Professional Documents
Culture Documents
Analisa Harga Satuan
Analisa Harga Satuan
Analisa Harga Satuan
1 M3 Urugan Pasir
1.200 M3 pasir Urug 90,000.00 - 108,000.00
0.300 Hr Pekerja 35,000.00 10,500.00 -
0.037 Hr Mandor 55,000.00 2,035.00 -
12,535.00 108,000.00 120,535.00
1 M3 Beton K.100
0.880 M3 Split 240,000.00 - 211,200.00
0.540 M3 pasir Cor 137,500.00 - 74,250.00
4.000 Zak Semen @ 50 Kg 54,000.00 - 216,000.00
1.000 Ls Peralatan 830.00 - 830.00
1.000 Hr Tukang 45,000.00 45,000.00 -
0.100 Hr Kepala Tukang 47,500.00 4,750.00 -
3.750 Hr Pekerja 35,000.00 131,250.00 -
0.144 Hr Mandor 55,000.00 7,920.00 -
188,920.00 502,280.00 691,200.00
1 M3 Beton K.225
0.875 M3 Split 240,000.00 - 210,000.00
0.625 M3 pasir Cor 137,500.00 - 85,937.50
6.200 Zak Semen @ 50 Kg 54,000.00 - 334,800.00
1.000 Ls Peralatan 3,592.50 - 3,592.50
1.100 Hr Tukang 45,000.00 49,500.00 -
0.200 Hr Kepala Tukang 47,500.00 9,500.00 -
3.429 Hr Pekerja 35,000.00 120,000.00 -
0.144 Hr Mandor 55,000.00 7,920.00 -
186,920.00 634,330.00 821,250.00
###
1 M3 Beton K.300
0.700 M3 Split 240,000.00 - 168,000.00
0.620 M3 pasir Cor 137,500.00 - 85,250.00
8.200 Zak Semen @ 50 Kg 54,000.00 - 442,800.00
1.000 Ls Peralatan 3,030.00 - 3,030.00
1.100 Hr Tukang 45,000.00 49,500.00 -
0.200 Hr Kepala Tukang 47,500.00 9,500.00 -
4.200 Hr Pekerja 35,000.00 147,000.00 -
0.144 Hr Mandor 55,000.00 7,920.00 -
213,920.00 699,080.00 913,000.00
rab dibuat hanya berdasrkan perhitungan global dari proyek proyek yang telah ada
material mengacu ke pabrikator lokal .
harga baja bisa berbeda beda tergantung sfesifikasi yang dipakai