Professional Documents
Culture Documents
Denmark Wind Power Report
Denmark Wind Power Report
Denmark Wind Power Report
Keywords
electrical engineering & distribution;
power stations (non-fossil fuel); weather
Fig. 1. Completed in December 2003, Nysted offshore wind farm in Denmark has 72 turbines with a
total capacity of 166 MW, making it the world’s largest (copyright: Elsam A/S)
The global oil price rise in the 1970s energy equivalent of 16% of national
prompted the Danish Government to demand.
switch to imported coal for its thermal This paper reports on performance data
power stations and to start a wind energy of the west Denmark power grid, to
programme targeted at generating 10% of which 80% of the country’s wind power
electricity by 2000. The target was is connected. The east Denmark power
achieved and there are now 5500 wind grid is entirely separate but both grids are
turbines—including the world’s two heavily interconnected to the national
largest offshore wind farms at Nysted grids of neighbouring countries to the
(Fig. 1) and Horns Rev—producing the north and south.
C I V I L E N G I N E E R I N G
WHY WIND POWER WORKS FOR DENMARK
Key: Key:
Local combined heat and power plants Wind turbine(s)
Thermal power plant
North
North Sea
Sea
Aalborg
Aalborg
Skive Skive
Aarhus Aarhus
DENMARK
DENMARK
Kolding
GERMANY GERMANY
0 km 30 0 km 30
Fig. 2. West Denmark’s six thermal power stations of 3516 MW are sup- Fig. 3. West Danish wind carpet has an installed capacity of 2374 MW,
plemented by a further 1450 MW from combined heat and power plants equivalent to 0.88 kW per person
in most towns and villages
A 15-year programme capacity of the main thermal power sta- During the 1990s, there was a crash-
tions at the end of 2003 was 3.5 GW. building programme for wind power,
In 1990 Denmark had six large power During the past 15 years there was also totalling 2374 MW1 at the end of 2003
stations, all of them designed as combined an intensive construction programme to (Fig. 3). Although more wind power overall
heat and power plants providing district upgrade the district heating plants in most has been installed in the US and Germany,
heating to west Denmark’s largest towns Danish towns and villages to combined the ‘wind intensity’ of western Denmark is
(Fig. 2). Five are coal-fired power stations heat and power. The total capacity of these still unmatched. It is equivalent to 0.88 kW
and the sixth is designed for ultra-super- ‘de-centralised’ power units in 2004 was of installed capacity per person in western
critical steam operation on gas. The coal- 1450 MW. They are mostly based on natur- Denmark compared with 0.18 kW per per-
fired station near Aalborg has since been al gas engines, though a significant number son in Germany and 0.01 kW per person in
extended and this and the gas-fired sta- are bio-fuelled. Many industrial combined the UK (at the end of 2003).
tion are now the most efficient Rankine- heat and power plants and factories also Furthermore, Denmark boasts one of the
cycle plants in the world. The installed supply heat to the district heating system. world’s most developed wind energy man-
C I V I L E N G I N E E R I N G 67
SHARMAN
25 duction from wind generators during 2003 dropped to around 25%. As time goes
20 was 4.36 TWh out of a total of nearly by and the development of wind power
15 27 TWh, with local consumption at just at the best wind sites gives way to less
over 20 TWh—a record amount. favourable ones, the specific output at
10 UK onshore each new site in the UK is likely to
West Denmark
5 Highly relevant to the UK decline further.
0
1999 2000 2001 2002 2003
Furthermore, wind generators are not
On the face of it, west Denmark has exempt from breakdown and, like any
Fig. 6. Load factors are now relatively steady already nearly achieved the 20% renew- other rotating plant, need regular servic-
in west Denmark but declining in the UK able energy goal to which the UK aspires ing. Breakdown outages and even rou-
(sources: ELTRA and for 2020. Its proximity and shared lati- tine service outages can be extended,
www.dti.gov.uk/energy/inform/dukes)
tudes with the UK—as well as the large especially if these are offshore. In
68 C I V I L E N G I N E E R I N G
WHY WIND POWER WORKS FOR DENMARK
Denmark there is a very large and wind output and the wind carpet con- ables hopes are founded, actually behaves.
healthy service sector devoted solely to sumed more power than it could pro- Output increases more or less linearly
the maintenance and repair of wind tur- duce. In other words, the wind carpet between a wind speed of 5 m/s and
bines. Maintenance and repair of an age- became a net energy consumer. There 13 m/s. Above this speed, output levels off
ing wind-carpet probably accounts for was also a whole week in February 2003 and, at 20 m/s (45 mph, force 8), stalls
some of the long-term decline in Danish when virtually no wind power was gen- altogether for many machines in the sys-
load factor. erated in west Denmark. tem. Most modern turbines are designed to
It is axiomatic that a high load factor In view of the Danish experience, it is operate above this speed with a 20% lower
will result in high output. A lower load probably imprudent to believe the UK
factor necessitates a larger installed can expect firm capacity from its wind
45
capacity just to deliver the volume of carpet, despite its larger size and more
40
energy required. If the Danish load fac- westerly geography. If the wind does not
35
tor is a reasonable guide to that which blow, no power can be generated—and
Capacity: GW
30
will be reached in the UK, the projec- high-pressure systems can be very large
25
tions of the capacity needed to deliver and persistent. Paradoxically, if the wind
20
the 60 to 70 TWh in 2020 foreseen by blows too much, there is also no power
15
the UK’s energy planners will be large. generated. A modern wind turbine needs 10
In Fig. 7, it can be seen that if 70 TWh a wind speed of around 4 m/s before it 5
are needed to fulfil the UK Government’s can begin generating but it must feather 0
renewable energy targets, this can be sup- its blades at around 25 m/s to prevent 20 25 30 35
Load factor: %
plied from 23 GW if the load factor is mechanical damage (Fig. 10).
35%—but 41 GW would be needed to Figure 11 illustrates how the country- Fig. 7. Installed wind farm capacity needed to
supply the same amount if the load factor wide wind carpet, consisting of the modern deliver the UK Government’s 2020 target of
70 TWh increases dramatically as load factor
were to be as low as the wind farms of wind machines on which the UK’s renew- decreases
west Denmark. Each GW of wind gener-
ation costs roughly £1 billion—this is the
average cost of equal amounts of offshore 2500
and onshore wind capacity—so the finan-
cial penalty for not getting the load factor 2000
right is enormous. To these costs must be
added the infrastructural costs of deliver-
Power: MW
1500
ing the power to load centres and the
accompanying costs of standby power 1000
and load balancing.
500
A highly variable supply
0
From an installed capacity in west January February March April May June July August September October November December
Month (2003)
Denmark of 2374 MW there were nine
occasions during 2003 when the wind Fig. 8. Wind power production in west Denmark exceeded 2000 MW nine times during 2003
carpet output exceeded 2000 MW
(Fig. 8). Furthermore, there were many
3500
events during 2003 when the whole car-
pet was delivering an output of over 75% 3000
of its installed capacity. When this hap- 2500
pens, it behaves as a single power station,
Power: MW
C I V I L E N G I N E E R I N G 69
SHARMAN
% of installed capacity
100
Output as a proportion
80
of capacity: %
60
20
0
0 5 10 15 20 25 30 35
Wind speed: m/s
Fig. 11. How power output in west Denmark increases, decreases and finally shuts down with increasing wind speed (source: ELTRA)
70 C I V I L E N G I N E E R I N G
WHY WIND POWER WORKS FOR DENMARK
their respective needs from water tur- tration of wind capacity in future. In con- Problems with forecasting
bines. Hydropower output can be adjust- trast, an ‘island’ system depending mostly
ed very rapidly as the highly variable on thermal generating capacity will have Although the climate of the British Isles
wind power flows through the intercon- to accommodate power swings by ramp- is notoriously fickle, Denmark also experi-
nectors. ing thermal capacity up and down, some- ences difficulties with weather forecasting.
It is also relevant that all three neigh- times very quickly. Fig. 15 shows a bad but unfortunately
bouring systems, including Germany’s,
are many times bigger than west
Denmark’s and can act as a power sink to 1500
500
was 1000 MW less, the Danish balancing
solution was mainly handled across the 0
interconnectors.
-500
The extent of the balancing challenge
can be seen in Fig. 14. This shows the -1000 Wind power output
changes in wind carpet output each hour -1500
Net exchange
Month (2002)
Fig. 14. Hourly changes in west Danish wind output power in 2002 as a percentage of overall wind
100
Skagerrak
capacity. In the absence of interconnectors, thermal power stations would need to be ramped up
0M
950
Sweden
MW
1500
580 MW 1350
Denmark 1200
North
Sea 610 MW 1050
Power: MW
900
750
1200 MW
Baltic
Sea 600
450
800 MW
Germany 0
2 4 6 8 10 12 14 16 18 20 22 24
Fig. 12. West Denmark has a total intercon- Time: h
nector capacity of 2400 MW with its neigh-
bours Germany, Norway and Sweden—about Fig. 15. Forecast versus actual wind power output in west Denmark on 27 October 2002 (source:
the same as its installed wind power capacity Jyllands Posten)
C I V I L E N G I N E E R I N G 71
SHARMAN
common day for Danish wind forecasts. 3000 MW installed by the end of 2003— difficult to do this with slower-reacting
Wind forecasting to the requirements of equivalent to 0.88 kW of wind energy thermal power stations and may thus
the transmission system operator is a major per person in west Denmark. The aver- have to limit their reliance on wind
challenge as even the best mean average age annual load factor for the wind tur- power.
wind speed can only be predicted to within bine carpet in west Denmark is measured
1 m/s. As indicated in Fig. 11, for west at approximately 20%. There are consid-
Denmark wind power this equates to +/- erable and often rapid output variations
320 MW or 12% of wind capacity. throughout the day and throughout the
West Denmark’s transmission system year. Accurate forecasting of wind speeds References
1. ELTRA. Oversigt 2003 (Overview 2003).
operator, ELTRA, is making significant is still difficult and output rarely matches
ELTRA, Fredericia, Denmark, 2003.
investments to improve the accuracy of demand, sometimes dropping below zero
2. TROEN I and PETERSEN E. L. European Wind
wind forecasting and it is possible that as stalled wind turbines still require Atlas. Risø National Laboratory, Roskilde,
during the next 10 to 15 years more power for their steering systems. Denmark,1989.
accurate weather predictions will make The variations, which are inherent in
surprise events somewhat rarer. However, any wind energy system, can be readily
it is unlikely they can be ruled out alto- accommodated in west Denmark because What do you think?
gether or that their probability can be there are very strong electrical connec- If you would like to comment on this paper,
reduced to an insignificant level. tions to the much larger grid systems of please email up to 200 words to the editor at
editor@ice.org.uk.
Norway, Sweden and Germany that can
If you would like to write a paper of 2000 to 3500
Conclusions absorb these variations, particularly due
words about your own experience in this or any
to their reliance on rapid-reacting related area of civil engineering, the editor will be
Denmark has the most intense wind hydropower. Countries such as the UK, happy to provide any help or advice you need.
carpet in the world, with a total of which operate an ‘island’ grid, will find it
72 C I V I L E N G I N E E R I N G