Professional Documents
Culture Documents
Test On Power Plant Operation
Test On Power Plant Operation
Test On Power Plant Operation
22) With All C.C Pumps Trip, Boiler Trips On_________________________ Protection.
25) APH cold end temperature should not be less than__________________oC and is
average of __________________________.
(A) 60, hot air leaving & flue gas entering (B) 90, hot air entering & flue gas
leaving
(C) 60,cold air entering & flue gas leaving (D) 90,cold end entering & flue gas
leaving
02. Warm start-up of turbine refer to the condition when HP Cylinder inner cooling
temperature is: -
a. Less then 150ºC but greater then 100ºC.
b. Between 150ºC and 335ºC.
c. Between 335ºC and 500ºC.
d. Between 500ºC and 1000ºC.
04. During turbine shutdown or tripping, while coasting down the barring gear takes
auto start at: -
a. Standstill (Zero rpm). b. 36 rpm
c. 250 rpm. d. 2750 rpm.
05. During boiler start-up, which equipment is run first just after drum filling: -
a. B.C.P. b. FD Fan
c. ID Fan d. Air Heater
06. What is the desired drum presser for starting cold rolling of turbine:-
a. 20.0 Kg/cm² b. 60.0 Kg/cm²
c. 30.0 Kg/cm² d. 100.0 Kg/cm²
07. At normal operating pressure, hydrogen purity in generator casing should be:-
a. > 50% Hydrogen in air. b. > 90% Hydrogen in air.
c. >76% Hydrogen in air. d. >98% Hydrogen in air
08. What is a “must” condition before taking the first FD fan in service: -
a. At least one coal mill should be in service.
b. At least one oil gun should be firing.
c. At least one soot blower purge air fan should be in service.
d. At least one I. D. Fan should be in service.
10. Which of the following equipment stops in auto while turbine run up from barring
speed to 3000 rpm: -
a. AC Jacking oil pump. b. Air side AC Seal Oil Pump.
c. AC Lub Oil Pump. d. All the above.
11. Which of the following will not cause a boiler tripping while unit is at 500MW: -
a. Loss of two coal mills. b. Loss of two ID Fans.
c. Loss of two FD Fans. d. Loss of two BCPs.
12. The following can not be indicated by the Capability curve trivectormeter meter: -
a. Reactive Power b. Power Factor
c. Load Angle d. Frequency
13. During turbine start-up, you are about to run AEP for condenser vacuum pulling.
Which of these equipments do you expect not to be running by now:-
a. C.E.P. b. Flame Monitor Purge air fan
c. B.F.P. d. Coal Mill
14. All turbine side leg drains, chest pre-warming drains and chest drains are
closed:-
a. Soon after leg charging
b. Just after completion of vacuum pulling.
c. After ensuring that HP-LP bypass is in service.
d. After unit synchronization.
15. What is the immediate activity to be done on TG side after completion of leg
charging:-
a. Close turbine drains.
b. Put the turbine gland sealing steam system on warm-up.
c. Start vacuum pulling.
d. Run the second C.E.P.
Q.2: Write the answer to these question in a few lines. Each question carry 3
marks.
1. What is the very first activity done while shutting down the boiler, when the unit
is operating at 500MW ?
2. what is the pH of boiler water ? What is done to maintain the pH value ?
3. While establishing generator seal oil system, Which side ( air or gas ) is sealed first
and why?
4. What is accepted as the “signal” of completion of warm-up of turbine gland
sealing steam system?
5. At how much unit load is 11KV Unit Bus load is transferred onto Unit
Transformer while load raising?
6. What does G.C.M. do?
7. What is the purpose of CBD? Why CBD operation is required during boiler start-
up?
8. Where do the stator cooling water actually flow to cool the stator winding?
9. What is the function of hydrogen dryer? How much is the duration of its one
cycle?
10. After shutting down the turbine, What is the criteria to stop barring gear safety?
Q.4: White the answer to these question in short. Each question carry 5 marks.
1. What is the significance of `Soot blower purge air fan’? During boiler start-up
when it is taken in service?
2. What is the function of ESP? When are ESP fields charged during boiler start-up?
3. What do you mean by drum DT?
4. What steps are taken in removing silica from boiler drum?
5. What are the necessary conditions for synchronization?
6. Draw an approximated capability curve of generator. Mark the boundaries
according to the operational limitations they impose.
7. What are the components cooled by hydrogen gas?
8. What is the function of vacuum breaker vlave?
Max. Marks: 50
QUESTION PAPEER ON
COMMISSIONING MODULE
FOR EXECUTIVE TRAINEES
4. The process of forming magnetic layer inside boiler tubes and other
vessels is called as:
(a) Passivation
(b) Steam blowing
(c) Chemical washing
(d)Water flushing
18. Acid washing of TG lube oil and governing oil pipe work is done by
a strong acid or mild acid?
22. How much speed is achieved during turbine over speed testing?
23. What for the oil injection test is carried out?
25. List out any o9ne commissioning test/ check carried out on lube oil
coolers.
[ ]
5. Write down the major steps of Acid cleaning and chemical names
required for Super heater back flushing? (10
marks)
(08
marks)
**********