Professional Documents
Culture Documents
CCS Demonstration in Developing Countries - Analysis of Key Issues and Barriers
CCS Demonstration in Developing Countries - Analysis of Key Issues and Barriers
Financing Roundtable
Singapore
7 April 2011
Ashok Bhargava
1
Disclaimer
2
Contents
Background
3
Background
4
CCS Issues and Barriers – An Overview
Technical Strategic
Not included in
Technology of technology portfolio
last resort
No experience in Mitigation only
Developing countries Limited technical technology
readiness No incentives
Limited No IGCC
experience plants No long term
No coal plant goal
Storage data not Weak strategic
With CCS High energy
available support Weak signal to
penalty
Delays in market
Only 5 plants Enabling framework
in operation Limited to
oil and gas industry
Need multi- Immature Uncertain market
Sectoral approach technology perception
Complex
design Slow progress
on CCS demonstration
Difficult financial
High risks
closure
Cautious process
Excessive energy
Expensive storage
penalty Uncertain
characterization Complex MMV
cash flow High environmental
requirements
and safety concerns
High cost Low risk Significant
Long term Limited
appetite operational risk
High Storage liability experience
capital costs High Complex regulatory
Offtake risks
risks needs
Financial Legal and Regulatory
5
Issues and Barriers – Strategic
Strategic
Not included in
Technology of technology portfolio
last resort
Mitigation only
technology
No incentives
No long term
goal
Weak strategic
support Weak signal to
Delays in market
Enabling framework
Uncertain market
perception
Technical
No experience in
Developing countries Limited technical
readiness
Limited No IGCC
experience plants
No coal plant Storage data not
With CCS High energy
available
penalty
Only 5 plants
in operation Limited to
oil and gas industry
Need multi- Immature
Sectoral approach technology
Complex
design
High risks
Cautious process
Complex MMV
High environmental
requirements
and safety concerns
Complex regulatory
needs
Legal and Regulatory
8
High perceived risks due to long-term liabilities
Issues and Barriers – Financial
Excessive energy
Expensive storage
penalty Uncertain
characterization
cash flow
High cost Low risk Significant
appetite operational risk
High
capital costs High
Offtake risks
risks
Financial
The base cost for IGCC plant is $1.6 million/ mega watt compared
to $ 0.7 million / MW for SC
10
Coal-fired Power Plants with CCS –
Financial Analysis………………..Contd
Without CCS
With CCS
120
60
51
400
Base 30
Cost Base
200 Cost
With CCS
120
24% 67
60
51
400
Base Base 30
Cost Cost
200
$226 M $226 M
12
Coal-fired Power Plants with CCS –
Financial Analysis………………..Contd
3.5 0.2
0.19 $/kWh
3
0.15
Cost ($million/MW)
2.5
0.11 $/kWh
Tariff ($/kWh)
2
0.09 $/kWh
0.1
1.5 0.08 $/kWh
1 0.05 0.05
0.5
0 0
Wind IGCC + CCS SC+CCS Solar Std Coal
Electricity generated -
1GW
and solar plants 4000 Solar
1 GW
3000 Coal-
GWh
GWh fired
3000
power
plant
Energy security solution 2000
1 GW
Wind
1000
Action Purpose By
Establish CCS Overcome near- to Contributions from
Demonstration Fund medium-term developed countries
of billion dollar scale commercial/economic
gaps (up to 2020) Multilateral
development banks to
Provide positive actively work with the
incentives for CCS donor governments
demonstration and developing
countries in setting up
Reduce time lag for the fund
CCS demonstration
between developed
and developing
15 countries
Fast Track CCS Demonstration –
Recommended Actions……………….contd
Action Purpose By
Provide complementary policy Encourage energy Governments in
support and power relevant developing
companies in countries
country–specific pilot regulatory developing
framework countries to move
forward with CCS
Provide suitable financial demonstration
incentives—tax relief, tariff
premiums for carbon-free
electricity, incentives, loan
guarantees, etc. for “with CCS”
demonstration projects
16
Role for CCS Demonstration Fund
A $5 billion fund to support CCS demonstration in developing
countries up to 2020
17
Conclusions and Way Forward
18
For further details
abhargava@adb.org
19