Comparison Chart - Diesel vs Gas Turbine Generators

○ Start up within 40 sec △


Item Diesel Generator Set Gas turbine Generator Set
features
Standard

Start up time Start up within 10 sec

△ If uniaxial, 100% output possible. ○


(Impossible to start within 10 sec)
Efficiency 50 to 70%kW out put of rated
capacity possible If biaxial, 70 ~ 100% output is

○ No overload capacity △
possible
Maximum possible 110% load of rated capacity up to

△ Enclosed cabinet type is standard △


output 1 hour is possible
Installation requirements

Indoor outdoor Up to 500kVA class, external


installation installation is possible. However, and can be installed either as
over this size, due to the noise, internal or external.

Roof/basement
an enclosed installation is
Due to heavy vibration and the △ Water cooling is not required, and ○
installation requirement of cooling water, with only slight vibrations,
installation of high roof top is not installation on building roof is
practical. 1fl or basement possible.
installation is common. If installed in the basement,
exhaust piping required is larger

Cold region Insulation to prevent water pipe △ than for a similar size diesel unit.
With no cooling water, support is ○
installation freezing is required. Same for fuel simple. Fuel pipes however need

○ △
oil pipes. insulation to prevent freezing.

○ ○
Fuel

Fuel consumption Fuel consumption 50% Fuel consumption is 100%


Possible fuel types Diesel & "A" type fuel and for Kerosene, Diesel, ship oil, "A"

△ ○
short operating runs type fuel and LNG are all usable
Cooling water Intake/exhaust

Cooling water If radiator cooling is used only top Air cooled system.
consumption up water is required. If cooling No cooling water is necessary.
water is used a large scale water

Cooling water
resevoir is required.
Several major equipments related △ No cooling water ○
○ In comparison to a similar size △
equipment required to the cooling system are facilities/equipment are
Air in take required With the increase in size, the air
intake increases in direct Diesel unit, the amount of air

○ ○
proportion. intake is much smaller.
Ventilation required With the increase in size, the In comparison to a similar size
amount of ventilation increases in Diesel unit, the amount of air

△ △
proportion. intake is much smaller.

△ △
Exhaus Exhaust required Smaller than for the gas turbine

Larger than for the diesel

△ △
t Temperature About 250 About 350
Noise

Generator Open condition Sound insulated cabinet is



Noise level 110 115db(A) @ 1m standard in the package. 85dB(A)
With the installation of sound @ 1m
deadening features a further Possible to lower noise further if

Exhaust noise level


reduction in noise can be
Standard noise reduction 85 ~ △ required.
Standard noise reduction 85 ~ △
90 dB(A) 90 dB(A)
With the installation of sound With the installation of sound
deadening features a further deadening features a further
reduction in noise can be
△ reduction in noise can be

Vibration

Vibration It is reciprocating facility, and big It is rotary machine, and small

○ ○
vibration. vibration.
Vibration prevention With anti-vibration device, turn No vibration absorption is


requirements the vibration down. necessary.
Maintenance/inspection As facilities construction is As facilities construction is
simple, overhaul a machine is complicated, factory rebuilt is
possible at the site. necessary.
Overall rating It is advantage that the body is It is advantageous to install gas
inexpensive than gas turbine, and is turbine on the roof as it does not
easy to reserve water. require cooling water though is costs
more than diesel.