Daily Progress Report

Ind-Barath Energy (Uthkal) Ltd. 2X350 MW Power Plant at Sahajbahal , Jharsuguda.

Report date:04-03-2011 Progress date:03-03-2011

Job Name:

Progress of Work(Procurement of Steel)Cooling Tower-2

Description Quantity Completed Balance


Sl of Work Total Qty Unit Till Last Day For the Day Cumulative Qty. Remarks
1 8mm mesh 55.987 MT
2 8mm 129.267 MT
3 10mm 140.329 MT
4 12mm 30.086 MT
5 16mm 267.925 MT 52 15 67 200.925
6 20mm 257.067 MT
7 25mm 0.266 MT

Daily Man power report


Contractor Electricians/
Sl. Name Location Carpenters Bar benders Supervisors Mason Un Skilled Total
1 Om Astha CT-2 8 4 14 26

Staff Details
Total No of
Staff: Engineers 4
Immidiate Requirement

Bar benders 15 N o's


Unskill (Helpers) 40 N o's
Masons 03 N o's