S.

No WORKS TO BE DONE DATE OF


STARTING ENDING
1 Dewatering 09-Jan-11 15-Jan-11
2 Silt Removal 16-Jan-11 16-Feb-11
3 Machinery, Tools & Tackles Mobilisation 09-Jan-11 20-Feb-11
4 Material Mobilisation 09-Jan-11 20-Feb-11
5 Civil Work of Power house from E.L - 283.10 to E.L.295.00 01-Mar-11 30-Jun-11
6 Civil work at Anchor Blocks upto Erection of Penstock Level 01-Mar-11 30-Jun-11
7 Civil works at wier & Head Regulator 15-Oct-11 31-Mar-12
8 Civil work of Power House Superstructure 01-Nov-11 15-Feb-12
9 Penstock Fabrication & Erection 01-Nov-11 31-Mar-12
10 Canal Excavation, Lining & Intake Structure works 01-Nov-11 31-Mar-12
11 Civil work at Anchor Blocks from Erection of Penstock Level 01-Nov-11 31-Mar-12
S.No WORKS TO BE DONE Jan-11 Feb-11 Mar-11
1 Dewatering
2 Silt Removal
3 Machinery, Tools & Tackles Mobilisation
4 Material Mobilisation
5 Civil Work of Power house from E.L - 283.10 to E.L.295.00
6 Civil work at Anchor Blocks upto Erection of Penstock Level
7 Civil works at wier & Head Regulator
8 Civil work of Power House Superstructure
9 Penstock Fabrication & Erection
10 Canal Excavation, Lining & Intake Structure works
11 Civil work at Anchor Blocks from Erection of Penstock Level

Completed
Planned
Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11
Jan-12 Feb-12 Mar-12