Bar Chart Of Jubilee Bridge Crack Repair

Sl. No. 1 2 3 4 5 6 7 8 9 10 11 Job description Mobilisation of machinery / tools & Tackles Arranging the site Removing existing stiffener & castoguna Dressing the damage Surface & providing clamps Marking & drilling the damage area Cutting the marked area by grousing D.P Test, Surface prepearation of Joint Fitting the Vertical & Bottom plate on the pendulum housing Joining the plate by welding. Dressing the Welded Surface Fitting of stiffener & Castoguna.

May-11
25 26 27 28 29 30 31 Done Completed 1 2 3 4 5 6 7 8

Jun-11
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

RIVER SIDE

TRACK SIDE

COMPLETED COMPLETE COMPLETE COMPLETE DONE DONE In Progress