S.

No Work Description Start Date End Date


1 Block work March 15,2011 April 15,2011
2 Plaser works April 16,2011 May 09,2011
3 Painting works May 10,2011 May 29,2011
4 Water Proofing and toilets May 01,2011 May 08,2011
5 Roof water proofing May 01,2011 May 13,2011
6 Floor tiles and toilets May 14,2011 May 25,2011
7 wall tiles and toilets May 10,2011 May 25,2011
8 Floor tiles at villa May 15,2011 May 25,2011
9 Skirting at villa May 25,2011 May 31,2011
10 Gypsum board wall at toilet May 10,2011 May 21,2011
11 Gypsum ceiling May 10,2011 May 25,2011
12 Sanitary fixtures May 27,2011 May 27,2011
13 Metal works at door May 23,2011 May 31,2011
14 Metal works at windows May 15,2011 May 31,2011
15 Kerb stone installation May 24,2011 May 26,2011
16 Tiles installation May 27,2011 May 31,2011
17 Punch list June 01,2011 June 02,2011
18 Hand over June 01,2011 June 05,2011
19 Out side drainage line April 23,2011 May 10,2011
20 Savito plaster April 23,2011 May 31,2011
21 Electrical April 14,2011 May 01,2011
22 Mob. Termination April 10,2011 May 20,2011
23 Electrical fixtures April 27,2011 May 31,2011