Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 50

Chapter 6

Schedule Management

Chapter 6: Schedule Management 1


Schedule Management

Chapter 6: Schedule Management 2


Introduction

Chapter 6: Schedule Management 3


Henry Ford Hospital
 Aggregate planning involves matching
hospital’s available capital, workers, and
supplies to a highly variable customer
demand pattern
 903 beds arranged into 30 nursing units
 Each nursing unit contains 8 to 44 beds
 Each nursing unit treated as independent
production facility
Chapter 6: Schedule Management 4
Factors Complicating Aggregate
Planning at Henry Ford Hospital
 High degree of demand variability
 average number of occupied beds in 1991
was 770
 in one 8-week period an average of 861 beds
was occupied
 in another 8-week period an average of 660
beds were occupied
 number of beds occupied could change by as
may as 146 beds in less than two weeks

Chapter 6: Schedule Management 5


Complicating Factors continued
 Large penalty for not being able to admit HMO
patients
 lost revenue
 must pay other hospital for patient’s stay
 a simple obstetrics case cost $5,000
 Tight labor market for RNs
 12 to 16 weeks to recruit and train nurses at cost of
$7,600
 Cost of 8-bed modules exceeds $35,000/
month
Chapter 6: Schedule Management 6
Importance of Aggregate Planning

 Without sufficiently long-term view may make


short-term decisions that hurt the
organization in the long-term
 For example, shortly after Henry Ford
Hospital reduced staff, it determined the staff
was needed
 New staff was recruited
 Both staff reduction and recruiting costs
incurred
Chapter 6: Schedule Management 7
Extremely Difficult Decision

 Demand can shift by more than 16% in


a two-week period
 Takes 12 - 16 weeks and costs $7,600
a piece to recruit new nurses
 By time staff hired, demand may have
shifted again

Chapter 6: Schedule Management 8


Extremely Difficult Decision
continued

 If don’t have enough staff, cost $5,000


per patient turned away (simple cases)
 Cost of one idle 8-bed module is
$35,000/month or $420,000/year

Chapter 6: Schedule Management 9


Package Products Inc.

 Folding Carton Packing for baker and


deli industry
 Significant growth during 1990s
 More demanding customers
 Needed to do better job of managing
operations

Chapter 6: Schedule Management 10


Producing Folding Cartons

 Four to eleven steps


 rolls of pulpboard cut into sheets
 sheets run through printing presses to
add four color images
 sheets dried and die cut
 cellophane window added
 cartons glued
 product prepared for shipping
Chapter 6: Schedule Management 11
Scheduling at Package
Products

 Initially used Gantt chart


 manually schedule jobs using a board
and magnetic strips
 capacity shortage problems
 critical information scattered throughout
organization
 Acquired finite capacity scheduling
(FCS) software package
Chapter 6: Schedule Management 12
Using the FCS Package

 Runs on PC
 Updates previous day’s schedule
 Allows performing what-if analysis
 Used to generate schedules for next 3 to 6 months
 Overtime reduced by 300%
 On-time delivery performance improved by 32%
 Backorders reduced by 53%
 Respond to customer inquiries in 22 seconds

Chapter 6: Schedule Management 13


Scheduling

 Ensuring the right tasks are conducted


at the right time on the right items
 Productivity problems often attributable
to poor schedule management
 Scheduling not anywhere as difficult
for continuous flow and processing
organizations as it is for job shops

Chapter 6: Schedule Management 14


The Sequence of Scheduling
Activities

Chapter 6: Schedule Management 15


Scheduling Activities

Chapter 6: Schedule Management 16


Demand Forecast
 Forecast supports entire scheduling process
 May not need forecast if customers place orders far in
advance
 Forecast used for different purposes
 Long-range forecasts used for capacity planning

 Forecast in range of 9 to 18 months used for

aggregate planning
 Short-range forecasts used for loading and

sequencing

Chapter 6: Schedule Management 17


The Aggregate Plan

 Approximate schedule of overall


operations that will satisfy demand
forecast at minimum cost
 Planning horizon often a year or more and
broken into monthly or quarterly periods
 Purpose is to minimize short-sighted
effects
 Work with aggregate units and resources

Chapter 6: Schedule Management 18


The Aggregate Plan continued

 Equivalent units
 Relevant costs
 hiring and layoff costs
 inventory and backorder costs
 wages and overtime charges
 subcontracting costs

Chapter 6: Schedule Management 19


The Production Plan
 Result of managerial iteration and changes to
aggregate plan
 Often disaggregated one level into major output
groups
 Aggregate Plan: number of automobiles to
be produced in each of the upcoming 12
months
 Production Plan: number of compacts, mid-
size, full-size, light trucks, and minivans to
produce in each of the upcoming 12 months

Chapter 6: Schedule Management 20


The Master Schedule

 Point where actual orders incorporated


into scheduling system
 Aggregate outputs broken down into
individual end items

Chapter 6: Schedule Management 21


Check for the Following Problems

 Does schedule meet production plan?


 Does schedule meet demand forecasts?
 Are there priority or capacity conflicts?
 Are other constraints violated?
 Does schedule conform to policy?
 Does schedule conform to laws and
rules?
 Does schedule provide flexibility?
Chapter 6: Schedule Management 22
Rough-Cut Capacity Planning

 Feasibility check of master production


schedule
 Historical ratios of loads placed on
workcenters used
 Workloads assumed to fall in period
end items demanded

Chapter 6: Schedule Management 23


Priority Planning

 What materials are needed when


 Feasibility check of master production
schedule to make sure all materials will
be available when needed
 Determine when order is needed and
schedule backwards from that date
 Material Requirements Planning (MRP)
systems often used
Chapter 6: Schedule Management 24
Capacity Planning

 Inventory control system and master


schedule used to determine required
capacity over planning horizon
 Load reports generated for each work
center
 Inventory and lead times considered

Chapter 6: Schedule Management 25


Loading

 Deciding which jobs to assign to which


work centers
 Often some equipment or workers
better for certain jobs

Chapter 6: Schedule Management 26


Sequencing

 After jobs assigned to work centers,


order in which to process the jobs
must be decided
 Sequencing can have impact on
timeliness of job completions
 Priority rules often used

Chapter 6: Schedule Management 27


Detailed (Short-Term) Scheduling

 Detailed schedules itemizing specific


jobs, times, materials developed
 Typically done for only a few days in
advance

Chapter 6: Schedule Management 28


Dispatching

 All previous activities are planning


activities
 Dispatching is the physical release of a
work order from production planning

Chapter 6: Schedule Management 29


Expediting

 Task of getting job done on time once


it is released to the shop floor
 Special tags used to identify hot jobs

Chapter 6: Schedule Management 30


Aggregate Planning

Chapter 6: Schedule Management 31


Capacity Options

 Overtime
 Additional or fewer shifts
 Hiring or laying off workers
 Subcontracting
 Building up inventories
 Leasing facilities
 Backlogging demand
 Changing demand
 Undersupplying the market

Chapter 6: Schedule Management 32


Pure Aggregate Planning Strategies

 Level Production
 Equal amount produced each period
 Steady employment
 Inventory costs and risks
 Chase Demand
 Production matched to demand for the
period
 Minimal inventory
 High overtime or hire/fire costs
Chapter 6: Schedule Management 33
Personnel Needed by Rap-X-Press

Chapter 6: Schedule Management 34


Level Production at 40 Workers

Chapter 6: Schedule Management 35


Cost of Chase Demand with 40 Workers

Chapter 6: Schedule Management 36


Master Scheduling

Chapter 6: Schedule Management 37


Master Production Schedule

 Production plan disaggregated into


individual end items
 Final word about what will be built and
when
 Altering the master schedule can alter
inventory levels, lead times, capacity
requirements and so on
 Should not be a “wish list”
Chapter 6: Schedule Management 38
Master Production Schedule
 Sales and operations key players in developing
master schedule
 MPS usually stated in terms of weekly periods
(buckets)
 Rolling schedule
 Four periods
 frozen period

 firm period

 full

 open

Chapter 6: Schedule Management 39


Orders Replacing the Forecast in the
Master Schedule

Chapter 6: Schedule Management 40


Master and Final Assembly Schedules

Chapter 6: Schedule Management 41


Four Periods in the Rolling MPS

Chapter 6: Schedule Management 42


Scheduling Services

Chapter 6: Schedule Management 43


Hospitals

 Patient arrivals somewhat


uncontrollable
 Specialized and expensive equipment
 Nurses must always be available
 Nurses represent large expense
 Constraints associated with scheduling
nurses
Chapter 6: Schedule Management 44
Urban Alarm Services

 Quick response required


 Personnel is a major expense
 Use of duty tours can complicate
scheduling

Chapter 6: Schedule Management 45


Educational Services

 Scheduling of classes
 Assignment of classes to students
 Allocation of faculty to classes
 Allocation of facilities to classes

Chapter 6: Schedule Management 46


Yield/Revenue Management and
Overbooking

 Attempt to allocate the fixed capacity


of a service to match the revenue
demand in the market place

Chapter 6: Schedule Management 47


When is Yield Management Appropriate?

 Fixed Capacity
 Perishable Capacity
 Segmentable Market
 Capacity Sold in Advance
 Uncertain Demand
 Low Marginal Sales Cost, High
Marginal Capacity Addition Cost
Chapter 6: Schedule Management 48
Overbooking
 An attempt to reduce costs through
better schedule management.
 Based on inventory solution for the
“newsboy problem.”

Chapter 6: Schedule Management 49


Copyright
Copyright John Wiley & Sons, Inc. All rights reserved.
Reproduction or translation of this work beyond that named in
Section 117 of the United States Copyright Act without the
express written consent of the copyright owner is unlawful.
Requests for further information should be addressed to the
Permissions Department, John Wiley & Sons, Inc. Adopters of
the textbook are granted permission to make back-up copies
for their own use only, to make copies for distribution to
students of the course the textbook is used in, and to modify
this material to best suit their instructional needs. Under no
circumstances can copies be made for resale. The Publisher
assumes no responsibility for errors, omissions, or damages,
caused by the use of these programs or from the use of the
information contained herein.
Chapter 6: Schedule Management 50

You might also like