Key Event Critical Path Analysis: Activities
Key Event Critical Path Analysis: Activities
Key Event
-modeling tool which used for analyzing the
-Milestone
events and activities in a project in order to
produce management information - Important event & being
nominated by manager
DUMMIES
ACTIVITIES
Events
Constrain or
-task that consume
logical connection. - Point time
time and resources
Do not consume
time & resources -Not consume time or resources
SYMBOL
For activities
Dangles
When an activity does not connect to other For event
event
Ordinary Dummy
activity
Ordinary
Start
Event
Event
Ordinary Ordinary
Event Event
1.
Number, in any order, the start events in the network
2. Mark all activities leaving the numbered events
3. Number, in any order, all events which have only marked activities entering them
4. If all events are numbered then stop. Otherwise go 2