week x x^2

1 38 1444
2 51 2601
To achive desired service level
3 25 625
4 60 3600 Average 42.56667
5 35 1225 sum of x^2 57499
6 42 1764 Std Dev 10.2329
7 29 841 Lead time 20
8 46 2116 For 99% service Level the value of z is 2.33thus
9 55 3025 z 2.33
10 19 361 Safety stock 106.6276 107
11 28 784
12 41 1681 Reorder point 958.3333 959
13 37 1369
14 44 1936
15 45 2025
16 56 3136
17 62 3844
18 53 2809
19 46 2116
20 41 1681
21 52 2704
22 38 1444
23 49 2401
24 46 2116
25 47 2209
26 41 1681
27 39 1521
28 50 2500
29 28 784
30 34 1156
Current servise level

Reorder Point 150


Safety stock -701.3333

this clearly shows that the safety


stocks are not being mantained by
the shop

To calculate optimum order


quantity we need to know Carrying
Cost and ordering cost in addition to
the information provided