, the edges of circular weld seams shall at no point be offset greater
than 1 mm (or 5 % of the wall thickness if wall thickness is greater than 20 mm).
c) Any point on the ends of a cylindrical section shall be within a tolerance of 5 3 mm with respect to
a plane normal to the longitudinal axis of a section.
+
d) The flattening of the longitudinal seam shall not exceed 2 mm. A gauge of 500 mm chord length
shall be used for measurement.
e) The innerdiameters or the lining cross sections (measured in various directions) shall not exceed
0.5% of the theoretical inner-diameters.
f) The maximal deviation of the roundness, measured with a .,SO0 Montel- Template" shall be 5 mm.
This deviation of roundness shall be considered in the structural analysis for external pressure
(placement of concrete, water in mountain).
g) The misalignment of the longitudinal welded seam shall not exceed 1.0 mm. For measurement, a
gauge of 300 mm chord length shall be used.
h) Angles of bends shall he within a tolerance of plus or minus 5 minutes of angle.
The tolerances listed are exclusive of any allowance provided for shrinkage or distonion to compensate for
effects of welding.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 09 Steel Lining - 6 -
1.3.3 Delivery
Each lining segment to be delivered should be numbered according to the installation plan, with flow
direction and material quality also given. These should be engraved onto the pieces and painted on in
colour. In addition, the association of each lining piece to its respective lining and installation position, the
material quality and thickness should be detailed in a list. The Employer shall be allowed to request the
sanding off of the engravings.
Pans shall not be painted before delivery. The worked surfaces should however have a coating to protect
against rust which can be washed off.
Steel lining segments should be lifted by a mobile crane
The cost and risk of the haulage of the parts to be delivered shall be borne by the ConWactor. The
Contractor is also responsible for the realization and supervision of the transport, as well as the transport of
assembly plant to and from the assembly site.
Transportation insurance shall be borne by the Contractor and shall be included in the item rates.
13.4 Installation
All sections or can assemblies of the penstocks, steel liners and bifurcations shall be individually assembled
and held together by temporary fastenings and bracing. Tack welds shall be subject to the same quality
requirements as the final welds. When assembled and ready for welding, the adjoining can assemblies or
sections shall be rigidly held with end spacing as required for hill penetration welds. Dimensions and
tolerances will be checked prior to final welding.
1.4.1 General
All material and welding tests, measurements, dimension control, etc., including the supply of all necessary
equipment shall be carried out by the Contractor on his own costs, responsibilities and risk.
The Employer shall entrust on his own costs an independent authorized Inspecting Authority for the
supervision of steel plate approval, welded joints testing, the competent execution of the fabrication and
installation as well as dimensional control.
By these means. the Employer and Contractor shall reach agreement for the extent of the quality control.
Individual inspections shall be carried out by the Inspecting Authority, should the personal not he present.
Materials, pans, and assemblies thereof entering into the work shall be tested according to the best
generally accepted method for this type of work. Where it is desired to use stock material not manufactured
specifically for the equipment furnished, evidence that such material conforms to the requirements stated
herein shall be obtained, in which case tests on these materials may be waived. Certified mill test reports
may be acceptable.
All testing must be carried out by testing personnel, who are qualified in accordance with EN 473 (or
equivalent). Examination certificates for the respective testing must be able to be provided to the
Employer, Inspecting Authority or on the construction site at any time.
The Employer andor their Inspecting Authority shall at any time have the right (after giving due notice) to
be present during fabrication and testing. Using all samples and controls, protocols shall be drawn up,
which are to be signed off by the Employer andlor their Inspecting Authority.
The Employer andor their Inspecting Authority shall be entitled to request extra tests to be carried out at
the expense of the Contractor.
In connection to each quality inspection that the Contractor undertakes in his factory, workshops of his
suppliers, or on the construction site, inspection protocols andor certificates shall be provided to the
Employer in the format and quantity the Employer wishes.
An inspection sheet concerning installation shall be provided for each lining segment, with the form and
contents of the sheet agreed upon with the Inspecting Authority.
The following services can be requested as part of inspections:
a) The lining segment number (as shown on the installation plans);
b) The measured circumference of both ends of the segment, measured length of the segment and
results of the tolerance inspection;
c) The quantity of plates used, the associated fusion and material quality;
d) Examination and finalization of welding procedure
e) Inspection of welding material and electrodes to be used
f ) Check or qualifying tests and approval of welders;
g) Supervision and examination of welds;
h) The results of ultrasonic and fissure testing;
i) The measured wall thickness;
j) Measurement of corrosion coat thickness;
k) Attendance at hydraulic tests;
I) Check of special tests in the event those performed by the supplier are judged to be unsuitable
If testing of a delivered item shows that it is defective or contrary to contract specifications, the Contractor
shall rectify any defects without delay and redress the contractual condition of the delivered item. Testing
_/
for the participation of
Inspecting Authority shall be borne by the Contractor.
Dagachhu HPP Senion 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 09 Steel Lining - 9 -
Invitation for inspections shall be made with sufficient time for the Employer to have the opportunity to
plan the inspections and so that no delay to the schedule arises. This also applies to the sample of test and
procedural certification and all decisions, which require the agreement of the Employer.
For inspections outside of Europe, the costs of travel and the resulting travelling time of the Employer
personnel and the personnel employed by the Employer for inspections are to be borne by the Contractor.
1.5.1 General
Unless otherwise specified, all and any kind of works. materials, equipment, services, safety measures, etc.,
as well as and if so requested by the Employer, all tests and samples required for the completion of the
work shall be included in the unit prices.
CHLORIMTSD RUBBER
HViVIBWICHLOXNlizD~UBBER
W B D D I C P A C I EPOXY
C I COALTAR EPOXY
STRUCTURES. STEEL
SrnUCWRESPFN.
BASINS. $ E E L
The Contractor shall consider that damage to paint work during storage and erection is practically
unavoidable and the application of all protective treatment should be programmed accordingly. Care must
be taken to remove salt crystals deposited during sea transport andlor storage at a seapon, by thorough
washing with clean fresh water. It is essential that before any coat of paint is applied, the surface shall be
prepared as described above so that it is clean and free from all deleterious matter and completely dry.
Temporary or permanent welding shall not be permitted on areas where the welding will damage paint or
other protective coatings, unless the areas of coatings, which would be damaged thereby, are accessible for
repairing and inspection. Material which has been painted shall be handled with care and protected as
necessary to preserve the coating in good condition.
' Chapter 10
DRILLING & GROUTING
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Chapter LO Drilling & Grouting ii .
TABLE O F CONTENTS
Lot 1 Civil Works. Volume I1
Section 6.2 Technical Specifications
Chapter 10
DRILLING & GROUTING
PAGE
1 GENERAL......................................................................................................... 5
1.1 Scope of Work ....................................................................................................................... 5
1.2 Installation of Equipment....................................................................................................... 5
1.3 Sampling ............................................................................................................................. 6
1.4 Water Pressure Tests .............................................................................................................. 6
1.5 Equipment .............................................................................................................................. 6
1.6 Material ................................................................................................................................ 6
1.7 Standards................................................................................................................................ 6
1.8 Plans and Program of Works.................................................................................................. 6
2 MATERIALS AND EQUIPMENT ......................................................................... . .7
"
1 GENERAL
1.3 Sampling
The possibility of continuous sampling shall be provided in rock, concrete and soil, both for disturbed as
wcll as undisturbed soil samples. Samples and drill cores shall be kept in core boxes with proper labelling.
Undisturbed soil samples shall be sealed and carefully handled according to normal techniques and sent to
material testing laboratories if so directed by the Employer.
1.5 Equipment
It is understood that all equipment, temporary plant, tools, machinery, installations, materials, auxiliary
services, tests, etc. are to be provided by the Contractor as required for an adequate performance of the
works as well as in such number as to perform the works within given time limits, taking also into
consideration that simultaneously heavy construction work is talang place at the same site.
1.6 Material
The actual amount of drilling and grouting material will depend on the nature of the rock as disclosed, the
excavation, on the results of water pressure tests and on the results of the actual grouting operations.
The Contractor shall not be entitled to any increase in the unit rates tendered in the Bill of Quantities due to
change or omission of the quantities or by reason of the location of the required drilling and grouting.
1.7 Standards
For all works to be performed and for all data obtained, the metric system (SI-system) shall be applied. If
not otherwise mentioned. the works shall be performed in conformity with these Specifications. For the
performance of tests relevant international standards shall be followed.
Records of work shall be kept throughout all drilling and grouting activities using forms and standard
formats.
2.1.1 General
Rotary, core and percussion drills may be required, and only electric, or air-driven tools will be accepted
for works to be executed underground. Equipment with diesel or other drives shall be used only for open-
air operation. This refers also to all drives for auxiliary equipment and temporary plant necessary for the
particular works. The rates shall also include the provision of measuring equipment such as photo or
electrical borehole sounds in order to check the actual inclination of boreholes.
The Contractor shall record all his activities in accordance with accepted standards in an approved form. In
case of core drillings with core recovery, the Contractor shall treat, handle and store cores and samples
according to the accepted standards or as directed. Copies of all records shall be promptly given to the
Employer. Casing for drill holes may be plastic or mild steel, solid or perforated.
22 Grouting Equipment
2.2.1 General
The grouting equipment to be used shall be of a type, capacity and mechanical condition to suit the Work to
be carried out, and shall consist of, but not be limited to, mixer, material storage tanks, pressure gauge,
pressure nozzles, tools, pumps, pipes, valves, and all accessories necessary to maintain a continuous supply
of grout and control of pressure. Automatic writing recorders for pressure and amount of grout are required
for all the grouting works. An accurate master pressure gauge to check periodically accuracy of all pressure
gauges installed in the grouting system shall also be furnished.
The equipment for mixing and placing grout shall be capable of effective mixing with high speed and
stining the grout and forcing it into the holes o r grout connections in a continuous, unintempted flow at
any specified pressure.
The internal diameter of the pipes and the grout mixture shall prevent harmful solid sedimentation at times
of pumping with low capacity.
The grouting equipment shall be maintained in a proper manner and shall be capable of continuous and
efficient performance during any grouting operation. Provision shall be made to permit accurate control of
grouting pressures and grout flows into the grout holes.
The mixing and pumping equipment shall be housed in one or two central stations as to enable continuous,
undisturbed work, independent on outside weather conditions and as to guarantee constant mix
composition.
Stand-by equipment for immediate continuation of work in case of disturbances shall be provided. The
distance between the grouting place and the pumps shall allow for continuous work without running the
risk of clogged pipes.
The arrangements shall be such as to ensure the continuous and unintermpted flow of grout to the hole
being injected. The grouting shall be carried out by a return flow system to guarantee continuous
, . circulation of grout to the hole being injected and return surplus grout which is not accepted by the hole to
the holding tank.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 10 Drilling & Gmuting - 9
Drilling equipment including all auxiliaries, instruments, temporary plant and installations shall be of
modem, appropriate design as to meet specified requirements, and shall be in perfect working conditions
when brought to the site. Sufficient auxiliaries, spares, tools, drilling bits, etc. shall be provided andlor kept
in stock at the site to warrant unintempted operation.
222 Pumps
All grout shall be pumped with electriclhydraulic pumps allowing independent regulation of pressure and
discharge arranged with interconnecting pipes and valves in such a way as to permit a stand-by pump to be
brought into immediate service.
The pumping equipment shall be capable of transporting grout into holes or grout connections in a
continuous, unintempted flow at any specified pressure up to a maximum of 4.0 MPa (40 kg/cm2), only
minimum fluctuations in pressure during pump cycle being permissible. The maximum internal diameter of
lines shall be 25 mm.
Also, low pressures will be required in the vicinity of linings and close to rock surfaces.
The grouting equipment shall be arranged as to provide a supply line and a return line from the grout pump
to the grout hole. They shall enable the discharge of 2 litres per minute up to 150 Umin, depending on the
system to be grouted and on the purpose. High rates are required for water pressure tests mainly.
Special emphasis shall be given to the control devices for pressure and volume of grout and for water tests.
For all curtain grouting works, self-recording devices are required for both pressure and discharge. For
contact grouting between steel or concrete linings and rock, for consolidation of rock around tunnels or in
the vicinity of structures, and for grouting to support excavation works, self-recording pressure meter and
hand-written accounts of the grout rate shall be satisfactory.
Grouting of anchors may be performed without recorded control except for indications of pressure and
grout rate in the reports.
The pressures applied shall be taken at the borehole head and be transmitted to such automatic recording
instruments.
Synchronized operation of pressure and discharge recorders must be ensured. For regular checking of
pressure at the pumps, these shall be fitted with additional pressure gauges having an accuracy of 0.1 MPa
( I bar).
All pressure gauges used shall permit safe reading of 0.1 MPa (1 bar), that means gauge scaling and the end
reading shall be adjusted to the applied pressure. Pressure and discharge recorders shall be checked against
calibrated gauges at appropriate intervals.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 10 Drilling & Grouting - 10
2.2.3 Mixers
The equipment for mixing the grout materials shall be capable of effective mixing and stimng with high
speed (colloidal type).
The mixers shall be provided with an accurate meter for controlling in lives the amount of mixing water
and other liquids such as bentonite slurry which are used as a mix component at an accuracy adequate to
the volume of the containers.
The minimum revolution speed of the mixer shall be 1200 rpm. In addition to the grout mixer, hold-over
agitator tanks with stirring propellers shall be provided.
Two compartment, high speed, colloidal mixers are to be used. The grout shall be mixed in one
compartment and be discharged into a separate tank. A screen shall be inserted between the holding tank
and the suction of the grout pump. The grout in the holding tank shall be continuously agitated. A water
meter shall be provided for the accurate measurement of the water to be used for mixing. The holding tank
shall be provided with a volume measure indicator to achieve a record of grout take to be made.
2.2.4 Packers
All packers used shall guarantee proper sealing of the respective borehole section and shall then be capable
of withstanding water pressure exceeding the maximum grout or water pressure to be used at the level
without leakage. This may require the use of different types and sizes of packers, such as double-tube
packers, hydraulic packers. pneumatic packers or self-sealing packers, each in accordance with the rock
conditions. The Contractor shall have all types of packers required available on site for immediate use.
2.3.1 General
Grout shall be composed of water and cement plus sand and additives, depending on previous and further
investigations and site conditions. All materials shall be of approved quality. The grout mixes shall be
varied to meet the requirements. In general, a cement grout shall be used. Where necessary, sand shall be
mixed so proportioned as to be readily pumpable. If reasonable, bentonite, rock flour or other fillers shall
be added, also chemicals and additives in case of aggressive groundwater or particular underground
conditions.
Material consumption records including water shall be submitted to the Employer in writing and in due
time together with necessary information and test results. All tests required for approval or for periodical
contml shall be performed by the Contractor without additional payment.
Dagachhu HPP Section 6 - Employer's Requirements 6.2 Technical Specifications
Chapter 10 Drilling & Grouting l l
232 Cement
Where chemically aggressive groundwater occurs, a special cement or Portland cement with admixture of
additives shall be used. All such contingencies shall be considered and agreed upon beforehand with regard
to the type of cement to be supplied by the Contractor. Compatibility of the binder with the intended
additive and the percentage of the same to be added shall be tested by the Contractor in the presence of the
Employer prior to use.
23.5 Sand
Aggregates shall meet the following specifications:
- The sand shall not contain more than an approved percentage of flat or elongated grains having a
maximum dimension in excess of five times the minimum dimension.
- This maximum percentage shall be such as to preclude the possibility of supply pipes being clogged
when pumping grout at the lowest waterlcement ratio at the lowest anticipated pressure and at the
lowest velocity.
- The sand shall be well graded from fine to coarse and a p d a t i o n as determined in accordance with
the relevant standards and shall conform to the requirements.
Gradation shall be approximately as follows (expressed as passing through sieves of the U.S. standard
series)
23.6 Bentonite
Bentonite shall be of the sodium montmorillonite type and may be added to the grout. Bentonite addition to
the grout may vary from 2% to 4% of the weight of cement, applicable for Liquid Limits (LL) of 550 and
350%, respectively.
23.7 Additives
All additives used such as accelerator or retarders or bentonite or chemicals, shall be free of chloride. Tbey
shall not promote steel corrosion or adversely affect the strength development and hardening pattern of the
grout, other than has to be normally expected. The Contractor shall be fully responsible for the suitability of
[he additives. He shall safeguard himself by manufacturer's guarantees. It is noted that special tests shall be
performed to check the compatibility of any additive with any cement in use. The quantity used shall be
kept to the absolute minimum necessary to attain the desired results. The additive shall be fed to the mixer
directly and in the exact proportion.
Prior to commencement of work, the Contractor shall provide the Employer with test results of how the
additive influences the strength development up to the point where the final strength is reached.
2.3.8 Water
The water used in the grout shall be fresh, clean, and free of sewage, oil, acid, alkali, salts, organic or other
undesirable matters. In cases of doubt; necessary tests have to be performed by the Contractor without
additional payment.
3 EXECUTION OF WORK
'S9lI)IJRIIS
alarauo3 largo pue saual@% [onuoa 'sde3 inoi% jo alarziuo3 paaioju!ar q8nolql saloq S u y ~ q -
:Llanoax a103 lnoql!m s%qw
's%u!llq a03'uaamoza!d ad!d-puea aloqxoq i o j s a p q iaame!p [erg mm ooz - 001 % U ! I I ~ -
:Lrano~xaroa inoql!m 4u!1[g ,s%mllup
aroa 'sisal aloqaioq 'gamd!nba %uuo~!uom's~uamnnsyB ~ a m o IOJ [ oJaaure!p aTqeFn jo Bu!l[g -
:iaKoldm~aw Lq pnaar!p se xaqmasla pue 'surane3 's~uaruu%!plauum pue
sainl3nns jo uoneao[ a m naM aql u! (arqeuen lalaurerp) spas pue qaor u! s%u!~ppaios Lro~eroldxa -
:suoneaol I U ~ ~ u!
J Jsuo~leiado
~ , Bu![[q Xu!mol[oj aql uuopad lleqs rolaenuo3 aql 'slaqlo %uomv
8 u ~ ~ aolnama~mbag
j CE
uonanpar l o uo!suaxa j! 'saaud ]Fun u! a%ueqa ou) syiom jo ssar%oldaql Ruunp suonrpuoa r e [ n a v d aql
01 pa~dcpeaq [pm yrom jo lunoure aqL . s a u a ~ p %
l o sxmaruls punofirapun WOIJ l o slauum moij se [lam se
syrom iaqlo ql!m palnaaxa kpuamauoa aq uea Law leql rauuem e qms u! pauueld aq [pqs syiom % q n o l g
.aauenpe u! pall!u~qnsaq [@qssucer%o~d %qyromK l y a a ~.lo1aenuo3 aql
Kq w d x d aq [pqs uo!lerado aql JO s[!elap %mlea!pu! alnpaq3s ssai2oid e 'su!%aq yiom B q n w %x o j a a
. a a ' k p sad sinoq
Brqlom 'paean aq 01 saloqjo lapro 'a[oq moi%JO qldap 'sax?n 'sxnssa~dinor%01 iajar hem suogeag!poK
'a[qeuosex
I! ayem s%uipugaql pue yrom l o ssar%oidaql j! suo!~eag!pou 01 ~aarqnsaq Ileqs s m % o i dq3nS .suo!lrpuoa
al!s pue [ea!Soloa% aql pue yiom aql jo aso&nd n l n a w d aql 01 spre%arql!m syiom aql jo >uamaauaunuoa
01 loud io13muo3 aql Kq paleioqela s m e ~ % o ~ 01d 8u!pio3ae pauuopad aq [pqs y o m %u!~noiS[[v
Dagachhu HPP Section 6 - Employef s Requirements 6.2 Technical Specifications
Chapter 10 Drilling & Gmuting - 14
3.4.4 Casings
It may be necessary to install casing in portions of holes drilled for grouting. Except in those portions of
holes which are not to be grouted, casing shall be provided. Wherever possible, any casing that is installed
for the purpose of keeping the grout hole open for grouting shall be removed immediately prior to or
simultaneously with the grouting process.
3.4.5 Additives
All holes shall be drilled without mud-support and without the use of grease, 'rod-dope'or other non-water
soluble material or the lubrication of the drill rods. The Employer may permit the use of an additive in the
drilling water. A sample of the additive shall be submitted to the Employer prior to its being used. The
concentration of the approved additive shall not exceed the manufacturer's recommendation.
3.5.1 General
Grout holes without core recovery shall be drilled wet with percussion type drills except where these are
found to be unacceptable for grouting. Rotary type diamond drills shall only he used where necessary. The
use of "rod-dope", grease or other lubricants on the drill rods or in grout holes will not be permitted. The
minimum diameter of grout holes shall be 50 mm. The depth may reach 40 m.
In rock surrounding tunnels, it is anticipated that the depth of drilling will in general not exceed approx.10
m into rock. In caverns, the depth may go beyond the 10 m. The diameter of such grout holes shall not be
less than 40 mm. All drilling directions upward and downward are included.
Grout holes shall be drilled through soil, rock and through reinforced and non-reinforced concrete.
Alternatively, where grout holes are to pass through heavily reinforced concrete, pipes shall be embedded
in the concrete, but the Contractor is responsible for ensuring that the position of pipes allows drilling
boreholes at specified direction. Grouting to be carried out through concrete shall not commence earlier
than 14 days after concrete pouring. Grouting shall also not he commenced in an area until all blasting have
been completed within 50 m.
3.7 Records
3.7.1 Drilling
Within 24 hours after completed drilling of a cored hole, the Contractor shall submit in duplicate a
complete log of the hole in a form approved by the Employer. The log shall include the following data:
- location (coordinates)
- borehole number
- type and diameter of boring
- ground level
- immediate, intermediate and equilibrium water levels with times and dates; note on colour and
losses, etc.
- description and state of weathering of rock and the levels of its boundaries
- percentage core recovery
- fracture log
- the results and levels of all in-situ testing
- a record of the driller's observations on progress of boring. rate of penetration, type of bit and speed
of rotation bit
- water pressure test results
- location of sample extraction (waterlcore material) for tests and change in s m t a can be readily
3.9.1 General
The Contractor shall furnish and install standard mild steel pipes for all standpipes and grout connections
set in the concrete or rock at the locations as required.
Pipes for grouting shall also be set over springs, crevices in the rock, faults or other foundation defects
Grout pipes set in concrete except those for the grout cap shall end not less than 30 mm inside the finished
surface of the concrete. When grouting is performed after the completion of concreting operations, a
standard coupling and wrapped nipple to facilitate removal after grouting shall be attached to the grout pipe
and shall extend outside the finished surface as required. The holes left upon removal of the wrapped
nipples shall be filled immediately and completely with element mortar.
The size of the grout pipe for each hole and the depth of holes for setting pipe for foundation grouting shall
be as required. Each pipe shall be anchored into the rock or concrete into which it is set and the space
around the pipe shall be carefully sealed with grout or other suitable material. All pipes and fittings to be
embedded in concrete shall be cleaned thoroughly of all din, grease, grout and mortar immediately before
being embedded in the concrete or rock.
3.93 Materials
All standard pipes and fittings for grouting, special grout outlets, all nails, tie-wire, wooden plugs, mastic
material for sealing purposes, temporary supports and other accessories required for installation of the
grouting system shall be furnished by the Contractor. The pipes shall be cut to length, threaded and
fabricated where required and placed by the Contractor.
The pipe shall be medium thickness in accordance with relevant standards. The pipe fittings shall be
malleable iron suitable for the pressure to be applied during grouting.
shall have been poured at least 30 calendar days prior to grouting work.
ut shall be placed at low pressures not exceeding 3.5 bar for each section.
Section 6Employer's Requirements 6.2 Technical Specificalions
Chapler 10 Dnlline & Grouting - 18
A sanded mortar grout shall be used. The gmuting of any hole shall not be considered complete until all
voids have been filled.
Vent pipes shall be installed for the release of air and water during grouting of crown, and overhreak
cavities which cannot he filled with concrete.
If any contact gmut hole may also he used for consolidating grout, the hole shall be cleaned for the first
grouting through the depth of the concrete lining. Prior to start consolidation grouting, contact grout shall
have set.
The borehole shall then be re-drilled to the depth as required, flushed and subsequently grouted
So far as practicable. the full grouting pressure shall be maintained constantly during grout injections.
However, as not to run a risk of rock or concrete displacement or while grout leaks are being caulked, the
pumping pressure or the suspension of pumping may be reduced. After the grouting of the holes or
connections is completed, the pressures shall be maintained by means of stopcocks or other suitable valve
devices, until the grout has set sufficiently so that it will be retained in the holes or connections being
grouted.
Any faulty stage or zone shall be re-grouted with grout which may differ from that originally used, until a
satisfactory result is obtained or, if this is unattainable, the depth concerned shall be grouted using
immediately adjacent holes until a satisfactory result is obtained in the original hole. The completed hole
shall then be filled with thick grout.
i
Dagachhu HPP Section 6 -Employer's Requirements 6.2 Technical Specifications
Cha~ter10 Drilline & Groutine - 21
- During grouting, grout leaks shall be caulked, but if this cannot be achieved and the leaks are
excessive, grouting shall be stopped and resumed later when the grout already injected into the
leaking fissures has hardened. Precautions shall be taken to ensure that the grout does not enter other
pans of the works such as drains. Where necessary, the Contractor shall establish level reference
points, upheaval gauges, etc. to be observed as a check against uplift. Any possible movement shall
be taken as an indication that the grouting pressure being used is excessive and it shall be
immediately relieved.
- Where grouting is practicable, the full grouting pressure shall be maintained constantly during grout
injections. However, as,a safeguard against rock or concrete displacement or while grout leaks are
being caulked, the Employer may require the reduction of the pumping pressure or the suspension of
pumping. After the grouting of the holes or connections is completed, the pressures shall be
maintained by means of stopcocks or other suitable valve devices, until the grout has set sufficiently
so that it will be retained in the holes or connections being grouted.
- Grouting of a hole shall not be considered completed until the required results have been reached.
Under embankment load of e.g. 40 m, the following grouting pressures for second stage grouting from the
gallery shall not be exceeded:
This grouting procedure shall include contact grouting to fill the joints between gallery and rock surface