20110707-0308 FERC PDF (Unofficial) 06/27/2011

BOYCE HYDRO POWER, LLC


A if((D. Boyce Trusts Legacy Enterprise Stephen B. Hultberg & Lee yir. Mueller, Co-Member Managers 6000 S. M-30 (P.O.Box 15) Eden ville, Ml 48624

tel:

(989) 689-3161/lax: (989) 689-3155

I'.'HXIYEO
JLIN

June 22, 2011

27')011

+NCAGO

Ms. Peggy A. Harding, PE Regional Engineer Federal Energy Regulatory Commission 230 S. Dearborn St., Suite 3130 Chicago, IL 60604

Re: 2012 and 2013 Schedules P-2785, P-10808, P-10809, P-10810


Dear Ms. Harding:

We are replying to your letter of May 31, 2011 concerning our recently submitted schedules.
Items 1 and items.

2: We

did not receive the April

18, 2011 letter you refer to

in

these two

Item 3, Edenville

- Enclosed please

find our proposed schedule for the Spillway

reconstruction

at Edenville.

Sincerely,

Boyce Hydro Power, LLC P


Frank O. Christie, PE General Manager

cc:

Lee W. Mueller Stephen Hultberg

20110707-0308 FERC PDF (Unofficial) 06/27/2011

BOYCE HYDRO POWER, LLC EDENVILLE/TOBACCO SPILLWAY RECONSTRUCTION WORK PLAN AND SCHEDULE June 22, 2011
YEAR
WORK TASK
Edenville

2013

Construct staging area.

2014

Edenville Lower impoundment, install cofferdam, construct pier extensions, remove cofferdam and raise impoundment. Edenville Install stop logs and reconstruct spillway bay No. 3, including new gate. Remove stop logs. Edenville Install stop logs and reconstruct spillway bay No. 2, including new gate. Remove stop logs. Install stop logs and reconstruct spillway bay No. I, including new gate. Remove stop logs.

2015

2016

2017
2018

Tobacco Construct staging area. Tobacco Lower impoundment,


install cofferdam, construct pier extensions, remove cofferdam and raise impoundment.

2019
2020

Install stop logs and reconstruct spillway bay No. 3, Tobacco including new gate. Remove stop logs.

Install stop logs and reconstruct spillway bay No. 2, Tobacco including new gate. Remove stop logs. Install stop logs and reconstruct spillway bay No. 1, including new gate. Remove stop logs.

Note: The actual start and completion dates each year will vary depending on the weather and the length of time needed for the spring runoff to subside.