Capacity Planning
Capacity Planning
Schedule
• Understanding of capacity planning – line –
factory section (attendance/efficiency)
• Operation breakdowns, independent and
dependent processes, flow diagrams.
• Machine, equipment and manpower
requirements.
• Line and production balancing.
• Production control
• Role of the supervisor
Factory capacity
• 500 operators working 48 hour week.
• Work content of 30 minutes per garment
Therefore
Borderline ?
Exercise
Section 1
Operator cont Att op. production SMV offStd Perf Uti Eff
min min
Alison 540 540 1. 1000 0.37 30
Betty 540 480 2 1120 0.30
charlie 540 0 3 0 0.26
Dorothy 540 540 4 950 0.23
3 350 0.26 75
Ethel 540 540 5 1070 0.45 15
Freda 540 540 6 1250 0.40 30
Gail 540 540 7 1200 0.21
3 880 0.26
Heather 540 540 8 600 0.85 30
Irma 540 540 8 600 0.85 45
June 540 540 9 1275 0.38 30
Totals
Exercise
• Section 1
Operator cont. Att op production SMV OffStd Perf Uti Eff
mins
Alison 540 540 1. 1000 0.37 30 72.5 94 68.5
Betty 540 480 2 1120 0.30 70 100 70
charlie 540 0 3 0 0.26
Dorothy 540 540 4 950 0.23 66.5 86 57.3
3 350 0.26 75
Ethel 540 540 5 1070 0.45 15 91.7 97 89.2
Freda 540 540 6 1250 0.40 30 98 94 92.5
Gail 540 540 7 1200 0.21 89 100 89
3 880 0.26
Heather 540 540 8 600 0.85 30 100 94 94.4
Irma 540 540 8 600 0.85 45 103 92 94.4
June 540 540 9 1275 0.38 30 95 94 89.7
Totals 5400 4800 3.22 255 87.6 94.7 83
Exercise
• Attendance = 4800/5400 = 89%
• total sms earned = 3982.30
Capacity planning
• Factory
• Department
• Section
• Machine
• Skill
• Restricting or defining factor
Capacity planning
• What is the starting point?
• How many garments can a section
produce?
• How many operators/machines do we
need to produce a given number of
garments?
• Same calculation – just reversed!
Information!!
• Labour content (SMVs/SAMs/Std. hrs)
• Available operators
• Contracted hours
• Absenteeism levels
• Efficiency levels
Capacity planning
• Information
• Information
• Information
• Obvious but where does it
come from?
• How accurate is it?
Work content. SAMs, SMVs
• Are they accurate? (can self correct in
capacity planning)
• What operations do they cover?
• What operations are unmeasured or
performed by indirect operators. Be clear!
Capacity planning - people
• How many garments can a given number
of people produce?
• Number of operators
• SMV (Labour content)
• Absenteeism
• Efficiency/ inefficiency!
Capacity planning - people
• 500 direct operators working 48 hours/week
• S.M.V. = 25 per garment
• Absence level of 8%
• Average efficiency of 85%
• Contracted time
1. Calculate standard hour/minutes that can be
produced by operators.
2. Calculate how many garments that represents
Capacity planning - people
• 500 operators x 48 hours = 24000 contracted
hours
• 24000 – 8% (1920 hours) absence = 22080
attended hours (absence costs 40 operators)
• At efficiency of 85% std. hours produced =
22080 x 85% = 18768 std hrs.
• 5232 hours lost to absence & inefficiency.=
21.8% of original contracted hours
Capacity planning - people
• 18768 std hrs produced
• S.M.V. = 25 mins. or 0.417 std. hrs.
• Garment capacity = 18768
0.417
= 45007 garments.
Capacity planning
• Under the same conditions how many
people are need to produced 70000
garments per week.?