CLIENT : TOKYO ROPE MALAYSIA SDN.BHD. PROJECT : SILC PHASE 3 SUBJECT : DAILY REPORT DATE : Friday, July 15, 2011 ITEM 1 COMPANY NAME
MHPT ENGINEERING
Manpower
DATE :
15-Jul-11
WORK DESCRIPTION a) Site coordination, safety briefing and work monitoring. a) Dismantling ceiling at Zone B (GL4-6)
REMARKS
80%
Completed except debris not move out Not complete - backhoe problem
NAKANO CONSTRUCTION
15
b) Hacking wall at existing toilet at Zone A (GL1,A) using backhoe c/w breaker c) Paving with crusher run at MHPT Staff parking area. a) Dismantling air-condintioning diffuser and exhaust grill for Zone D b) Dismantling piping at Zone A
SUNTAC ENGINEERING
14
c) Dismantling ducting at Zone C d) Dismantling outdoor ducting for exhaust duct at GL6a c/w exhaust fan e) Dismantling flexible duct and ducting at Zone B a) Dismantling cable tray at Zone A
JINWELL
b) Dismantling reflected lamp at Zone D c) Dismantling Switch gear and transformer at TNB room b) Dismantling cable tray,conduit and trunking at Zone B
44
11 AM
Fair
12 PM
Fair
1 PM
Fair
2 PM
Fair
3 PM
Fair
4 PM
Fair
5 PM
Fair
6 PM
Fair
7 PM
Fair
HOURS OF RAIN
COMPANY NAME
MHPT ENGINEERING
WORK DESCRIPTION a) Site coordination, safety briefing and supervision of work progress a) Dismantling ceiling at Zone B (GL12-14) b) Paving MHPT staff parking area
REMARKS
NAKANO CONSTRUCTION
12
c) Hacking brickwall at GL1(A-E) d) e) g) a) Dismantling diffuser at Zone D b) Dismantling sprinkler pipe at Zone B
SUNTAC ENGINEERING
Hacking wall at existing toilet at Zone A (GL1,A) using backhoe c/w breaker
Dismantling outdoor ducting for exhaust duct at GL6a c/w exhaust fan