Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

Formula AC

Definition

Actual Cost = CV (CPI - 1)

Formula BAC

Definition

Budget At Completion = (PV) at project completion

Formula Communication Channels

Definition

= (N * (N - 1)) 2 N = Number of Stakeholders

[ Return to Top ]

Formula Cost To Buy

Definition

= Initial Cost + # of Months * Monthly Maintenance Costs

Formula CPI

Definition

Cost Performance Index = EV AC Cost Peformance Index Values > 1 => Good

Formula CV

Definition

Cost Variance = EV - AC Cost Variance Values > 0 => Good

[ Return to Top ]

Formula EAC

Definition

Estimate at Completion = AC + bottom-up ETC = AC % Complete = BAC Cummulative CPI = AC + (BAC - EV) = AC + [(BAC - EV) (Cummulative CPI x Cummultive SPI)]

Formula EMV

Definition

Expected Monetary Value = Impact * Probability

Formula ETC

Definition

Estimate to Complete = EAC - AC

[ Return to Top ]

Formula EV

Definition

Earned Value Budgeted Cost of Work Performed(BCWP) = % complete * BAC = % complete * PV

Formula

Definition

Float

= LS - ES = LF - EF LS = Late Start ES = Early Start LF = Late Finish EF = Early Finish

Formula Normal Distribution

Definition

1 SD = 1 Sigma 1 Sigma = 68.26% 2 Sigma = 95.46% 3 Sigma = 99.73% 6 Sigma = 99.999%

[ Return to Top ]

Formula PERT Analysis

Definition

= (O + 4M + P) 6 O = Optimistic Estimate M = Most Likely Estimate P = Pessimistic Estimate

Formula Present Value

Definition

= FV ((1 + r)^n) FV = Future Value r = Rate of Interest n = number of time periods

Formula PTA

Definition

Point of Total Assumption

= ((Ceiling Price - Target Price) Buyer's Share Ratio) + Target Cost


[ Return to Top ]

Formula PV

Definition

Planned Value = SV (SPI - 1)

Formula ROI

Definition

Return on Investment = Net Benefits Net Cost

Formula SD

Definition

Standard Deviation of the Activity

= (P - O) 6 O = Optimistic Estimate P = Pessimistic Estimate


[ Return to Top ]

Formula SPI

Definition

Schedule Performance Index = EV PV Schedule Performance Index Values > 1 => Good

Formula

Definition

SV

Schedule Variance = EV - PV Schedule Variance Values > 0 => Good

Formula TCPI

Definition

To-complete Cost Performance Index = (BAC - EV) (BAC - AC) = (BAC - EV) (EAC - AC) = Remaining Work Remaining Budget TCPI Values < 1 => Good

[ Return to Top ]

Formula VAC

Definition

Variance at Completion = BAC - EAC

Formula Variance of Activity

Definition

= ((P - O) 6) ^ 2 = (Standard Deviation of the Activity) ^ 2

[ Return to Top ]

You might also like